Community Liaison Group North Group Meeting 19 March 2020 Construction Update East Zone Maribyrnong River River piling Footscray Road Column installation City Connections Appleton Dock Bored Piling E Gate Site Establishment Launching


slide-1
SLIDE 1

Community Liaison Group

North Group Meeting

19 March 2020

slide-2
SLIDE 2

Construction Update

slide-3
SLIDE 3

East Zone

slide-4
SLIDE 4

Maribyrnong River

River piling

slide-5
SLIDE 5

Footscray Road

Column installation

slide-6
SLIDE 6

City Connections

E Gate Site Establishment Appleton Dock Bored Piling

slide-7
SLIDE 7

Launching Gantry

The launching gantry being assembled on Footscray Road

slide-8
SLIDE 8

TUNNEL ZONE

slide-9
SLIDE 9

North Portal

Wall and corbel construction Maintenance level road deck

slide-10
SLIDE 10

South Portals

Cut and cover works at Outbound TBM retrieval pit

slide-11
SLIDE 11

West Gate Tunnel Project MTIA update

slide-12
SLIDE 12

West Gate Tunnel Neighbourhood funds

  • The inaugural round of the West Gate

Neighbourhood Fund – Partnerships closed on 26 February 2020.

  • A great response was received to the round with

a balance of applications from across both the Hobsons Bay and Maribyrnong Local Government Areas.

  • Applications are currently being assessed, with

input to be sought from CLG members in April.

  • Timing is being considered for the launch of the

West Gate Neighbourhood Fund – Grants.

slide-13
SLIDE 13

West Gate Tunnel Project MTIA update

Brooklyn Open House

  • On Wednesday 11 March, we spoke to 20 Brooklyn residents and businesses at an

‘Open House’ information session.

  • All three parties (WGTP MTIA, Transurban, JV) were present to answer any

questions the local public had.

  • WGTP also held a separate stand representing the West Gate Neighbourhood Fund,

with many locals interested in how the funds will be distributed. Soil Management

  • The project parties are working with the EPA to find a solution to manage the rock and

soil that will be created during tunnelling.

  • Factsheets have been published and sent to CLG members and are available on the

project website.

  • http://westgatetunnelproject.vic.gov.au/construction/soil-management
  • The EPA has published a PFAS factsheet and videos on their website
  • http://epa.vic.gov.au/pfas