CLARIFICATION MEETING
Date: 17 May 2019 Venue: New Germany Time: 10H00
CLARIFICATION MEETING Date: 17 May 2019 Venue: New Germany Time: - - PowerPoint PPT Presentation
CLARIFICATION MEETING Date: 17 May 2019 Venue: New Germany Time: 10H00 Eskom Values (ZIISCE) / Izimiso Ka-Eskom VALUE MEANING ISIMISO SISHO UKUTHINI ZERO HARM Eskom will strive to ensure that zero harm ZERO HARM U-Eskom uzoqhubeka
Date: 17 May 2019 Venue: New Germany Time: 10H00
2019/05/24 2
VALUE MEANING
ZERO HARM Eskom will strive to ensure that zero harm befalls its employees, contractors, the public and the natural environment. INTEGRITY Honesty
purpose, conduct and discipline in actions, and respect for people. INNOVATION Value-adding creativity and results
innovation. SINOBUNTU Caring. CUSTOMER SATISFACTION A commitment to meet and strive to exceed the needs of the receivers of products and services. EXCELLENCE Acknowledged by all for exceptional standards, performance and professionalism.
ISIMISO SISHO UKUTHINI
ZERO HARM U-Eskom uzoqhubeka nokulwela ukuqinisekisa ukuthi ukuphepha
lapho kwenziwa umsebenzi (Zero Harm) kuba yisikompilo kubasebenzi benkampani,
umphakathi kanye nokunakekelwa kwemvelo yonkana. UBUQOTHO Ukwenza izinto ngokungaguquki, ngendlela ekhuthaza ukwethenjelwa nokuzibophezela. IKHONO LOKUQAMBA Ukwakha isimiso esivumela ukukhula kwabantu abanamakhono. SINOBUNTU Ukuqhakambisa umusa nozwelo komunye nomunye. UKWANELISEKA KWAMAKHASIM- ENDE Ukuzibophezela ukwenzela amakha- simende umsebenzi
ngokuvelele nangokudlulele. UBUHLE OBUVELELE Ukuqhubeka ukulwela ukuba ngophuma phambili ngokusebenza ngendlela evelele nefaneleyo.
2019/05/24 3
2019/05/24 4 4
2019/05/24 5
2019/05/24 6
Enquiry No Closing Date Area Duration
DD 6742/AR 31 May 2019 at 10h00 Kranskop Not extending beyond 31 March 2022
2019/05/24 7
Basic Compliance and Mandatory Evaluation
tender):
Functionality:
PPPFA
. Objective Criteria
Basic Compliance (As per page 8 of the invitation to tender):
tender deadline
deadlines
affidavits confirming their level – non submission will not result in disqualification but will impact on the scoring
tender is a mandatory returnable at tender closing stage!
affidavit if no employees stating as such
2019/05/24 8
Mandatory Tender Returnables (As per page 9 of the invitation to tender):
entirety the submission will be disqualified
to tender is a mandatory returnable at tender closing stage!
2019/05/24 9
2019/05/24 10
be vetted by Eskom Legal department
buildings with a combined floor space of between 500 m2 - 600 m2 of buildings space which will be used for offices, workshops, standby quarters and ablutions within 4 km radius from 46 Main street, Kranskop, for approximately 33 months but not extending beyond 31 March 2022
any other municipal charges excluding water and electricity
included in the total price tendered
2019/05/24 11
written notice to the Lessor. In such a case, in addition thereto that obligations incurred by the Lessee prior to such giving notice remain intact and that the Lessor will credit the Lessee with amounts due to it.
2019/05/24 12
2019/05/24 13
being leased, provide exact location etc
2019/05/24 14
entirety the submission will be disqualified
tender returnable - Should the SBD 1 Form not be completed in its entirety the supplier will be disqualified.
2019/05/24 15
2019/05/24 16
The physical condition of the site evaluation will only be conducted for those tenderers that achieve a 85% threshold on Part 1 of the technical evaluation based on the tender submission
Technical Evaluation Criteria - Part 1 Weight
Score 10 if greater than 3500 m² and less than 5000 m² Score 0 if less than 3500m² or greater than 5000 m² 40%
m² Score 10 if greater than 500 m² and less than 600 m² Score 0 if less than 500m² or greater than 600 m² 30%
Score 10 if located less than/equal to 4km of current location Score 5 if located at between 4 km and 5 km of current location Score 0 if located greater than 5 km of current location 30%
2019/05/24 17
2019/05/24 18
in Part 1 Note: The final technical evaluation score will comprise solely of the evaluated score received in Part 2 of the technical evaluation criteria.
successfully pass the technical evaluation criteria
2019/05/24 19
scales starting with 75% and decreasing at increments of 5% to a minimum threshold of 60% for Part 2 should all tenderers not be able to meet the 80% requirement
Technical Evaluation Criteria - Part 2 Suitability of Property for desired use Weight
ease of accessibility to end-users such as closeness to main roads, taxi routes etc.) 20%
certificates, grade of the building, availability of services 20%
space, disability access, warehouse space, parking space and distance to entrances, ablutions, kitchens, drawings etc.) 20%
site if required 20%
type of perimeter fence, security gates and burglar bars to windows and doors, safety to end-users, crime rate of the area 20%
2019/05/24 20
A fully priced price list– Should the price list not be completed in its entirety the submission will be disqualified
electricity, sewage and refuse cost if applicable. These costs will be paid separately and must not be included in the total price tendered. Rates and taxes and any other municipal cost are the responsibility of the lessor. The gross lease agreement should have a clear breakdown of all cost making up the monthly rental cost. It is therefore imperative that the tenderer list all cost payable by Eskom. The tenderer is advised to add any items on the list that will be recoverable from Eskom during the course of this lease agreement Item Description Unit QTY (A) Rate (B) Monthly cost (C) C = A x B 1 Net rent for office space m2 R R 2 Other: R R 3 Other: R R 4 Other: R R 5 Other: R R 6 Other: R R 7 Other: R R 8 Other: R R Total cost of lease per month R
2019/05/24 21
Item Description Unit Yr2 Yr3 Yr4 1 Net rent for office space % 2 Other: % 3 Other: % 4 Other: % 5 Other: % 6 Other: % 7 Other: % 8 Other: % 9 Other: % 10 Other: %
2019/05/24 22
2019/05/24 23
terms of the 80/20 PPPFA preferential point scoring will be evaluated for
stage they will be given only 1 opportunity to submit the outstanding requirements.
DISQUALIFIED and the next supplier in terms of the 80/20 PPPFA preferential point scoring will be selected to take part in this enquiry.
even if you mistakenly omit 1 of the requirements or don’t pass the requirement for any reason you WILL NOT be given an opportunity to correct the error. Your submission will be disqualified
2019/05/24 24
2019/05/24 25
2019/05/24 26
2019/05/24 27
The pages are not secure and punched
Pages may be removed Pages tend to come loose from the binding during the stamping and handle process
2019/05/24 28
2019/05/24 29
The clip tends to bend with the size of the tender and during the handling of the tender.
Pages may be removed Tender Document is not tamper proof
2019/05/24 30
Tamper Proof Binding of Tender Documents
2019/05/24 31
2019/05/24 32
2019/05/24 33
2019/05/24 34
2019/05/24 35
NO REQUIREMENT 1 Acknowledgement for Eskom rules and requirements (Annexure B). Acknowledgement of the form must be fully completed, i.e. MD/CEO signatures 4 Proof of insurance for a building
2019/05/24 36
NO REQUIREMENT 1 Completed and signed form A Ensure form A is signed
2019/05/24 37
NO REQUIREMENT 1 Due diligence Assessment of the property If there are any historic environmental issues on the property. E.g. Hazardous chemicals or indigenous/protected trees on site, etc.) 2 Details of Interested Parties contact details of neighbours around the property) Note: this is an ISO14001:2015 requirement and KZN OU is an ISO14001 certified electricity utility 3 Copies of environmental authorisations/licenses/permits Provide copies of above if the land owner has any.
2019/05/24 38