Barrier Removal Sediment Barrier Removal Sediment Management Management
Presentation to the Rivers Management Advisory Committee Presentation to the Rivers Management Advisory Committee May 9, 2011 May 9, 2011
Barrier Removal Sediment Barrier Removal Sediment Management - - PowerPoint PPT Presentation
Barrier Removal Sediment Barrier Removal Sediment Management Management Presentation to the Rivers Management Advisory Committee Presentation to the Rivers Management Advisory Committee May 9, 2011 May 9, 2011 General Dam Information
Presentation to the Rivers Management Advisory Committee Presentation to the Rivers Management Advisory Committee May 9, 2011 May 9, 2011
1. Barrier removal is beneficial to river health. 2. The total volume of potentially mobile impounded sediment is critical to the sediment management process. As such, the level
the volume of potentially mobile impounded sediment. 3. Projects with small amounts of potentially mobile impounded sediment and no or limited due diligence issues should be able to proceed with no contaminant testing. 4. Sediment assessment and management protocols should not always be determined on a case-by-case basis. A standardized sediment assessment and management protocol should be utilized until specific sediment volume or contamination thresholds are exceeded. 5. Natural erosion of the potentially mobile impounded sediment should be the preferred sediment management alternative unless conditions/ factors dictate otherwise.
Conduct due diligence review
Determine quantity and potential mobility of impounded sediment, and assess whether mobile portion of sediment is likely to “cause problems” downstream
Does due diligence review suggest contaminant or other issues? Is mobile portion of impounded sediment likely to “cause problems” downstream? No contaminant testing or sediment management required DRAFT Barrier Removal Sediment Assessment & Management Protocol Flow Chart
#1 #2 #3 #5
No Yes No Yes
#4
Yes
Conduct due diligence review
Determine quantity and potential mobility of impounded sediment, and assess whether mobile portion of sediment is likely to “cause problems” downstream
Does due diligence review suggest contaminant or other issues? Is mobile portion of impounded sediment likely to “cause problems” downstream? No contaminant testing or sediment management required DRAFT Barrier Removal Sediment Assessment & Management Protocol Flow Chart
#1 #2 #3 #5
No Yes No Yes
#4
Yes
Conduct due diligence review
Determine quantity and potential mobility of impounded sediment, and assess whether mobile portion of sediment is likely to “cause problems” downstream
Does due diligence review suggest contaminant or other issues? Is mobile portion of impounded sediment likely to “cause problems” downstream? No contaminant testing or sediment management required DRAFT Barrier Removal Sediment Assessment & Management Protocol Flow Chart
#1 #2 #3 #5
No Yes No Yes
#4
Yes
Conduct grain size analysis
Does >10% by weight of potentially mobile sediment pass the No.200 sieve? Is quantity of potentially mobile sediment >10,000 cubic yards? Consult with DES for site specific sediment contaminant testing protocol Conduct sediment screening
Do any chemical constituents exceed thresholds? Conduct sediment contaminant testing as follows:
potentially mobile sediment within impoundment*
*Contact DES if >10,000 cubic yards of potentially mobile coarse-grained sediment
Yes Yes No No Yes No
#6 #7 #8 #9 #10 #11 #12
Yes
No further contaminant testing required Go to Box #17 Do any of the sediment samples from the impoundment exceed contaminant thresholds? Conduct additional risk investigation Consult with DES! No Is the mobile portion of sediment likely to “cause problems” downstream? (per Box #4) Allow natural erosion of sediment via slow drawdown of impoundment
#13
No
#15
Do any of the sediment samples from the impoundment exceed background levels from the downstream sample? Yes No
#14 #16a
No
#17 #18
Yes
Sediment exceeding downstream background levels must be capped, stabilized, dredged or excavated! Consult with DES!
#16b
Yes
Dredge/excavate portion of mobile sediment and allow remainder to naturally erode (via slow drawdown of impoundment) Consult with DES! Natural erosion of sediment not allowed Cap, stabilize, dredge or excavate contaminated sediment Consult with DES! Less Problematic* More Problematic**
#19 #20
*Less Problematic – moderate sediment quantity concerns and no sediment quality concerns
**More Problematic – significant sediment quantity concerns and moderate sediment quality concerns