community liaison group
play

Community Liaison Group 20.10.15 NLE Project Draft timetable Year - PowerPoint PPT Presentation

Northern Line Extension Battersea Community Liaison Group 20.10.15 NLE Project Draft timetable Year Key milestones 2014 Transport and Works Act Order decision, Design & Build contract signed 2015 Agreement on Code of Construction


  1. Northern Line Extension Battersea Community Liaison Group 20.10.15

  2. NLE Project Draft timetable Year Key milestones 2014 Transport and Works Act Order decision, Design & Build contract signed 2015 Agreement on Code of Construction Practice Part B, Start of main works at all sites 2016 Assembly of Tunnel Boring Machines 2017 Completion of tunnelling 2018 Fit out of new stations, Kennington shafts complete inc reinstatement, work at Kennington station complete 2019 Testing, commissioning, trial operations 2020 NLE complete and in service 2

  3. Summary Update June – Sept 2015 • Setting up Conveyor for muck away • Crossover box obstruction removal and piling mat installation • Setting up new office accommodation • Preparation for diaphragm walling activities • Crawler crane arrival • On - going survey and monitoring railway infrastructure 3

  4. Battersea Update June – Sept 2015 4

  5. Look Ahead Oct - Dec 2015 • Continue diaphragm piling • Bentonite Plant / Heavy plant arriving on site • Completion of utilities diversion • New entrance completed. Signalised junction in place • New office cabins fully operative • Barge operations start • On - going pre-construction defect surveys • On-going monitoring installation 5

  6. Conveyor and Barge movement • Installation of footbridge • Existing grade 2 listed bridge removed • Core Hours Loading • During Tunnelling, 24/7 • Two 500t barges = 50 lorries 6

  7. Your Feedback You Suggested We Did Demand on Local transport system from TfL is considering this enquiry construction workers More diligence and coordination for Traffic Bi-weekly open meetings between TfL Management Issues surface, authorities, NLE and community Opportunities for local businesses LEAP group is progressing. Site canteens are run by local businesses Concerns regarding delivery of Contacts added and issue resolved. information to Viridian and Savona Engagement Meetings Flo have had two drop in sessions at Kennington area in September / Cycling event on October 15 with BPSDC Integrated meetings with major NLE and Tideway are joining their CLG developments in the area meetings. BPSDC on same date every 6 months 7

  8. Engagement Opportunities • Drop-In sessions • Cycle Safety Events • Join Traffic Management meetings • Community Liaison Groups • Engagement Sessions 8

  9. Ways to contact us • It is important that calls are logged through the NLE 24/7 helpdesk on 0343 222 2424 • Email nle@tfl.gov.uk • Regular Drop In sessions • Please visit: https://tfl.gov.uk/northern-line-extension 9

  10. Population of London 1860 1860 2 million 2 million 1910 1910 4 million 4 million 2013 8 million Bazalgette design capacity • In 2014, 62 million cubic metres of sewage discharged to the tidal River Thames. • 50 discharges on average in a typical year 3

  11. Thames Tideway Tunnel 4

  12. Tunnel statistics • Length: 25 kilometres • Diameter: 7.2 metres • Gradient: Falls one metre every • Volume: 1.6 million cubic 790 metres to be self-cleansing metres (include Lee Tunnel) 5

  13. 6

  14. Bazalgette Tunnel Limited (BTL) The Infrastructure Provider is made up of the following investors: • Allianz • DIF • Dalmore Capital Limited • Amber Infrastructure Group The investor group includes a significant proportion of UK pension funds through which over 1.7 million UK pensioners will have an indirect investment in Tideway. 7

  15. Main Contractors System East West Central Integrator 8

  16. Kirtling Street Site 9

  17. Kirtling Street - Below Ground 10

  18. Commissioned Works: Kirtling Street Pilot 11

  19. Commissioned Works: Kirtling Street Pilot 12

  20. Kirtling Street Hoardings 13

  21. Up-coming Early Works Activities • 88 KIRTLING STREET: soft strip until end of this year and structural de-commissioning of building from early 2016 • 80 KIRTLING STREET: leased to Met Police for vehicle inspections • 2a Battersea Park Road: with Murphy’s for site set-up and preparations of new TBM sub-station delivery • BROOKS COURT: upcoming fit-out for use as office by FLO 14

  22. 80 Kirtling Street 15

  23. 80 Kirtling Street (Axis security) 16

  24. 2A Battersea Park Road (Murphy’s) 17

  25. Inspire 18

  26. 19

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend