Bellevue Dow ntow n Bellevue Dow ntow n Access Project Access - - PDF document

bellevue dow ntow n bellevue dow ntow n access project
SMART_READER_LITE
LIVE PREVIEW

Bellevue Dow ntow n Bellevue Dow ntow n Access Project Access - - PDF document

FHWA Accelerated Bridge Construction Workshop Olympia, WA Bellevue Dow ntow n Bellevue Dow ntow n Access Project Access Project NE 8 th Street Bridge NE 8 th Street Bridge Replacem ent Replacem ent September 30 , 2008 Presented by Ron


slide-1
SLIDE 1

1

FHWA Accelerated Bridge Construction Workshop – Olympia, WA

NE 8 th Street Bridge NE 8 th Street Bridge Replacem ent Replacem ent

September 30, 2008 Presented by Ron Ohlsen, PE HDR Engineering, Inc.

Bellevue Dow ntow n Bellevue Dow ntow n Access Project Access Project

Puget Sound Freew ay System Bellevue Direct Access Project

slide-2
SLIDE 2

2

Local Street Improvements Freeway Improvements Transit/HOV Improvements

TOTAL TIB WSDOT FHWA City of Bellevue Sound Transit $ 1 6 4 M $6 M $11.2 M $12.8 M $31.2 M $103.4 M

Funding Partners

NE 4 th Street Bridge

slide-3
SLIDE 3

3

NE 6 th Street NE 8 th Street Bridge I -4 0 5 Corridor Traffic

slide-4
SLIDE 4

4

NE 8 th Bridge Replacem ent Design Challenge How do you rebuild a major arterial running east/ west into the heart of downtown Bellevue without causing excessive disruption to traffic and commerce? Design Options:

Close Old Bridge to Traffic, Demolish and Rebuild Close Old Bridge to Traffic, Demolish and Rebuild Stage Demolition and Reconstruction, One Half at a Time Stage Demolition and Reconstruction, One Half at a Time Modified Stage Construction of Bridge in a Tem porary Location Modified Stage Construction of Bridge in a Tem porary Location

Modified Staged Construction

Risks Benefits

Design Selection

Can You Build and Roll the Bridge into Position? Can You Build and Roll the Bridge into Position? Reduce NE 8th Total Closures from 12- 18 Months to Nighttime Closures and a Handful of Weekend Closures. Reduce NE 8th Total Closures from 12- 18 Months to Nighttime Closures and a Handful of Weekend Closures. Build Half of the Bridge in a Temporary Location and then Roll the New Bridge Approximately 64 Feet to the North. Build Half of the Bridge in a Temporary Location and then Roll the New Bridge Approximately 64 Feet to the North.

slide-5
SLIDE 5

5

Structure Type Selection Considerations

  • Composite Steel Girder / Concrete Deck

Selected Structure Type Selected Structure Type Span Length Span Length Roadway Vertical Clearance During Construction Roadway Vertical Clearance During Construction Structural Depth / Weight Structural Depth / Weight

  • I-405

Traffic Maintenance Considerations Traffic Maintenance Considerations

  • NE 8th

7 Bridge Piers 6 Lanes 1 0 3 Feet W ide 2 9 2 .5 Feet Long

Old Bridge

3 Bridge Piers 8 Lanes 1 2 1 .5 Feet W ide 3 2 8 Feet Long

New Bridge

NE 8 th Bridge Construction

Existing Bridge Existing Bridge

slide-6
SLIDE 6

6

Existing Bridge Existing Bridge Construction Sequence – Stage 1 Construction Sequence – Stage 1 Construction Sequence – Stage 2 Construction Sequence – Stage 2

slide-7
SLIDE 7

7

Construction Sequence – Stage 3 Construction Sequence – Stage 3 Construction Sequence – Stage 4 Construction Sequence – Stage 4

NE 8 th Street Bridge Construction Stages

Stage 1

Summer 2002 Winter 2002/2003

Stage 2 Stage 3

Summer 2003

Stage 4

Autumn 2003

slide-8
SLIDE 8

8

August 2 0 0 2 Pier 1

South Half Temporary Location

August 2 0 0 2 Pier 2

South Half Temporary Location

Stage 1 : Girder Erection

September 9, 2002

slide-9
SLIDE 9

9

Stage 1

Novem ber 2 -3 , 2 0 0 2

Weekend Traffic Shift #1 Stage 2 : W inter 2 0 0 2 - 2 0 0 3

slide-10
SLIDE 10

10

Stage 2 : Bracing of rem aining piers

Stage 2 : Dem olish North Half of Bridge

Decem ber 2 0 0 2

North Half Dem olished

slide-11
SLIDE 11

11

  • Feb. 2 5 -2 7 , 2 0 0 3

Setting Girders North Half

March 2 0 0 3 Deck Form ing

North Half W eekend Traffic Shift # 2 North Half May 17 & 18, 2003

slide-12
SLIDE 12

12

Stage 3 : Sum m er 2 0 0 3 Stage 3 : Dem olition June 2 0 0 3 Demolition of Old South Half

slide-13
SLIDE 13

13

July 2 0 0 3 Pier 2 Construction South Half Permanent Location Bridge Relocation

Stage 4 Construction Bridge Roll Preparations

Jacking Scheme:

Pull Loads: 57 kips at Abutments, 191 kips at Center Pier Pull Loads: 57 kips at Abutments, 191 kips at Center Pier 2% Cross-Slope 2% Cross-Slope Jack Stroke: 12 inches Jack Stroke: 12 inches

slide-14
SLIDE 14

14

Bridge Roll Preparations

September 2003 Pier 2

Dyw idag Connection to Diaphragm Adjust Hilm an Rollers

slide-15
SLIDE 15

15

  • Sept. 1 9 , 2 0 0 3

Bridge Roll Before

slide-16
SLIDE 16

16

Cut Them Off

Be Flexible After Closure Pour

Closure Pour: Nov. 7, 2003 Photos: January 2004

slide-17
SLIDE 17

17

I nnovative Delivery and Construction Methods to Minim ize I m pacts to Traveling Public

– Detailed Traffic Analysis – City of Bellevue Involvement – Public Information

Traffic Maintenance Traffic Maintenance Structure Demolition Methods Structure Demolition Methods NE 8th Bridge Rolling NE 8th Bridge Rolling

Structure Dem olition Methods NE 8 th Project I ncentives

– Contractor Received $190,000 Worth of Incentives – Reduced HOV Lane Closures by 19 Days – Reduction in Traffic I mpacts – Good Press, Positive Feedback from City, Business Community and Public – Opportunity for Contractor to Control this Phase of Work

Results Results Project Incentives to Limit the Number of Days for Total HOV Closure Project Incentives to Limit the Number of Days for Total HOV Closure Benefits Benefits

slide-18
SLIDE 18

18

NE 8 th Project I ncentives Project Accom plishm ents

– Bellevue Chamber of Commerce Miracle of the Year (2) – ARTBA Pride Award 2005 – ASCE Outstanding Civil Engineering Project, Seattle Section 2005

Recipient of Several Awards Recipient of Several Awards Project Completed One Year Ahead of Schedule Project Completed One Year Ahead of Schedule Project Cost $25 million under budget Project Cost $25 million under budget

Bellevue Dow ntow n Access Project

Ron Ohlsen, P.E. HDR Engineering, Inc. ron.ohlsen@hdrinc.com