bayfront parkway
play

Bayfront Parkway Central Corridor Improvements Public Meeting - PowerPoint PPT Presentation

Bayfront Parkway Central Corridor Improvements Public Meeting August 7, 2019 Design Team PA Department of Transportation ms consultants, inc. Jim Foringer, District Executive Sean Sawford, Project Manager Brian McNulty,


  1. Bayfront Parkway Central Corridor Improvements Public Meeting – August 7, 2019

  2. Design Team PA Department of Transportation ms consultants, inc. • Jim Foringer, District Executive • Sean Sawford, Project Manager • Brian McNulty, Assistant District Executive – Design • Jim O’Mara, Project Engineer • Mark Nicholson, Project Manager Moore Design Associates, Inc. • Autumn Kelley, District Environmental Manager • Sara Moore, Landscape Architect • Brian Smith, District Traffic Engineer • Jill Harry, District Press Officer • Josh Kaufer, Safety Press Officer • Jennie Granger, Deputy Secretary for Multimodal Transportation August 7, 2019 www.BayfrontParkwayProject.com 2

  3. Bayfront Parkway Feasibility Study • Started in 2015 – Completed in 2017 • Established Project Advisory Committee (PAC) • Evaluated Current Functionality of Corridor • Defined Transportation Needs of the Entire Corridor • Developed Conceptual Improvements • www.BayfrontParkwayStudy.com August 7, 2019 www.BayfrontParkwayProject.com 3

  4. Ancillary Projects • 12 th Street Signal Improvements STATE STREET VIA: BAYFRONT PARKWAY 4 MIN 6 MIN 12TH STREET • ITS Signing at I-79 • East Side Safety Improvements August 7, 2019 www.BayfrontParkwayProject.com 5

  5. Working Meetings • • • Anchor Marine Ltd. EDP & Urban Engineers Lakeshore Towing / Wolverine Park Marina • • Bayfront East Side Taskforce (BEST) Erie City Council • MacDonald Illig Attorneys • • Bayfront Maritime Center Erie Community Foundation • Our West Bayfront (OWB) • • Bayshore Marine Services Erie County – Planning • PA Department of Community and • • BCP Properties Erie Downtown Development Economic Development (DCED) Corporation (EDDC) • Bike Erie • PA Rehab Council • Erie Downtown Partnership (EDP) • City of Erie – Bureau of Engineering • Passport Reality, LLC • Erie Events • City of Erie – Planning • Presque Isle Yacht Club • Erie Metropolitan Transit Authority • City of Erie – ADA Coordinator • Sidehill Copper Works, Inc. • Erie MPO • City of Erie – Mayor • UPMC Hamot • Erie School District • CSX Transportation • UPMC Hamot Emergency Services • Erie-Western PA Port Authority • EDP & Erie Arts and Culture • UPMC Hamot Police • Gannon University • EDP & Isaac Baker Menswear • UPMC Hamot Trauma • Harbor View Miniature Golf • EDP & Sherlock’s/Park Place • WMF / Scott Enterprises • EDP & UPMC Hamot August 7, 2019 www.BayfrontParkwayProject.com 6

  6. Common Themes Reduce Congestion Full Access at Enhance Safety State Street Remove the Bayfront “Barrier” Improve Multi-Modal Access Smart Land Use (Bikes/Peds/Transit) (Minimize R/W Impacts) 12 th Street Improvements August 7, 2019 www.BayfrontParkwayProject.com 7

  7. Current Status • Final Stages of Alternatives Analysis • Cultural Resource Investigations On-Going • CSX Coordination On-Going • Funding Opportunities • Public Meetings Conducted in Dec 2018 August 7, 2019 www.BayfrontParkwayProject.com 8

  8. Public Meetings Two (2) Open House Public Plans Displays Conducted: Date: December 4, 2018 Time: Noon to 8pm Location: Emerson Gridley School Gymnasium Date: December 11, 2018 Time: Noon to 8pm Location: Russian Orthodox Church of the Nativity Community Center August 7, 2019 www.BayfrontParkwayProject.com 9

  9. Public Meeting Feedback Purpose and Need Agree 40% Neutral 9% Strongly Agree 37% Disagree 4% Strongly Disagree 10% Do you generally agree with the identified Purpose and Need? August 7, 2019 www.BayfrontParkwayProject.com 10

  10. Refined Project Purpose and Need Purpose: The purpose of the project is to improve the pedestrian, bicycle, transit, and passenger vehicle connection of the Erie Central Business District and adjacent neighborhoods to the waterfront property north of the Bayfront Parkway, to reduce crashes as much as practical on the Bayfront Parkway, to improve future congestion to an acceptable level of service or delay, and to improve traffic operations and efficiency. August 7, 2019 www.BayfrontParkwayProject.com 11

