Monthly Stakeholder Meeting August 26, 2020 This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this


slide-1
SLIDE 1

Monthly Stakeholder Meeting August 26, 2020

slide-2
SLIDE 2

2

This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity

  • ther than FDOT staff is not official. Any questions can be sent to FDOT-

D6PIO@dot.state.fl.us. This presentation may not be altered.

slide-3
SLIDE 3

* This schedule does not reflect days added to the contract for holidays, weather days or special events

3

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

Ongoing nighttime closure on I-95 from NW 8 Street to NW 29 Street for concrete replacement on northbound and southbound lanes

slide-4
SLIDE 4

* This schedule does not reflect days added to the contract for holidays, weather days or special events

4

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

  • Total plan quantity of new concrete

pavement is: 118,720 Square Yards

  • Total new concrete pavement placed to

date is: 62,705 Square Yards

slide-5
SLIDE 5

* This schedule does not reflect days added to the contract for holidays, weather days or special events

5

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

NB I-95 bridge over SR 836 ramp (Bridge 108)

slide-6
SLIDE 6

* This schedule does not reflect days added to the contract for holidays, weather days or special events

6

THREE MONTH LOOK AHEAD

ANTICIPATED TRAFFIC SHIFTS ON THE I-95 CORRIDOR SR 836/I-395 Ramps to NB I-95 Traffic Shift – Shift ramp traffic to the east to continue roadwork – mid September 2020 NB I-95 Shift to Exit 4A – One

  • utside NB I-95 traffic lane will be

closed from NW 11 Street to north of NW 20 Street for a period of approximately three weeks to allow for the widening of EB SR 836 ramp to NB I-95. Exit 4A can be used to continue north – September 9, 2020.

slide-7
SLIDE 7

* This schedule does not reflect days added to the contract for holidays, weather days or special events

7

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

ANTICIPATED LANE CLOSURES ON THE I-95 CORRIDOR:

  • Nighttime lane/ramp closure along I-95 between NW 8 Street and NW

29 Street

  • Closure hours have been adjusted based on current traffic

conditions from 8 p.m. until 5:30 a.m.

slide-8
SLIDE 8

8

Ongoing widening of the eastbound SR 836 ramp to northbound I-95 (Bridge 107) for an additional lane. Anticipated completion: Summer 2021.

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

slide-9
SLIDE 9

9

Bridge widening on SR 836 near NW 10 Avenue

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

slide-10
SLIDE 10

10

Demolition of median area on SR 836 is ongoing west of the Miami River

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

slide-11
SLIDE 11

11

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

Bridge widening on SR 836 at NW 17 Avenue Sheet pile work on SB ramp to WB SR 836

slide-12
SLIDE 12

12

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

PILE FOUNDATIONS

  • Total of 91 piers requiring pile
  • foundations. 39 have been completed.
slide-13
SLIDE 13

13

AUGER CAST PILE (ACP) FOUNDATIONS

  • ACP installation ongoing at SR 836,

west of NW 12 Avenue.

  • Total of 492 ACP will be used for viaduct
  • foundations. 50 installed to date.

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

slide-14
SLIDE 14

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

14

ANTICIPATED LANE CLOSURES ON SR 836 CORRIDOR:

  • Single and double lane/ramp closures along eastbound and westbound SR

836

  • Arterial roads under SR 836
  • Closure hours have been adjusted based on current traffic conditions

from 8 p.m. until 6 a.m.

  • Single daytime lane closures on westbound SR 836 from 6 a.m. – 2 p.m.

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

slide-15
SLIDE 15

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

15

  • ACP installation for signature

bridge Arch # 4 foundation starting mid-September. Contractor preparing for Arch # 5 sheet pile.

  • Signature bridge center pier ACP

completed – Total 128/128

  • Ongoing ACP foundations for

Arches # 1, # 2 and bridge pier 1L – Total: 61/81

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

slide-16
SLIDE 16

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

16

  • Excavation of center pier foundation

underway.

  • Pouring of seal slab expected to take

place in mid/late September and will require 2,500+ CY of concrete. 250+ X

  • Mass concrete pour for the footer

scheduled for mid-December and will require 5000+ CY of concrete. 500+ X

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

slide-17
SLIDE 17

* This schedule does not reflect days added to the contract for holidays, weather days or special events

17

I-395 Segmental ACP – 355/857 I-395 Signature ACP – 189/520

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

slide-18
SLIDE 18

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

18

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

  • Total number of I-395 Columns: 94
  • Total number completed to date: 14
slide-19
SLIDE 19

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

19

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

Ongoing foundation and column construction adjacent to I-395 between NW 3 Avenue and NW 1 Avenue

slide-20
SLIDE 20

20

Segments erected to date: 36 Bridge segments for I-395 weigh between 50 and 93 tons each

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

slide-21
SLIDE 21

21

ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES

Weekend closures on Biscayne Boulevard for the installation of drainage structures and drainage pipes. Work will be done over two weekends and weeknights starting on Saturday, September 12.

slide-22
SLIDE 22

* This schedule does not reflect days added to the contract for holidays, weather days or special events

22

UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Traffic shift on Biscayne Boulevard from NE 13 Street to NE 11 Terrace. There will be three NB Lanes (two through lanes and one left turn lane onto NE 13 Street) and three SB Lanes (two through lanes and one left turn lane onto EB MacArthur Causeway). Close Bayshore loop ramp to EB MacArthur Causeway (September/October 2020).

1 1 2 2

slide-23
SLIDE 23

* This schedule does not reflect days added to the contract for holidays, weather days or special events

23

SEGMENTAL CASTING YARD Total Segments: 1949 Total Segments Cast to Date: 270

1

slide-24
SLIDE 24

SR 836 UPCOMING CONSTRUCTION ACTIVITIES

24

ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:

  • Lane closures along eastbound and westbound I-395
  • Lane closures along Biscayne Boulevard and other arterial roadways

adjacent to I-395

  • I-395 to I-95 ramp closures
  • Closure hours have been adjusted based on current traffic

conditions from 8 p.m. until 5:30 a.m.

ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD

slide-25
SLIDE 25

25

COMMUNITY OUTREACH

PROJECT WEBSITE

  • www.i-395miami.com
  • Sign-up for project alerts/updates

Lane closure information Upcoming construction activities Presentations

  • Calendar of events

OUTREACH OFFICE IN THE OVERTOWN COMMUNITY

  • 1035 NW 3 Avenue, Miami, Florida 33136 (CLOSED AT

THIS TIME DUE TO COVID 19) STAKEHOLDER MEETINGS

  • Stakeholder meetings will be held virtually until further
  • notice. Next meeting date: TBD