Community Liaison Group 20.10.15 NLE Project Draft timetable Year - - PowerPoint PPT Presentation

Northern Line Extension Battersea Community Liaison Group 20.10.15 NLE Project Draft timetable Year Key milestones 2014 Transport and Works Act Order decision, Design & Build contract signed 2015 Agreement on Code of Construction


slide-1
SLIDE 1

Northern Line Extension Battersea Community Liaison Group 20.10.15

slide-2
SLIDE 2

2

NLE Project Draft timetable

Year Key milestones 2014 Transport and Works Act Order decision, Design & Build contract signed 2015 Agreement on Code of Construction Practice Part B, Start of main works at all sites 2016 Assembly of Tunnel Boring Machines 2017 Completion of tunnelling 2018 Fit out of new stations, Kennington shafts complete inc reinstatement, work at Kennington station complete 2019 Testing, commissioning, trial operations 2020 NLE complete and in service

slide-3
SLIDE 3

3

  • Setting up Conveyor for muck away
  • Crossover box obstruction removal and piling mat installation
  • Setting up new office accommodation
  • Preparation for diaphragm walling activities
  • Crawler crane arrival
  • On - going survey and monitoring railway infrastructure

Summary Update June – Sept 2015

slide-4
SLIDE 4

4

Battersea Update June – Sept 2015

slide-5
SLIDE 5

5

  • Continue diaphragm piling
  • Bentonite Plant / Heavy plant arriving on site
  • Completion of utilities diversion
  • New entrance completed. Signalised junction in place
  • New office cabins fully operative
  • Barge operations start
  • On - going pre-construction defect surveys
  • On-going monitoring installation

Look Ahead Oct - Dec 2015

slide-6
SLIDE 6

6

Conveyor and Barge movement

  • Installation of footbridge
  • Existing grade 2 listed

bridge removed

  • Core Hours Loading
  • During Tunnelling, 24/7
  • Two 500t barges = 50

lorries

slide-7
SLIDE 7

7

Your Feedback

You Suggested We Did

Demand on Local transport system from construction workers TfL is considering this enquiry More diligence and coordination for Traffic Management Issues Bi-weekly open meetings between TfL surface, authorities, NLE and community Opportunities for local businesses LEAP group is progressing. Site canteens are run by local businesses Concerns regarding delivery of information to Viridian and Savona Contacts added and issue resolved. Engagement Meetings Flo have had two drop in sessions at Kennington area in September / Cycling event

  • n October 15 with BPSDC

Integrated meetings with major developments in the area NLE and Tideway are joining their CLG

  • meetings. BPSDC on same date every 6

months

slide-8
SLIDE 8

8

Engagement Opportunities

  • Drop-In sessions
  • Join Traffic Management meetings
  • Cycle Safety Events
  • Community Liaison Groups
  • Engagement Sessions
slide-9
SLIDE 9

9

Ways to contact us

  • It is important that calls are logged through

the NLE 24/7 helpdesk on 0343 222 2424

  • Email nle@tfl.gov.uk
  • Regular Drop In sessions
  • Please visit:

https://tfl.gov.uk/northern-line-extension

slide-10
SLIDE 10

3

2013 8 million

1860 2 million 1860 2 million 1910 4 million 1910 4 million

Population of London

  • In 2014, 62 million cubic metres of sewage discharged to the tidal River Thames.
  • 50 discharges on average in a typical year

Bazalgette design capacity

slide-11
SLIDE 11

4

Thames Tideway Tunnel

slide-12
SLIDE 12

5

Tunnel statistics

  • Length: 25 kilometres
  • Gradient: Falls one metre every

790 metres to be self-cleansing

  • Diameter: 7.2 metres
  • Volume: 1.6 million cubic

metres (include Lee Tunnel)

slide-13
SLIDE 13

6

slide-14
SLIDE 14

7

Bazalgette Tunnel Limited (BTL)

The Infrastructure Provider is made up of the following investors:

  • Allianz
  • DIF
  • Dalmore Capital Limited
  • Amber Infrastructure Group

The investor group includes a significant proportion of UK pension funds through which over 1.7 million UK pensioners will have an indirect investment in Tideway.

slide-15
SLIDE 15

8

Main Contractors West Central East System Integrator

slide-16
SLIDE 16

9

Kirtling Street Site

slide-17
SLIDE 17

10

Kirtling Street - Below Ground

slide-18
SLIDE 18

11

Commissioned Works: Kirtling Street Pilot

slide-19
SLIDE 19

12

Commissioned Works: Kirtling Street Pilot

slide-20
SLIDE 20

13

Kirtling Street Hoardings

slide-21
SLIDE 21

14

Up-coming Early Works Activities

  • 88 KIRTLING STREET: soft strip until end of this year

and structural de-commissioning of building from early 2016

  • 80 KIRTLING STREET: leased to Met Police for vehicle

inspections

  • 2a Battersea Park Road: with Murphy’s for site set-up

and preparations of new TBM sub-station delivery

  • BROOKS COURT: upcoming fit-out for use as office by

FLO

slide-22
SLIDE 22

15

80 Kirtling Street

slide-23
SLIDE 23

16

80 Kirtling Street (Axis security)

slide-24
SLIDE 24

17

2A Battersea Park Road (Murphy’s)

slide-25
SLIDE 25

18

Inspire

slide-26
SLIDE 26

19