city rail link
play

City Rail Link 1 Aotea Community Liaison Group (CLG) 10 th of - PowerPoint PPT Presentation

City Rail Link 1 Aotea Community Liaison Group (CLG) 10 th of November 2016 Welcome Speaking tonight are: Carol Greensmith , CRL Communications Manager Richard Jenkins , Principal Planner Sonya Leahy , Advocacy & Stakeholder


  1. City Rail Link 1 Aotea Community Liaison Group (CLG) 10 th of November 2016

  2. Welcome Speaking tonight are: • Carol Greensmith , CRL Communications Manager • Richard Jenkins , Principal Planner • Sonya Leahy , Advocacy & Stakeholder Manager • Also here is Makere Carroll , Communications Coordinator

  3. Overview • Revisit the City Rail Link project – progress so far • A recap of the purpose of the Community Liaison Group • Aotea Station • Aotea alteration designation hearing • Potholing in Aotea area

  4. The Route

  5. General update • C1/C2 contracts • DSC • Funding agreement • Procurement • Industry briefing

  6. CLG Recap

  7. The role of the CLG • AT is required by the CRL designation conditions to establish CLGs in the areas of surface works • The Aotea CLG was established in November 2015 • AT wants input into various documents that guide the delivery of construction work • A Community Liaison Group, representing those affected by the work is a key tool for this • In addition, we will continue to keep in touch via the project website, e-updates, etc.

  8. CLG requirements Condition 7.5 of the CRL designation requires AT to consult with those directly and in proximity parties affected by the CRL construction works. This happens through the CLG by: • regular updates provided by AT on construction progress • providing feedback on the development of the Delivery Work Plans (DWPs) and Construction Environmental Management Plans (CEMPs), and the Communication and Consultation Plan • input into a regular forum monitoring the effects on the community • reporting concerns and issues to AT that it will respond to • possibly proposing potential initiatives to the Property Management Strategy on the interim use of properties acquired by the CRL

  9. Aotea Station

  10. Virtual Tour

  11. BIM model

  12. Aotea designation alteration

  13. Overview • Vents in footpaths in Albert and Kingston Streets • Shifting bluestone wall • Slip lane parking • Temporary requirement to use private land for pedestrians • Canopy Removals

  14. Utilities investigation in Aotea area

  15. Overview • Investigation into condition of network utilities to assist with station design • Potholing, Ground Penetrating Radar (GPR) and drainage surveys including CCTV • Results will be used to plan utility diversions • 11 trenches proposed for Aotea Station area • Works may start as early as December 2016 • Duration of works will be 6 – 8 weeks • Works to take place during daytime hours

  16. Aotea Station Utilities Investigations • A series of investigation trenches typically between 5m to 14m long, up to 1m wide and 1.5m deep.

  17. Contact Website: AT.govt.nz/crl Facebook: Facebook.com/cityraillink Email: CRLProject@at.govt.nz Phone: 09 355 3553

  18. Questions or comments?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend