SLIDE 1
Monthly Stakeholder Meeting August 26, 2020
SLIDE 2 2
This PowerPoint presentation was prepared by the Florida Department of Transportation (FDOT) staff and has been made available to the public as part of public records access. Any dissemination of this presentation by anyone or entity
- ther than FDOT staff is not official. Any questions can be sent to FDOT-
D6PIO@dot.state.fl.us. This presentation may not be altered.
SLIDE 3
* This schedule does not reflect days added to the contract for holidays, weather days or special events
3
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
Ongoing nighttime closure on I-95 from NW 8 Street to NW 29 Street for concrete replacement on northbound and southbound lanes
SLIDE 4 * This schedule does not reflect days added to the contract for holidays, weather days or special events
4
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
- Total plan quantity of new concrete
pavement is: 118,720 Square Yards
- Total new concrete pavement placed to
date is: 62,705 Square Yards
SLIDE 5
* This schedule does not reflect days added to the contract for holidays, weather days or special events
5
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
NB I-95 bridge over SR 836 ramp (Bridge 108)
SLIDE 6 * This schedule does not reflect days added to the contract for holidays, weather days or special events
6
THREE MONTH LOOK AHEAD
ANTICIPATED TRAFFIC SHIFTS ON THE I-95 CORRIDOR SR 836/I-395 Ramps to NB I-95 Traffic Shift – Shift ramp traffic to the east to continue roadwork – mid September 2020 NB I-95 Shift to Exit 4A – One
- utside NB I-95 traffic lane will be
closed from NW 11 Street to north of NW 20 Street for a period of approximately three weeks to allow for the widening of EB SR 836 ramp to NB I-95. Exit 4A can be used to continue north – September 9, 2020.
SLIDE 7 * This schedule does not reflect days added to the contract for holidays, weather days or special events
7
ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD
ANTICIPATED LANE CLOSURES ON THE I-95 CORRIDOR:
- Nighttime lane/ramp closure along I-95 between NW 8 Street and NW
29 Street
- Closure hours have been adjusted based on current traffic
conditions from 8 p.m. until 5:30 a.m.
SLIDE 8
8
Ongoing widening of the eastbound SR 836 ramp to northbound I-95 (Bridge 107) for an additional lane. Anticipated completion: Summer 2021.
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
SLIDE 9
9
Bridge widening on SR 836 near NW 10 Avenue
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
SLIDE 10
10
Demolition of median area on SR 836 is ongoing west of the Miami River
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
SLIDE 11
11
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
Bridge widening on SR 836 at NW 17 Avenue Sheet pile work on SB ramp to WB SR 836
SLIDE 12 12
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
PILE FOUNDATIONS
- Total of 91 piers requiring pile
- foundations. 39 have been completed.
SLIDE 13 13
AUGER CAST PILE (ACP) FOUNDATIONS
- ACP installation ongoing at SR 836,
west of NW 12 Avenue.
- Total of 492 ACP will be used for viaduct
- foundations. 50 installed to date.
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
SLIDE 14 SR 836 UPCOMING CONSTRUCTION ACTIVITIES
14
ANTICIPATED LANE CLOSURES ON SR 836 CORRIDOR:
- Single and double lane/ramp closures along eastbound and westbound SR
836
- Arterial roads under SR 836
- Closure hours have been adjusted based on current traffic conditions
from 8 p.m. until 6 a.m.
- Single daytime lane closures on westbound SR 836 from 6 a.m. – 2 p.m.
ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD
SLIDE 15 SR 836 UPCOMING CONSTRUCTION ACTIVITIES
15
- ACP installation for signature
bridge Arch # 4 foundation starting mid-September. Contractor preparing for Arch # 5 sheet pile.
- Signature bridge center pier ACP
completed – Total 128/128
- Ongoing ACP foundations for
Arches # 1, # 2 and bridge pier 1L – Total: 61/81
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
SLIDE 16 SR 836 UPCOMING CONSTRUCTION ACTIVITIES
16
- Excavation of center pier foundation
underway.
- Pouring of seal slab expected to take
place in mid/late September and will require 2,500+ CY of concrete. 250+ X
- Mass concrete pour for the footer
scheduled for mid-December and will require 5000+ CY of concrete. 500+ X
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
SLIDE 17
* This schedule does not reflect days added to the contract for holidays, weather days or special events
17
I-395 Segmental ACP – 355/857 I-395 Signature ACP – 189/520
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
SLIDE 18 SR 836 UPCOMING CONSTRUCTION ACTIVITIES
18
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
- Total number of I-395 Columns: 94
- Total number completed to date: 14
SLIDE 19
SR 836 UPCOMING CONSTRUCTION ACTIVITIES
19
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
Ongoing foundation and column construction adjacent to I-395 between NW 3 Avenue and NW 1 Avenue
SLIDE 20
20
Segments erected to date: 36 Bridge segments for I-395 weigh between 50 and 93 tons each
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
SLIDE 21
21
ONGOING AND UPCOMING CONSTRUCTION ACTIVITIES
Weekend closures on Biscayne Boulevard for the installation of drainage structures and drainage pipes. Work will be done over two weekends and weeknights starting on Saturday, September 12.
SLIDE 22
* This schedule does not reflect days added to the contract for holidays, weather days or special events
22
UPCOMING & ONGOING CONSTRUCTION ACTIVITIES Traffic shift on Biscayne Boulevard from NE 13 Street to NE 11 Terrace. There will be three NB Lanes (two through lanes and one left turn lane onto NE 13 Street) and three SB Lanes (two through lanes and one left turn lane onto EB MacArthur Causeway). Close Bayshore loop ramp to EB MacArthur Causeway (September/October 2020).
1 1 2 2
SLIDE 23
* This schedule does not reflect days added to the contract for holidays, weather days or special events
23
SEGMENTAL CASTING YARD Total Segments: 1949 Total Segments Cast to Date: 270
1
SLIDE 24 SR 836 UPCOMING CONSTRUCTION ACTIVITIES
24
ANTICIPATED NIGHTTIME LANE CLOSURES ON I-395 CORRIDOR:
- Lane closures along eastbound and westbound I-395
- Lane closures along Biscayne Boulevard and other arterial roadways
adjacent to I-395
- I-395 to I-95 ramp closures
- Closure hours have been adjusted based on current traffic
conditions from 8 p.m. until 5:30 a.m.
ONGOING LANE CLOSURES THREE MONTH LOOK AHEAD
SLIDE 25 25
COMMUNITY OUTREACH
PROJECT WEBSITE
- www.i-395miami.com
- Sign-up for project alerts/updates
Lane closure information Upcoming construction activities Presentations
OUTREACH OFFICE IN THE OVERTOWN COMMUNITY
- 1035 NW 3 Avenue, Miami, Florida 33136 (CLOSED AT
THIS TIME DUE TO COVID 19) STAKEHOLDER MEETINGS
- Stakeholder meetings will be held virtually until further
- notice. Next meeting date: TBD
SLIDE 26
786-280-0983 OGonzalez@mrgmiami.com Contact: Oscar Gonzalez
www.i-395miami.com
THANK YOU!
26