a return to fairness in ground risk allocation the new
play

A return to Fairness in Ground Risk Allocation- The New SEMINARIUM - PowerPoint PPT Presentation

A return to Fairness in Ground Risk Allocation- The New SEMINARIUM / SEMINAR SEMINARIUM / SEMINAR FIDIC/ITA Emerald Book. WYZWANIA NOWOCZESNEGO TUNELOWANIA CHALLENGES OF MODERN CHALLENGES OF MODERN Standard Form of Contract for TUNNELLING


  1. A return to Fairness in Ground Risk Allocation- The New SEMINARIUM / SEMINAR SEMINARIUM / SEMINAR FIDIC/ITA Emerald Book. WYZWANIA NOWOCZESNEGO TUNELOWANIA CHALLENGES OF MODERN CHALLENGES OF MODERN Standard Form of Contract for TUNNELLING TUNNELLING Tunnels and Underground Works September, 2019 Andrés Marulanda E. andres@ingetec.com.co

  2. RISKY NATURE OF UNDERGROUND WORKS 1. Subsurface Risks (geotechnical risks) amplified in Tunnels. • Geotechnical uncertainty stems from: • Inadequate knowledge of geological conditions. • Ground response often difficult to predict. • Complex ground-structure interaction. Most structures foundation often main source of uncertainty. In tunnels the • ground is the main construction material. Lineal nature and extent of tunnels makes characterizing the ground costly and • difficult. Most activities in the critical path. Difficult to introduce additional excavation • fronts.

  3. Underground construction projects demand special contractual considerations Difficulty of predicting ground behavior and unforeseen conditions imply an inherit uncertainty for tunneling projects Allocation of underground risks among the stakeholders becomes critical in underground construction NEW FIDIC EMERALD BOOK 3

  4. TG 10

  5. 3. Almost Five Years in the Making! • Started in Geneva. September 2014. • 18 meetings. • Published in Naples May 2019 . 5

  6. SELECTING THE PROCUREMENT STRATEGY FIDIC suit of contracts for procurement alternatives: Traditional Design-Build (Design-Bid-Build, (Engineer-Procure-Construction EPC) DBB) 1. Who develops detail design? 2. Mode of payment to Turnkey Contract: Not the suitable for tunneling Contractor projects=> risk shifted completely to contractor

  7. 4. Ground Related Risk Allocation Under Previous FIDIC Contracts 1. The owner bears the risk of physical conditions which could not have been reasonably foreseeable by an experienced contractor at the date of tender. (clause 4.12). 2. Owner required to provide all relevant data it has on subsurface conditions. 3. Contractor obliged to inspect site and procure necessary info that might affect works (clause 4.10). 4. Red and yellow books allow for time extension and additional costs if physical conditions are not reasonably foreseeable. 5. Risk distribution philosophy=> employer owns ground risk. 6. Practical difficulty interpreting boundary of ground risk allocation and establishing what is “reasonably foreseeable”. Also no clear definition of how to recognize extra cost and time. 7. This often leads to claims and disputes. 7

  8. 5. Based on Yellow Book 2017 Version

  9. 6. Background principles Emerald Book Ø Fair Allocation of risk • The ground and groundwater related risks should be assigned to the owner; • The performance related risk for the expected ground conditions should be assigned to the Contractor. Ø Inclusion of a contractual geotechnical baseline • Sets the contractual limits of the conditions anticipated to be encountered during construction. Ø Disclosure of all available information • Geological and Geotechnical information should be shared during the tendering stage. 9

  10. 6. Background principles • Inclusion of a contractual unforeseeable physical conditions clause. • Implementation of a ground classification system that properly reflect the effort for excavation and stabilization. • Time adjustment according to ground conditions should be regulated by the contract. • A flexible mechanism for remuneration according to ground conditions, foreseen and unforeseen, should be implemented. 10

  11. 6. Background principles Ø Strengthening of the position, authority and requirements of the Engineer . Both the Employer and the Contractor need an experienced and capable Engineer to ensure a correct application of the Contract, provide registrations and make the necessary determinations in due time. Ø Management of the project-related risks through effective tools. Ø Alternative Dispute Avoidance and Resolution . Conventional methods of dispute resolution (through arbitration tribunals and courts) do not satisfy the need of timely adjudication. Standing Dispute Avoidance and Adjudication Boards have proved to be useful to all parties and to the projects. 11

  12. 6. Setting the Baseline To set the allocation of subsurface risk in the contract documents, a Geotechnical Baseline Report (GBR) is used: • GBR must be a part of the contract. • GBR shall contain the Employer’s proposal for excavation and lining works methods. • Anticipated quantities of Excavation and Lining in the GBR shall be itemized in one or more Baseline Schedules. 12

  13. 7. Geotechnical Baseline Report Ø The Geotechnical Baseline Report describes the subsurface physical conditions to serve as a basis for the execution of the Excavation and Lining Works, including design and construction methods, and the reaction of the ground to such methods. Ø The GBR sets out the allocation of the risk between the Parties for subsurface physical conditions. Ø The Geotechnical Baseline Report (GBR) single source contractual document that describes the anticipated subsurface conditions to be encountered during the execution of the Works. Ø The Contractor shall be entitled to rely on the anticipated sub-surface conditions set out in the Geotechnical Baseline Report 13

  14. 7. Geotechnical Baseline Report Ø Only contractual definition of the foreseeable subsurface physical conditions for the Underground Works and serves as the basis for the preparation of the Tender and execution of the Works. Ø The GBR also serves to convey and highlight the key project constraints and requirements, to enable the tenderers to grasp key project issues. Ø What is in the GBR is foreseen Ø Anticipated quantities of Excavation and Lining in the GBR Ø What is not in the GBR is shall be itemized in one or more Baseline Schedules. unforeseen 14

  15. 8. Setting the baseline • The Schedule of Baselines sets out the anticipated activities or items of work for the Excavation and Lining Works and their corresponding quantities consistent with the conditions described in the GBR • The production rates or durations entered by the Contractor against each activity or item of work are deemed to allow for the time the Contractor requires to complete that activity or item of work • The contractual time and cost for Excavation shall be adjusted according to the amounts and production rates stated in the Baseline Schedules. 15

  16. 9. Cost structure to facilitate remeasurement • Cost items associated with ground conditions , such as the underground excavation, support and lining should be regularly remeasured depending on the actual conditions encountered in comparison to the anticipated ones in the GBR. • All other works shall be handled in the lump sum component of the contract price. • Major portion of costs incurred by Contractors relates to time rather than quantities produced. The Contract documents shall consequently provide for time-related items which allow for corresponding adjustments in the Contract Price according to the adjustments in Time for Completion 16

  17. 10. Adjustment of time for completion RISK RISK Sub-surface Production physical Employer Contractor rates conditions • The time available to the Contractor for the Underground Excavation and Lining stages shall be f( D Expected sub-surface physical conditions expected (quantified in the Baseline Schedule) Vs subsurface physical conditions actually encountered) • No adjustment shall be provided for any difference between production rates stated in Contractor’s proposal and actually achieved, for the specified set of sub-surface physical conditions. 17

  18. 11. Adjustment of Time in Practice • Consider a 1000m long tunnel with the following characteristics: Characteristic Section A Section B Length [m] 500 500 Advance rate [m/day] 10 1 Time for completion [days] 50 500 • Total time for completion = 550 days Figure 1 – Base Scenario. Bid with Ground Conditions as per anticipated in the GBR. 18

  19. 11. Adjustment of Time in Practice • Scenario 1 - Encountered conditions are better than foreseen in the Baseline Schedule: • Reduce Time for Completion. • More favorable conditions allow the Contractor to advance according to his proposed rate for better ground. • Encountered length: • Section A = 600m • Section B = 400m • Total time for completion = 460 days Figure 2 – Scenario 1. Encountered ground conditions better than anticipated. 19

  20. 11. Adjustment of Time in Practice • Scenario 2a - Encountered conditions are worse than foreseen in the Baseline Schedule: • Extend Time for Completion. • Contractor should be compensated in time and cost. • Encountered length: • Section A = 400m • Section B = 600m • Total time for completion = 660 days. Figure 3 – Scenario 2a. Encountered ground conditions worse than anticipated. 20

  21. 11. Adjustment of Time in Practice • Scenario 2b - Encountered conditions are worse than foreseen in the Baseline Schedule but the Contractor performed with faster advance rates than offered: • Contractor would perceive a gain. • Employer should recognize the extra cost and time. Figure 3 – Scenario 2b. Encountered ground conditions worse than anticipated, but contractor advances with higher rates. 21

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend