Briefing on day-ahead load forecasting Amber Motley, Manager Short - - PowerPoint PPT Presentation

briefing on day ahead load forecasting
SMART_READER_LITE
LIVE PREVIEW

Briefing on day-ahead load forecasting Amber Motley, Manager Short - - PowerPoint PPT Presentation

Briefing on day-ahead load forecasting Amber Motley, Manager Short Term Forecasting Board of Governors Meeting General Session November 14, 2018 Load forecast accuracy improved 10% in 2018 CAISO Day Ahead Mean Absolute Percent Error


slide-1
SLIDE 1

Briefing on day-ahead load forecasting

Amber Motley, Manager – Short Term Forecasting Board of Governors Meeting General Session November 14, 2018

slide-2
SLIDE 2

0.0% 0.5% 1.0% 1.5% 2.0% 2.5% Q1 Q2 Q3 Q4

CAISO Day Ahead MAPE

2013 2014 2015 2016 2017

MAPE MAPE

Load forecast accuracy improved 10% in 2018

Page 2

0.0% 0.5% 1.0% 1.5% 2.0% 2.5% Q1 Q2 Q3 Q4

CAISO Day Ahead Mean Absolute Percent Error (MAPE)

2013 2014 2015 2016 2017 2018

MAPE MAPE

Forecast improvement observed in Q1 and Q2 2018

slide-3
SLIDE 3

Analysis of load forecast error looked at the following:

  • Effect of behind the meter resource production
  • Underlying temperature / weather forecast
  • Regional forecast granularity / micro climate effects
  • Machine learning model tuning parameter
  • Manual adjustments

Page 3

slide-4
SLIDE 4

Hourly error increases in middle of day due to effects of increasing behind the meter production on mid-day load.

Page 4

slide-5
SLIDE 5

Page 5

Average MW behind the meter error varies significantly by Quarter in 2017.

slide-6
SLIDE 6

During Q1, Q2, and Q4 ISO forecasts are driven by cloud cover

Page 6

Quarter

slide-7
SLIDE 7

Page 7

There is a difference between ground measured irradiance and satellite interpolated actuals in 2017.

Quarter

slide-8
SLIDE 8

Conclusion of analysis

  • Load forecast accuracy is most impacted by cloud cover

variability effects on 7,000MW of behind-the-meter capacity during Q1, Q2, and Q4.

  • New forecast techniques are needed to support the magnitude

and changes to behind-the-meter resource capacity.

  • Improved visibility into the actual aggregate behind-the-meter

production is needed to improve calibration of forecast models

Page 8

slide-9
SLIDE 9

Work plan of next steps

Page 9

Task Estimated Schedule Regional Breakout End of 2018 Incorporate Behind the Meter Actuals June 30, 2019 Re-assess BTM Forecast Provider June 30, 2019 Modeling Environment TBD; working with IT Multiple Models TBD; working with IT Appropriate Blending Options TBD; working with Vendor Probabilistic Forecasting TBD working with DOE Sponsored Research Project Develop new forecasting approaches Continuously researching best practices & new techniques