Industry Briefing | 29 November 2016 Agenda Project Overview - - PowerPoint PPT Presentation

industry briefing 29 november 2016 agenda
SMART_READER_LITE
LIVE PREVIEW

Industry Briefing | 29 November 2016 Agenda Project Overview - - PowerPoint PPT Presentation

Industry Briefing | 29 November 2016 Agenda Project Overview Target Programme Designation and resource consent conditions Ground investigations Mana Whenua Design Status Tunnels Stations


slide-1
SLIDE 1

Industry Briefing | 29 November 2016

slide-2
SLIDE 2
  • Project Overview
  • Target Programme
  • Designation and resource consent conditions
  • Ground investigations
  • Mana Whenua
  • Design Status
  • Tunnels
  • Stations
  • Sustainability
  • Design Management and Interfaces
  • Questions - followed by afternoon tea

Agenda

slide-3
SLIDE 3

Planned Outcomes

A safe reliable and attractive railway

  • 24 trains per hour in each direction ultimate track capacity
  • 18,000 passengers per hour in each direction as the ultimate

patronage capacity through two new stations and two modified stations

  • Future proofing oversite development opportunities at each

station

  • Sustainability IS project target rating 'excellent'
  • Operating in 2023/24
slide-4
SLIDE 4

Route Context

slide-5
SLIDE 5

Climbing the Hill

slide-6
SLIDE 6

Designation Boundaries

slide-7
SLIDE 7

Contract Split

slide-8
SLIDE 8

C3/C7 Interface

  • Trackwork
  • Signalling
  • Overhead line
  • Communications
  • Fire engineering
  • Tunnel ventilation
  • Controls
  • Integration
  • Testing
  • Commissioning
slide-9
SLIDE 9

Procurement Programme

slide-10
SLIDE 10
  • C1,C2, DSC complete in 2019
  • C3 2019-2023/24
  • C5 2019-2022
  • C6 2018-2019
  • C7 2019-2023/24
  • C8 TBA
  • C9 2023/24

Target Construction Programme

slide-11
SLIDE 11
  • Surface and subsurface designations
  • 3 resource consent packages
  • Noise and vibration
  • Traffic impacts
  • Business disruption
  • Settlement impacts

Designation and Resource Consent Conditions

slide-12
SLIDE 12

Ground Investigations

  • Approx. 130 BHs and CPTs carried
  • ut (excluding non-CRL BHs)
  • Extensive network of groundwater

monitoring installations and core sample storage

  • Geotechnical Baseline Report

(GBR) and Geotechnical Data Report (GDR) will be available to tenderers

slide-13
SLIDE 13

Geotechnical Longsection

slide-14
SLIDE 14

Mt Eden Geology

slide-15
SLIDE 15

Utilities Investigations

  • Utility surveys undertaken in Albert Street and Beresford Square
  • Further utility potholing to be carried out in open cut sections
  • Anticipated completion end of 1st quarter 2017
  • Potential early utilities diversions and/or removal of canopies
slide-16
SLIDE 16

CRL's Mana Whenua forum

The eight Mana Whenua who self-identified their interest in CRL, and who are part of the forum :

  • Ngāi Tai Ki Tāmaki
  • Ngāti Maru
  • Ngāti Paoa
  • Ngāti Tamaoho
  • Ngāti Te Ata Waiohua
  • Ngāti Whātua o Ōrākei
  • Te Ᾱkitai Waiohua
  • Te Kawerau a Maki
slide-17
SLIDE 17

Cultural Narratives

Illustration Aotea station - indicative expression of narratives

slide-18
SLIDE 18

Mandated Design

slide-19
SLIDE 19

STEPS Modelling

slide-20
SLIDE 20

Design Document Structure

slide-21
SLIDE 21

BIM Model

slide-22
SLIDE 22

Tunnels

Mined Tunnels Cut and Cover Tunnels Bored Tunnels

slide-23
SLIDE 23

Tunnels & Alignment

slide-24
SLIDE 24

Tunnels & Alignment - Aotea to Karangahape

slide-25
SLIDE 25

Tunnels & Alignment Newton Junction

N

slide-26
SLIDE 26

Tunnels & Alignment - East Connection

slide-27
SLIDE 27

Tunnels & Alignment - West Connection

slide-28
SLIDE 28

C1 and C2

N

slide-29
SLIDE 29
  • Modification of existing platforms, tracks and signals
  • Addition and alteration works of operation support entities i.e.
  • ffices, gates, stairs etc