  11. Refined Project Purpose and Need Needs: Mobility • Multimodal transportation connections are lacking • Inconsistent pedestrian and bicycle connections • Limited existing transit service • Bayfront Parkway acts as a barrier Safety • 80 crashes within 5-year period Operations & Efficiency • Poor existing and future Levels-of-Service (LOS) • Limited gaps for left turning vehicles August 7, 2019 www.BayfrontParkwayProject.com 12

  12. Public Meeting Feedback Sassafras Street Ext Alternatives Neutral Beneficial/ Very 14% Beneficial 37% Little/ No Little/ No Beneficial/ Benefit Benefit Very Beneficial/ Very 33% Little/ No 40% Beneficial Beneficial Benefit 61% 9% Neutral 77% 23% Neutral 6% No Build Roundabout Traffic Signal August 7, 2019 www.BayfrontParkwayProject.com 13

  13. Neutral 14% Beneficial/ Little/ No Very Benefit Beneficial 77% 9% No Build

  14. Little/ No Beneficial/ Benefit Very 33% Beneficial 61% Neutral 6% Roundabout

  15. Beneficial / Very Little/ Beneficial No 37% Benefit 40% Neutral 23% Traffic Signal

  16. Public Meeting Feedback State Street Alternatives Neutral Little/ No Little/ No 6% Benefit Benefit Beneficial/ Beneficial/ Very 23% 20% Very Beneficial Beneficial/ Very Little/ No Benefit Beneficial 73% Beneficial 90% 58% 4% Neutral 19% Neutral 7% No Build Traffic Signal Roundabout August 7, 2019 www.BayfrontParkwayProject.com 17

  17. Neutral 6% Beneficial/ Little/ No Benefit Very 90% Beneficial 4% No Build

  18. Little/ No Beneficial/ Benefit Very 20% Beneficial 73% Neutral 7% Roundabout

  19. Little/ No Benefit Beneficial/ 23% Very Beneficial Neutral 58% 19% Traffic Signal

  20. Public Meeting Feedback Holland Street Alternatives Neutral 12% Beneficial/ Very Beneficial/ Beneficial/ Little/ No Little/ No Beneficial Very Little/ No Very Benefit Benefit 8% Beneficial Benefit Beneficial 27% 29% 51% 80% 61% Neutral Neutral 12% 20% Roundabout No Build Traffic Signal August 7, 2019 www.BayfrontParkwayProject.com 21

  21. Neutral 12% Little/ No Benefit Beneficial/ 80% Very Beneficial 8% No Build

  22. Beneficial/ Little/ No Very Benefit Beneficial 27% 61% Neutral 12% Roundabout

  23. Beneficial Little/ No / Very Benefit Beneficial 29% 51% Neutral 20% Traffic Signal

  24. Alternative Evaluation Criteria Enhancements to Meets the Purpose Pedestrian & Bicycle Safety Improvement Public Input and Need Mobility Environmental Right-of-Way Utility Impacts Impacts Impacts Intersection Operation Visual Effects Constructability Construction Cost & Efficiency August 7, 2019 www.BayfrontParkwayProject.com 27

  25. Overall Estimated Project Costs Sassafras Street Ext $5.7M to $8.0M State Street $35.4M to $45.7M Holland Street $10.2M to $16.7M S&S Access Improvements $1.5M to $2.0M CSX Rail Relocations $4.5M to $5.0M CM / CI $5.0M to $6.5M Utility Relocations $0.5M to $1.0M Right-of-Way Acquisition $1.0M to $2.5M Engineering / Design $5.0M to $6.5M TOTAL $68.8M to $93.9M * High-level construction cost estimates subject to change based upon more detailed design and engineering. August 7, 2019 www.BayfrontParkwayProject.com 29

  26. Available Funding • $15 Million – State Appropriations 581 Fund – Secured • $17.6 Million – Federal Surface Transportation Program (STP) – Secured • $1.2 Million – Railroad Section 130 Fund – Secured • $25 Million – B.U.I.L.D. Grant – Submitted Application July 2019 (Better Utilizing Investments to Leverage Development) Potential Total = $58.8 Million August 7, 2019 www.BayfrontParkwayProject.com 30

  27. Tentative Project Schedule (BUILD Alternative) NOTE: PROJECT SCHEDULE SUBJECT TO CHANGE. August 7, 2019 www.BayfrontParkwayProject.com 33

  28. Open Discussion www.BayfrontParkwayProject.com www.facebook.com/groups/BayfrontParkwayProject/ August 7, 2019 www.BayfrontParkwayProject.com 34

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend