Public Works Delivery Methods and Use at Sound Transit
12/12/19
Public Works Delivery Methods and Use at Sound Transit 12/12/19 - - PowerPoint PPT Presentation
Public Works Delivery Methods and Use at Sound Transit 12/12/19 Why We Are Here Review public works delivery methods and use at Sound Transit Share how Sound Transit selects the appropriate delivery method Discuss Sound Transits
12/12/19
2
3
DESIGNER
DESIGN SUBCONSULTANTS SPECIALTY TRADES
GENERAL CONTRACTOR
4
Planning & Programing
Final Design Construction Designer Selected Contractor Selected Cost Established Delivery Method Selected
5
DESIGNER
DESIGN SUBCONSULTANTS SPECIALTY TRADES GENERAL CONTRACTOR / CONSTRUCTION MANAGER
6
Planning & Programing
Final Design Construction Construction Cost Established Contractor Selected Designer Selected Delivery Method Selected
7
DESIGN BUILDER
DESIGN SUBCONSULTANTS SPECIALTY TRADES
8
Planning & Programing
Final Design & Construction
Cost Established Design Builder Selected Delivery Method Selected
9
year term
10
commitments
10
11
12
Selection - Contractor input is essential during design phase Preconstruction
Contractor/Construction Manager and Designer
Construction
Examples - East Link Extension - International District Station to South Bellevue Segment (E130), Northgate Link Extension - Systems (N830)
13
Important Considerations
expectations around permits
and certification
arrangements
Examples - East Link Extension - Bellevue to Redmond Technology Station Segment (E360), Federal Way Link Extension