BROWARD COUNTY Broward County Project Number 5413 Qualifications for Construction Engineering and Inspection Services CEI Services for Wiles Road from Riverside Drive to Rock Island Road YOUR CEI SOLUTION YOUR PARTNERS MEET THE AE TEAM


  1. BROWARD COUNTY Broward County Project Number 5413 Qualifications for Construction Engineering and Inspection Services CEI Services for Wiles Road from Riverside Drive to Rock Island Road YOUR CEI SOLUTION – YOUR PARTNERS

  2. MEET THE AE TEAM YOUR CEI SOLUTION – YOUR PARTNERS

  3. I Expertise and Manpower II Issue Identification and Resolution III Communication, Coordination & Stakeholder Outreach Calvin Giordano + Associates, Inc.

  4. I Expertise and Manpower Calvin Giordano + Associates, Inc.

  5. Cory Nichols, P.E. Roderick Myrick, P.E. Sr. Project Engineer (AE) Quality Assurance Quality Control Eddie Hernandez. P.E., Project Administrator (AE) Marlin Engineering Inc. Survey & Mapping Udin Dwarica-Ogeer , Contract Support Specialist (AE) Universal Engineering Sciences, Inc. Randy Rosa, P.E., Materials Specialist (AE) Geotechnical Serivces Christina Yero, P.E., LAP Contract Compliance Specialist (AE) Erica Valencia, Resident Compliance Specialist (AE) Mike Latulippe, Senior Inspector (AE) Gerard Fleurgin, Senior Inspector (SCE) Christopher Bradbeer, Inspector Chase Elliott, Inspector Derek Wynne, Landscape (RS&H) (RS&H) Inspector (AE) Torrance Thomas, Inspector Arie Saraga, Inspector Michael Davis, Inspector (AE) (SCE) (SCE) I Expertise and Manpower Calvin Giordano + Associates, Inc.

  6. Manpower We have found that the key to successful management of our projects is the assignment of the right personnel with the necessary skills and similar past experience. Senior Project Engineer: • Roderick Myrick, P.E. (21 years experience) core responsibilities include Overall Management, Customer Service, and Timely Project Delivery Project Administrator: • Eddie Hernandez, P.E. (11 years experience) responsibilities – Verify and Monitor CPM Schedule and Shop Drawings, Coordinate Materials Testing Contract Support Specialist: • Udin Dwarica, (25 years experience) responsibilities – Project Documentation, Organization, Monthly Estimates and Closeout Assistance Senior Inspector: • Mike Latulippe (25 years experience) responsibilities – Daily Project Oversite, Materials Testing LAP Specialty Services: • Christina Yero, P.E. (8 years experience) responsibilities – LAP Monthly Invoicing and Final Settlement with FDOT LAP Office • Erica Valencia (12 years experience) responsibilities –Resident Compliance Specialist • Randy Rosa, P.E. (8 years experience) responsibilities – Materials Specialist I Expertise and Manpower Calvin Giordano + Associates, Inc.

  7. Expertise – Similar Experience Recent Projects: • FDOT Broward Operations; SR-A1A 3R from Mercedes River to Sunrise Blvd; FM 430601-1-52-01: Milling & resurfacing, widening, drainage including French drain , signalization improvements, sidewalk and curb ramp construction • City of West Palm Beach; Clematis Street Improvements; FDOT LAP Project FM 427652-1-58-01: Pedestrian, safety and landscape improvements including sidewalk construction and milling & resurfacing City of West Palm Beach; 15 th Street Beautification Project; FDOT LAP Project FM • 431652-1-58-01: Scope included signalization and drainage improvements , milling & resurfacing, and bike lane striping • FDEP; SR 5/Overseas Hrt. Trail @ MM 47 (Knights Key Pedestrian Underpass – FDOT LAP Project FM 428061-1-58-01: ADA ramps, retaining walls , bulkhead wall, sidewalks, railing, pedestrian bridge approach, landscaping , signage, and striping within DOT right-of-way. • FDEP; SR 5/Overseas Hrt. Trail Spanish Harbor Historical Bridge @ MM 33 FDOT LAP Project FM 422628-1-58-01: Replacement of missing bridge span sections via proprietary pre-fabricated truss and precast concrete beams, existing deck milling and resurfacing, joint/crack cleaning and resealing, aluminum safety railing , navigational lighting, striping and signage . I Expertise and Manpower Calvin Giordano + Associates, Inc.

  8. Presentation Topics II Issue Identification and Resolution Consistent with order of categories distributed in short- list announcement Calvin Giordano + Associates, Inc.

  9. Unique Project Issues: Drainage • 1524 LF of French drain installation – Filter fabric and aggregate • Thirty-eight (38) Inlets, and thirty-one (31) Manholes • Cast-in-place structures – Verifying elevations prior to shop drawing approval Signalization • Coordination with Broward County and FDOT for acceptance • Seven (7) Mast Arms installed at Riverside Dr. and Leitner/Woodside Dr. • Drilled Shaft – Deep removal of existing foundations Asphalt • Limits of Milling and Overbuild – Maintaining positive drainage • Paving Operations Challenges – Smoothness and Rideability • Binder Type – PMA called out Concrete Operations • Gravity Wall Construction per Index 6011 • Sidewalk and curb ramps – maintaining pedestrian and driveway access II Issue Identification and Resolution Calvin Giordano + Associates, Inc.

  10. III Communication, Coordination & Stakeholder Outreach Calvin Giordano + Associates, Inc.

  11. Communication and Coordination Rod Myrick, P.E and Eddie Hernandez, P.E. – CEI Point of Contact (POC) Rod will serve as the Sr. PE/Project Manager. Eddie will be serving as the coordinator of all information concerning the project. This ensures that there will be no communication break-downs amongst the team members. Key members that we will coordinate with include: • Construction Contractor • Project Manager • Design Team/ Consultant • Broward County Traffic Communications will include: • Kick-off meeting prior to Pre-Construction Meeting • Pre-Construction Meeting • Weekly or bi-weekly meetings • Weekly updates to County staff • Clarifying or resolving issues in a timely manner • Discrepancies/ disputes • Budget • Compliance III Communication, Coordination & Stakeholder Outreach Calvin Giordano + Associates, Inc.

  12. Stakeholder Outreach • Door to Door Outreach o Prior to construction visit each affected business/residence within the project corridor o Identify a contact person for each affected stakeholder o Provide expectation for the project impacts o Develop relationship with project team to minimize public complaints during construction • Risk Analysis o Identify each construction operation and its effect on adjacent properties o Include contact information obtained during door to door o Use the database to proactively inform the affected parties before operations • Risk Management • Identify possible risks during construction • Assess the risk probability and impact to time, money and public goals • Develop a risk response strategy III Communication, Coordination & Stakeholder Outreach Calvin Giordano + Associates, Inc.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.