SINGAPORE POWER CABLE TUNNEL PROJECT ABSIS (ACTIVITY BASED SAFETY IMPROVEMENT SYSTEM) Speaker: Edward Raj Deputy Director Group Safety and Health, Singapore Power ABSIS – Edward Raj Singapore – 11 November 2016
Stakeholders Singapore Power WorleyParsons AECOM Mott MacDonald Obayashi Corporation SK E&C Nishimatsu Construction Co. Ltd & KTCCE JV Samsung C&T Corporation Hyundai E&C ABSIS – Edward Raj Singapore – 11 November 2016
SINGAPORE POWER CABLE TUNNEL PROJECT • Project Value of S$2.8 Billion • Deepest , Tightest and Longest tunnels in Singapore • 24/7 operations • Average of 3500 workers per day • 7 main contracts • 21 active work sites • 40 km of tunnel construction • 16 TBMs underground ABSIS – Edward Raj Singapore – 11 November 2016
SINGAPORE POWER CABLE TUNNEL PROJECT A CTIVITY B ASED S AFETY I MPROVEMENT S YSTEM ABSIS – Edward Raj Singapore – 11 November 2016
SINGAPORE POWER CABLE TUNNEL PROJECT ABSIS focuses on safe work methods of various critical activities in tunnel construction Video - Capturing critical work activities while workers are performing the task Write up - Step by step identification of hazards and appropriate safety measures ABSIS – Edward Raj Singapore – 11 November 2016
ABSIS Video of an activity will be captured *Component 1: Video recorded will be reviewed *Component 2: Hazards identified in various sub-activities Component 1: VIDEO of the video will be documented Analysed and discussed with Project Managers, Safety Managers and Supervisory Staff Shared with workers Component 2: Write Up Presented in weekly progress meeting & monitored by SPPG ABSIS – Edward Raj Singapore – 11 November 2016
ABSIS ABSIS – Edward Raj Singapore – 11 November 2016
SINGAPORE POWER CABLE TUNNEL PROJECT EXAMPLES OF IMPLEMENTATION FROM ABSIS ABSIS – Edward Raj Singapore – 11 November 2016
VEHICLE PARKING & ACCESS MATERIAL HANDLING Before Workers using hands to handle load whilst lowering segments After Segment holder was used to handle load without pinch point hazards ABSIS – Edward Raj Singapore – 11 November 2016
LIFTING OPERATION ABSIS – Edward Raj Singapore – 11 November 2016
CONCURRENT OPERATION ABSIS – Edward Raj Singapore – 11 November 2016
EXCAVATOR OPERATION LOCOMOTIVE OPERATION Guide rail for M&E platform (Fixed Distance) ABSIS – Edward Raj Singapore – 11 November 2016
ABSIS Further improvement to enhance the ABSIS implementation. Workers watching ABSIS video when resting in the canteen Workers watching ABSIS video when traveling in the lift ABSIS – Edward Raj Singapore – 11 November 2016
SINGAPORE POWER CABLE TUNNEL PROJECT ACHIEVEMENT ABSIS – Edward Raj Singapore – 11 November 2016
ACHIEVEMENT In FY 15/16, target was 0.88 We achieved LTIFR of 0.55 ABSIS – Edward Raj Singapore – 11 November 2016
Sharing Cable Tunnel Safety Initiatives at TUCSS - Symposium on Innovation & Challenges Won the ROSPA (The Royal Society for the in Asian Tunnelling 2015 Prevention of Accidents) award Won the Best Safety Practice at Singapore Power Sharing at PUB’s Construction Safety Seminar Group Safety Summit ABSIS – Edward Raj Singapore – 11 November 2016
CONCLUSION • Workers learn their mistakes and safety lapses from the playback of the video • Change workers’ behaviour and enhance their safety awareness • Overcome language barriers in workers • Ease of implementation • Raise construction safety standard and quality ABSIS is the first of its kind in the tunnelling industry ABSIS – Edward Raj Singapore – 11 November 2016
SINGAPORE POWER CABLE TUNNEL PROJECT THANK YOU ABSIS – Edward Raj Singapore – 11 November 2016