Beechworth Community Meeting 21 November 2016 newater.com.au Agenda 1. Planned works for Beechworth 2. Beechworth Sewer Improvements 3. Your feedback 4. Next steps newater.com.au Planned works for Beechworth 3.5ML treated water


slide-1
SLIDE 1

Beechworth Community Meeting

21 November 2016

newater.com.au

slide-2
SLIDE 2

Agenda

  • 1. Planned works for Beechworth
  • 2. Beechworth Sewer Improvements
  • 3. Your feedback
  • 4. Next steps

newater.com.au

slide-3
SLIDE 3

Planned works for Beechworth

  • 3.5ML treated water storage tank at our water treatment

plant on Dingle Road

  • Improvements to the Beechworth Sewerage System

– Sewerage treatment plant – Transfer Pipe

slide-4
SLIDE 4

Beechworth Sewer Transfer Pipe

slide-5
SLIDE 5

Community Values

What is it you value about this setting?

slide-6
SLIDE 6

History

Sept 1967 Completion

  • f sewer

transfer main to WWTP from Church St Apr 1980 Establishment

  • f

Beechworth Historic Park 1997 Upgrade of Church St

  • utfall

structure 2006 N.E.W reporting identified infiltration as main cause of issue 2007 - 2008 N.E.W undertook significant relining of sewer mains targeting known high risk infiltration pipe materials 2012 N.E.W identified infiltration Mayday Hill site as a significant source of infiltration 2013 - 2014 Remediation work at Mayday Hills 2016 N.E.W capital investment of Beechworth Sewer Transfer Pipe

slide-7
SLIDE 7

Background

  • Beechworth positioned on a unique granite shelf
  • Stormwater infiltration has caused overflows to the sewer

system creating an unacceptable threat to the environment

  • Re-lining of the town's sewer pipe network has not

resolved this issue

slide-8
SLIDE 8

A shared challenge

  • Increase capacity for town growth
  • Improve our environmental performance –

acknowledging the cultural and environmental values of the area

  • Collaborate with the community to

resolve this issue

slide-9
SLIDE 9

Our Engagement Goal

  • North East Water promises to work directly with the

Beechworth community throughout the process to ensure your issues and concerns are consistently understood and considered;

  • North East Water will provide feedback to the

Beechworth community on how your input influenced the decision;

  • The final decision rests with the Board of North East

Water.

slide-10
SLIDE 10
  • 2 preliminary options identified – tank or pipe
  • Collaborate with the community on these options
  • Other stakeholders we will be talking to include:

– Indigo Shire Council – Parks Victoria – EPA – DELWP – local groups.

slide-11
SLIDE 11

Beechworth’s sewer system

slide-12
SLIDE 12

Existing Pipeline Route

Red line is the boundary

  • f Beechworth Historic

Park

slide-13
SLIDE 13

Option 1: Storage Tank

  • Located at back of Church Street Inlet
  • Provide storage for excess flows until there is sufficient

capacity within the sewer system

  • A minimum 3ML tank would be required (3 Olympic size

swimming pools)

  • Cost estimate $4m
slide-14
SLIDE 14
slide-15
SLIDE 15

Option 1: Storage Tank

slide-16
SLIDE 16

Option 2: Replace pipeline over alternate route

a) Partially in the Park - using current pipe down the gorge and along Malakoff Road b) Completely out of the Park – Malakoff Road c) Partially in the Park – Old Chiltern Road using existing track

slide-17
SLIDE 17

Option 2a

Partially in the Historic Park - using current pipe down the gorge and along Malakoff Road:

  • Cost estimate $8m to $10m
  • Approximately 4.5km of pipeline
  • Impacts Beechworth Historic Park
slide-18
SLIDE 18

Option 2a – Partially in the Historic Park – Malakoff Road

slide-19
SLIDE 19

Option 2b

Completely out of the Historic Park – a new pipeline along Malakoff Road

  • Cost estimate $15m
  • Approximately 10km of pipeline
  • No impact to Historic Park
slide-20
SLIDE 20

Option 2b – Completely out of the Historic Park

newater.com.au

slide-21
SLIDE 21

Option 2c

Partially in the Historic Park – route along Old Chiltern Road:

  • Cost estimate $8 - $10m
  • Approximately 4km of pipeline
  • Impacts Beechworth Historic Park
slide-22
SLIDE 22

Option 2c – Partially in the Historic Park – Old Chiltern Road

newater.com.au

slide-23
SLIDE 23

The community’s views…..

Would you prefer a tank or a new pipeline?

slide-24
SLIDE 24

Next steps

  • We will take your comments and views to our Board
  • We will undertake further concept planning & testing
  • Continue working with our stakeholders for approvals as

required

  • Board will make a decision in early 2017
  • NEW will advise the community of the Board’s decision