Community Liaison Group Joint Group Meeting 20 February 2020 # - PowerPoint PPT Presentation

Community Liaison Group Joint Group Meeting 20 February 2020 # Item Detail Welcome, introductions, apologies & safety briefing 1 5.30pm Maribyrnong River site walk 2 5.45pm Questions and discussion from members 3 6.15pm Actions


  1. Community Liaison Group Joint Group Meeting 20 February 2020

  2. # Item Detail Welcome, introductions, apologies & safety briefing 1 5.30pm Maribyrnong River site walk 2 5.45pm Questions and discussion from members 3 6.15pm Actions update 4 6.35pm Tea Break 5 6.50pm Construction update 6 7.00pm West Gate Project MTIA update 7 7.20pm Actions arising and close 8 7.30pm

  3. Introduction Jim Williamson

  4. Maribyrnong River site walk – East Zone Alan Platt

  5. East Zone update Update provided onsite, including: • Maribyrnong River piling and bridge works • Footscray Road piling and launching gantry construction • City connections piling

  6. Report from CLG community members

  7. Actions from previous meetings

  8. Tea break

  9. West Zone Charles Fairbairn

  10. Noise Walls Noise walls being installed along the Model representation of completed West Gate freeway noise walls

  11. Hyde Street Ramps Arial view of Hyde Street Stony Creek earthworks in preparation for temporary access Ramps track

  12. Fogarty Avenue Drainage Preparing for trenching works

  13. Millers Road Millers Road outbound entry ramp Millers Road bridge works

  14. M80 Preparatory works for M80 Top-down bridge beam lift ramps

  15. Tunnel Zone David Hake

  16. North Portal Wall and corbel Maintenance level road deck construction

  17. South Portals Cut and cover works at TBM retrieval pit

  18. Questions and discussion from CLG members on upcoming works

  19. West Gate Tunnel Project MTIA update Liz Evans

  20. West Gate Neighbourhood Fund • Partnerships ($100k+ applications) round 1 closes for applications on 26 February, with Grants (up to $100k) round 1 to open for applications in early March • Community representatives, groups, and associations within each CLG will be invited to participate in the review of shortlisted Partnerships applications • Participating CLG members will be provided a summary of shortlisted Partnerships applications and a review form in mid- April • A meeting will be scheduled for late April in order to discuss and collate CLG feedback on the Partnerships applications • Feedback received from the CLG members will be used to inform the final assessment of applications

  21. Actions arising and close

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.