public works delivery methods
play

Public Works Delivery Methods and Use at Sound Transit 12/12/19 - PowerPoint PPT Presentation

Public Works Delivery Methods and Use at Sound Transit 12/12/19 Why We Are Here Review public works delivery methods and use at Sound Transit Share how Sound Transit selects the appropriate delivery method Discuss Sound Transits


  1. Public Works Delivery Methods and Use at Sound Transit 12/12/19

  2. Why We Are Here • Review public works delivery methods and use at Sound Transit • Share how Sound Transit selects the appropriate delivery method • Discuss Sound Transit’s experience using the delivery methods • Today we are here to provide a briefing 2

  3. Design-Bid-Build Structure OWNER • 1 Design Contract • 1 Construction Contract GENERAL • No Relationship DESIGNER CONTRACTOR Between Designer and Contractor DESIGN SPECIALTY SUBCONSULTANTS TRADES 3

  4. Design-Bid-Build Profile • Linear Process • Owner Controls Design • Owner Responsible for Design Risk • Owner Makes All Decisions Designer Selected Contractor Selected Planning & Final Design Construction Programing Delivery Method Cost Established Selected 4

  5. General Contractor/Construction Manager Structure • 1 Design Contract OWNER • 2 Construction Contracts • Preconstruction (During Design) GENERAL • Construction CONTRACTOR / DESIGNER CONSTRUCTION MANAGER • Indirect Relationship Between Designer and DESIGN SPECIALTY Contractor SUBCONSULTANTS TRADES 5

  6. General Contractor/Construction Manager Profile • Contractor Input During Design • Potential for Reducing Project Risks • Owner Controls Design and Owns Design Risk • Owner Makes All Decisions • Negotiated Contract (Not to Exceed Amount) Designer Selected Construction Cost Established Planning & Final Design Programing Construction Delivery Contractor Method Selected Selected 6

  7. Design Build Structure OWNER • 1 Design and Construction Contract DESIGN BUILDER • One Team Responsible for all Design and Construction DESIGN SPECIALTY SUBCONSULTANTS TRADES 7

  8. Design Build Profile • Managing to Project Performance • Integrated Process • Design Builder Owns Design Risk • Owner & Design Builder Design Collaboration • Build During Design Design Builder Selected Planning & Final Design & Construction Programing Delivery Cost Established Method Selected 8

  9. Delivery Selection Authority Public Bodies must obtain approval through State’s Project Review Committee (PRC) Two Ways to Gain PRC Approval • Individual Project/Contract Approval • Public Body Certification for Design Build and/or GCCM for a 3- year term 9

  10. Main Drivers for Delivery Method Selection • Schedule • Type of work • Community, permit and/or jurisdictional commitments • Opportunity for creativity • Team • Jurisdictional relationship and capacity • Current market conditions and capacity • Design complexity 10 10

  11. Design-Bid-Build in Practice The traditional approach • Commitments often control design • Schedule affords linear process, where contractor is selected after the design is complete • Better entry opportunity for new contractors • Price is everything Examples • East Link Extension - South Bellevue Segment (E320) • Northgate Link Extension - Northgate Tunnel (N125) 11

  12. GC/CM in Practice Selection - Contractor input is essential during design phase Preconstruction • Develop intentional and purposeful relationship between General Contractor/Construction Manager and Designer • Be receptive to contractor feedback on design • Optimize framework for continuous schedule and cost feedback • Advance conversations around trade packaging strategy early • Negotiation strategy Construction • Alignment with contractor on changes. Examples - East Link Extension - International District Station to South Bellevue Segment (E130), Northgate Link Extension - Systems (N830) 12

  13. Design Build in Practice Important Considerations • Alignment of owner and AHJ on design development – clear expectations around permits • Owner benefit from design builder means and methods • Threshold for quantity of prescriptive elements • Realistic assessment of contractor role in quality, commissioning and certification • Availability of designers and contractors; risk tolerance for new arrangements • Extract Value from Procurement Examples - East Link Extension - Bellevue to Redmond Technology Station Segment (E360), Federal Way Link Extension 13

  14. Thank you. soundtransit.org

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend