Community Consultative Committee February 2019 Agenda item 3 - - PowerPoint PPT Presentation

community consultative committee february 2019 agenda
SMART_READER_LITE
LIVE PREVIEW

Community Consultative Committee February 2019 Agenda item 3 - - PowerPoint PPT Presentation

Community Consultative Committee February 2019 Agenda item 3 Correspondence (August, Sept, Oct, Nov, Dec 2018 and Jan 2019) - Department of Planning and Environment Site inspection held Friday 1 st February 2019 regarding Modification 5 -


slide-1
SLIDE 1

Community Consultative Committee February 2019

slide-2
SLIDE 2

2

Agenda item 3 – Correspondence (August, Sept, Oct, Nov, Dec 2018 and Jan 2019)

  • Department of Planning and Environment
  • Site inspection held Friday 1st February 2019 regarding Modification 5
  • Supplementary information supplied to Department with more required by end of February
  • EPA
  • Site inspection November 2018
  • Discussion re Modification 5 Noise conditions
  • Environment Protection Licence Annual return
  • NSW Water
  • Site inspection November 2018
  • G Clark
  • weather data reviews – weather station monthly reviews (July, August, Sept, Oct, Nov, Dec 2018)
slide-3
SLIDE 3

3

Agenda item 4 – Operations

  • Safety
  • Achieved zero LTI’s since last CCC (August 2018)
  • Overburden
  • Overburden works continue with the development of the southern overburden and associated storm

water controls

  • Tree planting, top-soiling and hydro-mulching of these areas has commenced
  • Pit update
  • Mine plan remains a consistent Easterly direction with additional load and haul of rock from top bench

as part of the overburden works

  • Processing
  • A new excavator (150t CAT) has helped increase uptime through our primary plant
  • Continuous improvement works have helped deliver a daily record production volume just this week
  • With improved plant uptime and throughput rates we have now brought in an additional train
  • Currently in the process of building a store for parts to reduce reliance on shipping containers
  • People
  • We have recently advertised for 8 new operator roles.
  • Majority of these roles have been filled. This now takes the site to 53 full time employees.
slide-4
SLIDE 4

4

Agenda item 5 – OH&S Performance

  • No loss time injuries
  • DPI audit on Working at Heights
  • No major issues identified
  • Finalist for the 2018 National IQA safety awards but unsuccessful
  • Hearing tests performed on all Peppertree quarry staff as part of bi annual checks
  • Personal dust monitoring undertaken as part of annual testing
  • Health Control plan developed to assess range of risks to ensure controls are in

place

slide-5
SLIDE 5

5

Agenda Item 6 - Environmental Performance Incidents

August 2018 - 3 (2 spills / 1 sewerage) November 2018 - 1 (dust) September 2018 - 3 ( 2 spills / 1 wombat) December 2018 - 7 ( 4 spills, 3 erosion) October 2018 - 1 (potential erosion) January 2019 - (1 spill)

slide-6
SLIDE 6

6

Agenda item 6 – Environmental Performance Complaints

slide-7
SLIDE 7

7

Agenda item 6 – Environmental Performance Air

Annual Average goal of 4gm2/month not in compliance at the site however majority of insoluble solid is organic Annual average would be below goal at the boundary Report received advising relocation of the bottle to the boundary

slide-8
SLIDE 8

8

Agenda item 6 – Environmental Performance Air

Annual Average goal of 4gm2/month In compliance – 3.89

slide-9
SLIDE 9

9

Agenda item 6 – Environmental Performance Air

Annual Average goal of 4gm2/month In compliance However Bottle continues to have a high organic content. Report has been received advising relocation of bottle.

slide-10
SLIDE 10

10

Agenda item 6 – Environmental Performance Air – Particulate Matter <10 microns – annual average

In compliance with the annual average goal Gap in data due to failure of the sampler to operate – additional samples have been run

slide-11
SLIDE 11

11

Agenda item 6 – Environmental Performance Air – Particulate Matter <10 microns – 24 hour criteria

August, September, October, November, December 2018 in compliance Note criteria is at the nearest residence and not the HVAS.

slide-12
SLIDE 12

12

Agenda item 6 – Environmental Performance Air - Total Suspended Particulates

TSP below Annual average goal

slide-13
SLIDE 13

13

Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring October (November) 2018 daytime

All in compliance

Receiver Date Site Noise Level Contribution Operational Criteria (dB(A)) EPL ID LAeq, 15 minute (dB(A)) daytime R17 27/11/18 22 35 R2 27/11/18 32 35 R3 27/11/18 19 35 R4 27/11/18 33 35 R8 27/11/18 35 41 R17 29/11/18 26 35 R17 29/11/18 24 35 R3 29/11/18 31 35 R3 29/11/18 31 35 R2 29/11/18 27 35 R2 29/11/18 26 35 R8 29/11/18 33 41 R8 29/11/18 29 41 R4 29/11/18 31 35 R4 29/11/18 33 35

slide-14
SLIDE 14

14

Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring October (November) 2018– evening

All in compliance

Receiver Date Site Noise Level Contribution Operational Criteria (dB(A)) EPL ID LAeq, 15 minute (dB(A)) Night time R3 29/11/18 30 35 R2 29/11/18 32 35 R8 29/11/18 25 41 R4 29/11/18 33 35 R17 29/11/18 21 35

slide-15
SLIDE 15

15

Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring October (November) evening 1min

All in compliance

Receiver Date Site Noise Level Contribution Operational Criteria (dB(A)) EPL ID LA1, 1 minute (dB(A)) evening R3 29/11/18 30 45 R2 29/11/18 32 45 R8 29/11/18 25 45 R4 29/11/18 33 45 R17 29/11/18 21 45

slide-16
SLIDE 16

16

Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring July 2018 daytime

Receiver Date Site Noise Level Contribution Operational Criteria (dB(A)) EPL ID LAeq, 15 minute (dB(A)) daytime R3 31/7/18 31.2 35 R8 31/7/18 31.0 41 R8 31/7/18 31.0 41 R3 31/7/18 31.5 35 R2 31/7/18 32.0 35 R2 31/7/18 29.7 35 R17 31/7/18 27.7 35 R17 31/7/18 26.1 35 R4 31/7/18 31.9 35 R4 31/7/18 29.6 35 R2 1/8/18 25.9 35 R2 1/8/18 27.1 35 R17 1/8/18 24.9 35 R17 1/8/18 23.8 35 R3 1/8/18 24.1 35 R3 1/8/18 28.8 35 R8 1/8/18 28.7 41 R8 1/8/18 29.3 41 R4 1/8/18 28.2 35 R4 1/8/18 27.3 35

All in compliance

slide-17
SLIDE 17

17

Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring July 2018– evening

Receiver Date Site Noise Level Contribution Operational Criteria (dB(A)) EPL ID Leq, 15 minute (dB(A)) evening / night R2 1/8/18 26.3 35 R2 1/8/18 24.9 35 R17 1/8/18 17.1 35 R17 1/8/18 20.0 35 R3 1/8/18 33.3 35 R3 1/8/18 31.3 35 R8 1/8/18 33.3 35 R8 1/8/18 33.6 35 R17 1/8/18 15.2 35 R4 1/8/18 31.4 35 R4 1/8/18 27.2 35 R8 1/8/18 14.9 35 R3 2/8/18 30.4 35 R33 2/8/18 26.8 35 R8 2/8/18 31.2 35 R2 2/8/18 18.1 35 R8 2/8/18 29.0 35 R2 2/8/18 23.8 35 R8 2/8/18 31.6 35 R3 2/8/18 33.5 35 R8 2/8/18 31.5 35 R3 2/8/18 35.0 35 R17 2/8/18 12.8 35 R4 2/8/18 32.5 35 R4 2/8/18 32.5 35 R17 2/8/18 13.4 35

All in compliance

slide-18
SLIDE 18

18

Agenda item 6 – Environmental Performance Noise - quarterly noise monitoring July evening 1min

Receiver Date Site Noise Level Contribution Operational Criteria (dB(A)) EPL ID LA1, 1 minute (dB(A)) evening R3 1/8/18 38.3 45 R3 1/8/18 36.3 45 R8 1/8/18 38.3 45 R8 1/8/18 38.6 45 R17 1/8/18 15.2 45 R4 1/8/18 41.4 45 R4 1/8/18 37.2 45 R8 1/8/18 14.9 45 R3 2/8/18 35.4 45 R3 2/8/18 36.8 45 R8 2/8/18 31.2 45 R2 2/8/18 18.1 45 R8 2/8/18 29.0 45 R2 2/8/18 23.8 45 R8 2/8/18 31.6 45 R3 2/8/18 38.5 45 R8 2/8/18 31.5 45 R3 2/8/18 40.0 45 R17 2/8/18 17.8 45 R4 2/8/18 37.5 45 R4 2/8/18 37.5 45 R17 2/8/18 18.4 45

All in compliance

slide-19
SLIDE 19

19

Agenda item 6 – Environmental Performance Blast monitoring

All in compliance

50 100 150 dB (lin peak)

2017 - jan 2019 Blast trend - Overpressure

criteria 1 criteria 2 north west boundary north east boundary Pace 683 Marulan sth road

slide-20
SLIDE 20

20

Agenda item 6 – Environmental Performance Blast monitoring

All in compliance

2 4 6 8 10 12 mm/sec)

2017 - jan 2019 Blast trend - Ground Vibration

criteria 1 criteria 2 north west boundary north east boundary 683 Marulan sth road Pace

slide-21
SLIDE 21

21

Agenda item 6 – Environmental Performance Surface water

Quarterly monitoring round undertaken in September and November 2018 Due to lack of rain only 3 sites sampled – no flow onto the site. Analyses now compared to trigger levels Next sample round March 2019 Total Nitrogen for T1 is in compliance, levels in the dam have always been higher but have decreased during 2017 and leveled off. Marulan south creek increasing and may be due to lack of flow of water

slide-22
SLIDE 22

22

Agenda item 6 – Environmental Performance Surface water

Total dissolved solids in compliance with the exception of Marulan south creek – due to low flow Turbidity In compliance with the exception of the dam following rain event of 43mm in the preceding 24hours

slide-23
SLIDE 23

23

Agenda item 6 – Environmental Performance Surface water

pH in compliance for the last rounds of sampling Total phosphorus - In compliance for T1 but showing fluctuations for the dam. May be due to changes in water level introducing nutrients from above the site and / or an increase in water fowl population in the dam. Marulan south creek shows a similar pattern, with a decrease in September and an increase following the rain event in November 2018

slide-24
SLIDE 24

24

Agenda item 6 – Environmental Performance Ground water

  • No draw down of ground water from sentinel well .i.e. no impact on local groundwater.
slide-25
SLIDE 25

25

Agenda item 6 – Environmental Performance Ground water

  • Monitoring conducted July and October 2018
  • Measured against trigger levels
  • Continue to have Exceedances of total nitrogen and total phosphorus at some

bores (background levels are higher than guidance standards)

  • Continue to have higher than trigger levels on a range of analytes such as

chloride, sodium magnesium.

  • The majority of these results however are minor, and likely due to the poorly

developed nature of the bores and the limited dataset utilised for trigger levels development.

  • Statistical review of the results and trigger values is being commissioned
slide-26
SLIDE 26

26

Agenda item 6 – Environmental Performance Environmental flow

All in compliance

slide-27
SLIDE 27

27

Agenda item 6 – Environmental Performance Heritage

  • No Heritage associated works undertaken.
  • Next step to fence scar trees
slide-28
SLIDE 28

28

Agenda item 6 – Environmental Performance Ecology

  • Second Rapid Visual assessment

undertaken to identify any rehabilitation site issues

  • First transect monitoring undertaken on

rehabilitated sites. This is undertaken every 2 years to provide guidance on the success of the plantings

  • 40 000m2 area hydro mulched on the southern overburden
  • Top of the eastern overburden and slope have been planted
  • 67 feral goats removed from site with more to be captured.
slide-29
SLIDE 29

29

Agenda item 6 – Stakeholder Engagement (august 2018 to February 2019)

  • CVA schools program conducted at Marulan Public school
  • Outward Bound – May 2019
  • Kite festival September 2018
  • 150th railway celebrations
  • Representatives at Tallong Armistice Day
  • Marulan Village plan
  • Visit to Marulan Public school with other quarry representatives
  • Participation in the CMIC 18 Conference
  • Goulburn Mulwaree Council Charity Golf day
  • Goulburn Mulwaree Community Bike ride
  • IQA Women in Quarrying conference
slide-30
SLIDE 30

30

Agenda item 7 – Plans for the next three months

  • Safety
  • Maintain zero harm to our employees and contractors
  • Focus on pedestrian and vehicle interactions
  • Overburden
  • Completion of the Southern overburden dump by June 2019
  • Pit update
  • In March 19 we will be constructing a new conveyor to head South across the pit floor
  • In April 19 the primary crusher will move onto this new conveyor and progress South for the

rest of the year

  • Processing
  • The store for parts storage will be completed allowing for a large tidy up around site of parts
  • We will be bedding in the additional train
  • People
  • Continuation of training and development of our people
slide-31
SLIDE 31

31

Agenda item 8 – General Business

  • Weather station update
  • Site inspection by Alec from Todoroski Air Sciences. Preferred location identified, waiting on

report

  • Waiting to confirm current weather station is compatible with the real time noise monitoring
  • Real Time noise monitoring
  • Contract has been let to install real time noise monitoring at a sensitive receiver to enable pit
  • perations to be shut down if noise is excessive
  • Independent Audit
  • Required every 3 year. Being undertaken by Advisian. Conducted in November 2018 with

report to be made available end of January 2019.

  • Drought Contingency planning
  • Site has been working on planning for drought with only 2 months of water supply remaining

back in December 2018

slide-32
SLIDE 32

32

Agenda item 8 – General Business

  • Marulan South Limestone update
  • The company has lodged a revised EA in December 2018.
  • Department of Planning visited site Friday 1st 2019 with Local government

representatives visiting Thursday 7th February.

  • Next step is for formal public exhibition
slide-33
SLIDE 33

33

Agenda item 8 – General Business

  • Peppertree Quarry Modification 5
  • has been on Public exhibition
  • Number of responses from government authorities and 2 public submissions
  • Preliminary response to comments has been made to the Department with a final response

required by the end of February 2019.

  • Site inspection by the Department of planning Friday 1st February 2019
slide-34
SLIDE 34

34

Agenda item 8 – General Business

slide-35
SLIDE 35

35

Agenda item 8 – General Business

  • Next meeting dates –
  • May 2019
slide-36
SLIDE 36

END