C9 Britomart East

slide-30
SLIDE 30

Stations - Aotea

N

slide-31
SLIDE 31

Aotea Station - Existing Structures

Bluestone Wall Crown Plaza Deck Public Trust Building Verandahs

slide-32
SLIDE 32

Aotea Station - Utilities & Stormwater Diversion

  • Albert Street stormwater pipe jack
  • Orakei Main Sewer
  • Existing subsurface utilities to be

diverted/protected

slide-33
SLIDE 33

Aotea Station - Connection to Structure

  • Connect to C2 cut and cover

tunnel south of Wyndham Street

  • C2 expected completion 3rd

quarter 2019

  • Potential future integration with

NDG’s development at Albert Street/Victoria Street junction

  • Potential future connection to

SkyCity

slide-34
SLIDE 34

Aotea Station Construction Site - Bledisloe Carpark

  • Available as site support area

during construction

  • Carpark side entrance along

Wellesley to be maintained

slide-35
SLIDE 35

Aotea Station Geology

slide-36
SLIDE 36

Aotea Station - Plan (North)

slide-37
SLIDE 37

Aotea Station - Plan (Middle)

slide-38
SLIDE 38

Aotea Station - Plan (South)

slide-39
SLIDE 39

Aotea Station - Typical Section (North)

slide-40
SLIDE 40

Aotea Station - Typical Section (South)

slide-41
SLIDE 41

Aotea Station

slide-42
SLIDE 42

Architecture

slide-43
SLIDE 43

Stations - Aotea

slide-44
SLIDE 44

Aotea Station - Future Oversite Development

  • Feasibility and space proofing

carried out

  • Resource Consent granted
  • Structural enabling works within

station structure

slide-45
SLIDE 45

Virtual Station Tour

slide-46
SLIDE 46

Karangahape Station Location Plan

N

slide-47
SLIDE 47

Karangahape Station - General Arrangement

slide-48
SLIDE 48
  • Beresford Square
  • Current carpark area

Karangahape Station - Construction Support Area

slide-49
SLIDE 49
  • Mercury Plaza site
  • Available as construction

support area

  • Building possibly demolished

as advanced work

Karangahape Station - Construction Support Area

slide-50
SLIDE 50

Karangahape Station - Geology

slide-51
SLIDE 51

Karangahape Station - Existing Structures

Beresford Square Mercury Theatre (Former) George Courts Building Methodist Church

N

slide-52
SLIDE 52

Existing Structures - Verandahs

  • Existing verandahs may obstruct

construction of station

  • Potentially advanced work
  • Verandahs to be removed and reinstated/

replaced

slide-53
SLIDE 53

Stations - Karangahape

slide-54
SLIDE 54

Stations - Karangahape

slide-55
SLIDE 55

Stations - Karangahape

slide-56
SLIDE 56

Stations - Karangahape

slide-57
SLIDE 57

Mt Eden Plan

slide-58
SLIDE 58

Structures - Cross Over Shaft

slide-59
SLIDE 59

C6 Mt Eden Stormwater Diversion

  • Diversion of 1950mm SW

pipe

  • 3 shaft locations
  • Approximately 450m

length

  • Pipe jack launch at Mt

Eden Rd shaft

  • Tunnelling largely below

basalt layer

slide-60
SLIDE 60

Structures - Station Box

N

slide-61
SLIDE 61

Construction Sites

Mt Eden

slide-62
SLIDE 62

Geology

slide-63
SLIDE 63

Stations - Mt Eden

slide-64
SLIDE 64

Pedestrian Bridges - Western Line

slide-65
SLIDE 65

Perspective of Normanby Road

slide-66
SLIDE 66
  • Western Line Metro and freight services maintained
  • Limited full blocks of line
  • Staged testing and commissioning
  • Civil, structural, trackwork, railway systems scope

Western Line

slide-67
SLIDE 67
  • Decision making that considers social, environmental

and cultural impacts, risks and opportunities

  • Truly integrated design
  • Understanding and considering whole of life costs
  • Collaboration around interfaces

Delivering CRL Sustainably

slide-68
SLIDE 68
  • Reducing resource consumption - measuring CRL’s carbon footprint
  • energy, water, materials
  • Zero waste to landfill - aspirational goal
  • designing out waste
  • avoiding construction waste
  • Social outcomes
  • workforce development, employment, social enterprises
  • Mana Whenua outcomes - kaitiakitanga
  • Reporting - qualitative and quantitative

Focus areas

slide-69
SLIDE 69

Comparing three options for constructing 200m long, 7-9m deep platform trench

Carbon footprint

slide-70
SLIDE 70
  • 'Excellent' Design and As-built rating

for whole project

  • Each contract package will be

contributing their own rating

  • C1, C2, C3, C5, C7 and C9
  • (not C6 and C8)
  • New Zealand pilot - CRL version:
  • NZ criteria
  • incorporates Mana Whenua cultural

values

Infrastructure Sustainably

Infrastructure Sustainability Council of Australia

slide-71
SLIDE 71

Kaitiakitanga includes:

  • protecting, restoring, enhancing the mauri of te Ao Māori;
  • fulfilling spiritual, emotional and inherited responsibilities to

the environment;

  • maintaining mana over te taiao; and
  • ensuring the welfare of the people.

In Tamaki Makaurau it is Mana Whenua who are Kaitiaki. In meeting their sustainability commitments the CRL project is supporting kaitiakitanga and Mana Whenua as kaitiaki.

Kaitiakitanga, Sustainability & CRL

slide-72
SLIDE 72

Social Outcomes for Auckland

  • There are eight local boards with higher than

average numbers of people Not in Employment Education or Training (NEET)

  • There is a significant skills shortage in

construction and infrastructure

  • Creating positive social value through the

delivery of CRL

slide-73
SLIDE 73

Journey so far

Contracts 1 & 2

slide-74
SLIDE 74

Work undertaken:

  • Materiality assessment for the scope of each contract package
  • Reference design level footprints
  • for operations only
  • Principal’s evidence

Infrastructure Sustainably

slide-75
SLIDE 75
slide-76
SLIDE 76

Process

  • Particular requirements
  • Planning conditions
  • Mandated design elements
  • Interface management and control
  • DOORS Database
  • Multi-discipline Gateway Reviews
  • Systems Assurance

Design Management

slide-77
SLIDE 77
  • Progressive information co-ordination and delivery
  • Intermediate gate in interactive pre-award period
  • Gates through detailed design
  • Final gate at completion of detail design
  • On line real time demonstration of the co-ordinated information

delivery and compliance with requirements

Gateway Reviews

slide-78
SLIDE 78
  • Interface boundary mapping and ownership- DOORS
  • C3-C6, C3-C2, C3-C7, C3-C5, C3-C9
  • C7-C1, C7-C2, C7-C3, C7-C5, C7-C9
  • Interface control documents
  • Geographical co-ordination
  • Cross boundary co-ordination
  • Collaborative development - cross contract resolution
  • Collective responsibility

Interfaces

slide-79
SLIDE 79
  • Fully co-ordinated 3D model required
  • Single source of truth required throughout delivery
  • Cross contract co-ordination into one federated model generation
  • BIM 200 at start, BIM 400 on completion of the works

BIM

slide-80
SLIDE 80
  • Not to hurt anybody
  • Maintain design quality and cultural narratives
  • Improve delivery programme - working smarter
  • 20% cost reduction
  • Meeting all RMA designation conditions
  • Key specialist resources in place at start of contract and

maintained through delivery

  • Draft OPW’s in place prior to contract award and lodge within four

weeks of award

  • Exceed sustainability targets to ‘leading’ status
  • To leave behind a more skilled workforce

The Challenge

slide-81
SLIDE 81
  • For Procurement questions please email

CRLProcurement@at.govt.nz

Technical Questions

slide-82
SLIDE 82

Thank you.

slide-83
SLIDE 83

The Project Route