project update
play

Project Update Dal Hawks | Project Director 09/03/2009 Progress - PowerPoint PPT Presentation

Project Update Dal Hawks | Project Director 09/03/2009 Progress Update June - October: November 19: Winter 2010: Spring 2010: December: DB Proposal DB Proposals Design / Construction Selection Development Due Mobilization Starts


  1. Project Update Dal Hawks | Project Director 09/03/2009

  2. Progress Update June - October: November 19: Winter 2010: Spring 2010: December: DB Proposal DB Proposals Design / Construction Selection Development Due Mobilization Starts • Proposer one-on-one meetings ongoing • Design-Build proposals due in 11 weeks

  3. Procurement Schedule  Released RFQ (www.i15core.utah.gov): Apr 16  Design builders submit SOQs: May 14  Short list design builders: May 28  Commission endorsement of values statement: May  Issue RFP: Jun 16  Conduct industry outreach and technical proposal discussions: Jun 17 to Oct 30 • Issue final RFP addendum: Oct 13 • Design builders submit proposals: Nov 19 • Select design builder: December • Start construction: Spring 2010

  4. Expansion from American Fork to Provo

  5. Fixed Price/Best Design Approach • Analysis of DB approaches led to Fixed Price/Best Design method • Bidders develop highest-value, creative solution for fixed construction budget • Proposals evaluated on meeting or exceeding defined criteria

  6. Selection Criteria • Proposals are evaluated by defined criteria: – Technical, must-have requirements – Pass/Fail elements – Project goals and values

  7. Three Design-Build Proposers • Three teams short-listed to bid on I-15 CORE – Committed: Fully engaged in the process; Developing unique plans and solutions – Competent: partnerships of local, national and international firms with successful design-build experience – Competitive: process is driving innovation and increased value

  8. Flatiron-Skanska-Zachry • Flatiron Constructors • Project Engineering Consultants (PEC) • Skanska USA Civil West • Resource Systems Group California District (RSG) • Zachry Construction • Stanley Consultants Corportation • CH2M Hill • Earthtec Testing and Environmental • AECOM Inc • Dr. T Leslie Youd Consultant • AMEC Earth and Environmental

  9. Provo River Constructors • Fluor Enterprises • Intermountain GeoEnvironmental Services • Ames Construction Company • CRS Consulting Engineers • Ralph L. Wadsworth • Raba-Kistner Consultants Construction Company • Wadsworth Brothers • TransCore IP Construction Company • Stillwell & Associates • Fluor/HDR Global Design • Applied Research Associates Consultants • Fehr & Peers Transportation • Michael Baker Jr. Consultants • Jacobs Engineering Group • Psomas • H.W. Lochner • CME Transportation Group • Kleinfelder West

  10. Timpanogos Transportation Constructors • Kiewit Western Co. • GeoEngineers • Granite Construction • Shannon & Wilson Company • Stantec • W.W. Clyde & Co. • SWCA Environmental • Parsons Transportation Consultants Group • TBE Group • PB Americas • Terracon Consultants • Wasatch Electric (a division • URS Corporation of Dynalectric) • Utility Mapping Services • Apex Design, PC • Bowen, Collins & Associates

  11. Maintenance of Traffic • Project Goal: Minimize inconvenience to the public - Strict contract requirements regarding MOT - UDOT will evaluate and score design-build team MOT plans as part of the selection process - Design-build MOT plans become contractual requirements - Public information and education is a top priority

  12. Mainline I-15 MOT Requirements • Peak Period Full Closure : not allowed • Off-Peak Full Closure : not allowed during Holiday Period or Civic Event Period • Peak Period Partial Closure : maintain minimum of 2 or 3 lanes in each direction (one lane fewer than existing) • Off-Peak Partial Closure : – Maintain a minimum of 2 lanes in each direction – Limited allowance to reduce to 1 lane – Not allowed during Holiday Period or Civic Event Period

  13. Ramp MOT Requirements • Full or Partial Closure: not allowed at consecutive on-ramps or consecutive off-ramps • Full Closure: not allowed at SR-77, SR-75, University Ave, University Parkway, Pleasant Grove Blvd, American Fork Main, Lehi Main • Long-Term Full Closure : generally 30-90 days, specific to proposers’ plans

  14. Cross Street MOT Requirements • Full or Partial Closure : limited to ensure that all cross streets in an area are not closed at the same time • Long-Term Full Closure : limited to certain cross streets for pre-determined durations • Short-Term Full Closure : limited to cross streets passing under I-15

  15. Proposal Stage Form F: Sheets F-1 through F-6: Contractor provides Long-Term Closure durations in boxes for each element

  16. Proposal Stage MOT Evaluation – Regional mobility modeled for proposed phasing and closures

  17. Public Notification of Closures • Design-Builder is responsible for providing advance notice of all closures • UDOT is responsible for disseminating the information to the public • Public notified via: – News media – E-mail – Text messaging – Web site – Roadway signs – Radio

  18. For More Information: Phone: 1-888-i15core (1-888-415-2673) Email: i15core@utah.gov Website: www.i15core.utah.gov

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend