  2. AGENDA A BAY VIEW ELEMENTARY SCHOOL A DE LAVEAGA ELEMENTARY SCHOOL A BRANCIFORTE SMALL SCHOOLS A NATURAL BRIDGES A SOQUEL HIGH SCHOOL MADI ARCHITECTS + PLANNERS

  3. BAY VIEW ELEMENTARY SCHOOL MADI ARCHITECTS + PLANNERS

  4. Bay View Elementary School – Measure B PROJECT START COMPLETE PROJECT BUDGET Multi-Project Overhead ONGOING ONGOING $689,100 Re-Roofing COMPLETE COMPLETE $925,529 New Kindergarten Building & Site Work TBD TBD $1,587,408 New Classroom Building & Site Work 02/01/2019 11/02/2019 $3,574,686 Modernization-Phase 1 04/01/2020 08/31/2020 $2,684,000 Modernization-Phase 2 09/01/2020 12/31/2020 $2,684,000 Portable Demolition & Site Work 06/15/2021 08/23/2021 $732,000 Card Access Security System 06/10/2019 08/21/2020 $190,000 Data Infrastructure Improvements 06/10/2019 08/21/2020 $300,000 Fire Line 06/10/2019 08/21/2020 $488,000 PROJECT BUDGETS MADI Bay View Elementary School Bond Projects ARCHITECTS + PLANNERS

  5. PREVIOUSLY COMPLETED - REROOFING MADI Bay View Elementary School Bond Projects ARCHITECTS + PLANNERS

  6. PREVIOUSLY COMPLETED – PLAYGROUND RESURFACING MADI Bay View Elementary School Bond Projects ARCHITECTS + PLANNERS

  7. RECENTLY COMPLETED – NEW CLASSROOM BUILDING MADI Bay View Elementary School Bond Projects ARCHITECTS + PLANNERS

  8. RECENTLY COMPLETED – NEW CLASSROOM BUILDING MADI Bay View Elementary School Bond Projects ARCHITECTS + PLANNERS

  9. CLASSROOM MODERNIZATION STANDARD CLASSROOM FLOOR PLAN PENDANT LIGHTING ROLLER SHADES UPCOMING PROJECT – CLASSROOM MODERNIZATION MADI Bay View Elementary School Bond Projects ARCHITECTS + PLANNERS

  10. DELAVEAGA ELEMENTARY SCHOOL MADI ARCHITECTS + PLANNERS

  11. DeLaveaga Elementary School – Measure B PROJECT START COMPLETE PROJECT BUDGET Multi-Project Overhead ONGOING ONGOING $743,092 New Shade Structure & Parking Lot COMPLETE COMPLETE $1,600,000 New Classroom Building & Site Work 06/15/2019 11/02/2019 $3,670,192 Modernization-Phase 1 05/01/2020 08/31/2020 $3,599,000 Modernization-Phase 2 09/01/2020 12/31/2020 $3,599,000 Re-Roofing 06/15/2020 08/23/2021 $355,439 Portable Demolition & Site Work 06/15/2021 08/23/2021 $854,000 Card Access Security System 06/10/2019 08/21/2020 $190,000 Data Infrastructure Improvements 06/10/2019 08/21/2020 $300,000 PROJECT BUDGETS MADI DeLaveaga Elementary School Bond Projects ARCHITECTS + PLANNERS

  12. PREVIOUSLY COMPLETED – PARKING LOT & SHADE STRUCTURE MADI DeLaveaga Elementary School Bond Projects ARCHITECTS + PLANNERS

  13. RECENTLY COMPLETED – NEW CLASSROOM BUILDING MADI DeLaveaga Elementary School Bond Projects ARCHITECTS + PLANNERS

  14. RECENTLY COMPLETED – NEW CLASSROOM BUILDING MADI DeLaveaga Elementary School Bond Projects ARCHITECTS + PLANNERS

  15. RECENTLY COMPLETED – NEW CLASSROOM BUILDING MADI DeLaveaga Elementary School Bond Projects ARCHITECTS + PLANNERS

  16. CLASSROOM MODERNIZATION PENDANT LIGHTING ROLLER SHADES STANDARD CLASSROOM FLOOR PLAN UPCOMING PROJECT – CLASSROOM MODERNIZATION MADI DeLaveaga Elementary School Bond Projects ARCHITECTS + PLANNERS

  17. NATURAL BRIDGES MADI ARCHITECTS + PLANNERS

  18. Natural Bridges Campus – Measure B PROJECT START COMPLETE PROJECT BUDGET Multi-Project Overhead ONGOING ONGOING $272,682 Campus Re-Roofing COMPLETE COMPLETE $1,438,440 Gymnasium Interior Modifications & Parking Lot COMPLETE COMPLETE $533,626 Exterior Gym Repairs & Modular Restroom 08/16/2019 11/02/2019 $586,243 Repainting & Repairs COMPLETE COMPLETE $203,740 PROJECT BUDGETS MADI Natural Bridges Bond Projects ARCHITECTS + PLANNERS

  19. PREVIOUSLY COMPLETED – RE-ROOFING OF THE MAIN BUILDING MADI Natural Bridges Bond Projects ARCHITECTS + PLANNERS

  20. PREVIOUSLY COMPLETED – CAMPUS RE-PAINTING MADI Natural Bridges Bond Projects ARCHITECTS + PLANNERS

  21. PREVIOUSLY COMPLETED – GYMNASIUM INTERIOR MODIFICATIONS MADI Natural Bridges Bond Projects ARCHITECTS + PLANNERS

  22. RECENTLY COMPLETED – MODULAR RESTROOM MADI Natural Bridges Bond Projects ARCHITECTS + PLANNERS

  23. ONGOING PROJECT – GYMNASIUM EXTERIOR MODIFICATIONS MADI Natural Bridges Bond Projects ARCHITECTS + PLANNERS

  24. BRANCIFORTE SMALL SCHOOLS MADI ARCHITECTS + PLANNERS

  25. Branciforte Small Schools – Measure A & B PROJECT START COMPLETE PROJECT BUDGET Multi-Project Overhead ONGOING ONGOING $521,068 Relocated Playground, Shade Structure & Ramp COMPLETE COMPLETE $740,215 New Classroom Building & Site Work 02/01/2019 11/02/2019 $3,452,475 Alternative Family Education Campus TBD TBD $2,484,569 Modernization-Phase 1 06/30/2020 12/31/2020 $1,159,000 Modernization-Phase 2 01/01/2021 08/23/2021 $902,800 Portable Demolition & Site Work 06/15/2021 08/23/2021 $671,000 Card Access Security System 06/10/2019 08/21/2020 $135,000 Data Infrastructure Improvements 06/10/2019 08/21/2020 $250,000 PROJECT BUDGETS MADI Branciforte Small Schools Bond Projects ARCHITECTS + PLANNERS

  26. PREVIOUSLY COMPLETED – RELOCATED PLAYGROUND MADI Branciforte Small Schools Bond Projects ARCHITECTS + PLANNERS

  27. PREVIOUSLY COMPLETED – ADA RAMP TO MAIN BUILDING MADI Branciforte Small Schools Bond Projects ARCHITECTS + PLANNERS

  28. STORAGE STORAGE SPECIAL ED. CLASSROOM INTERVENTION CLASSROOM FUTURE PORTABLE DEMOLITION AND OFFICE PLAYGROUND EXPANSION SPECIAL ED. CLASSROOM OFFICE STORAGE MUSIC WEIGHTS ART OFFICE STORAGE OFFICE RECENTLY COMPLETED – NEW CLASSROOM BUILDING MADI Branciforte Small Schools Bond Projects ARCHITECTS + PLANNERS

  29. RECENTLY COMPLETED – NEW CLASSROOM BUILDING MADI Branciforte Small Schools Bond Projects ARCHITECTS + PLANNERS

  30. 1 st FLOOR CLASSROOM MODERNIZATION UPCOMING PROJECT – CLASSROOM MODERNIZATION MADI Branciforte Small Schools Bond Projects ARCHITECTS + PLANNERS

  31. 2 ND FLOOR CLASSROOM MODERNIZATION UPCOMING PROJECT – CLASSROOM MODERNIZATION MADI Branciforte Small Schools Bond Projects ARCHITECTS + PLANNERS

  32. 3 RD FLOOR CLASSROOM MODERNIZATION UPCOMING PROJECT – CLASSROOM MODERNIZATION MADI Branciforte Small Schools Bond Projects ARCHITECTS + PLANNERS

  33. UPCOMING PROJECT – NEW ELEVATOR MADI Branciforte Small Schools Bond Projects ARCHITECTS + PLANNERS

  34. SOQUEL HIGH SCHOOL MADI ARCHITECTS + PLANNERS

  35. Soquel High School – Measure A PROJECT START COMPLETE PROJECT BUDGET Multi-Project Overhead ONGOING ONGOING $1,703,567 Pool (by Belli) COMPLETE COMPLETE $7,502,688 Site Infrastructure COMPLETE COMPLETE $3,256,100 New Concessions Building & Ramp TBD TBD $1,842,438 Tennis Courts COMPLETE COMPLETE $221,361 Modernization Phase 1: Reverse TI COMPLETE COMPLETE $366,000 Modernization Phase 2: Wing 100 08/16/2019 12/31/2019 $6,097,267 Modernization Phase 3: Wing 200 01/01/2020 08/23/2020 $5,878,867 Modernization Phase 4: Wing 300 TBD TBD $3,000,000 Site Work 06/08/2020 08/23/2020 $610,000 Card Access Security System 06/10/2019 08/21/2020 $310,000 Data Infrastructure Improvements 06/10/2019 08/21/2020 $700,000 Fields (Sunk Cost) - - $1,527,272 PROJECT BUDGETS MADI Soquel High School Bond Projects ARCHITECTS + PLANNERS

  36. PREVIOUSLY COMPLETED – TENNIS COURT RESURFACING MADI Soquel High School Bond Projects ARCHITECTS + PLANNERS

  37. RECENTLY COMPLETED– SITE INFRASTRUCTURE & FIRE ROAD MADI Soquel High School Bond Projects ARCHITECTS + PLANNERS

  38. RECENTLY COMPLETED – WING 300 MODERNIZATION (REVERSE T&I) MADI Soquel High School Bond Projects ARCHITECTS + PLANNERS

  39. ONGOING ITEMS: • EXTERIOR PARITIONS • ONGOING COUNTY HEALTH DEPT. REVIEW CONSTRUCTION 95% COMPLETE ONGOING CONSTRUCTION– CONCESSIONS BUILDING & ADA RAMP MADI Soquel High School Bond Projects ARCHITECTS + PLANNERS

  40. SCOPE:  ADMINISTRATION UPGRADES  LIBRARY MODERNIZATION  CLASSROOM MODERNIZATION  SPECIAL EDUCATION  WORLD LANGUAGE  ENGLISH  MATH KEY DATES:  ADMINISTRATION & LIBRARY  AUGUST 2019 START  NOVEMBER 2019 COMPLETE  CLASSROOMS  AUGUST 2019 START  DECEMBER 2019 COMPLETION ONGOING CONSTRUCTION – WING 100 MODERNIZATION MADI Soquel High School Bond Projects ARCHITECTS + PLANNERS

  41. ADMINISTRATION CONSTRUCTION ADMINISTRATION CARPET LAYOUT ONGOING CONSTRUCTION – WING 100 MODERNIZATION (ADMINISTRATION) MADI Soquel High School Bond Projects ARCHITECTS + PLANNERS

  42. LIBRARY RENDER LIBRARY MODERNIZATION ONGOING CONSTRUCTION – WING 100 MODERNIZATION (LIBRARY) MADI Soquel High School Bond Projects ARCHITECTS + PLANNERS

  43. ONGOING CONSTRUCTION – WING 100 MODERNIZATION MADI Soquel High School Bond Projects ARCHITECTS + PLANNERS

  44. SCOPE:  CLASSROOM MODERNIZATION  SCIENCE  COMPUTER LABS  SPECIAL EDUCATION  WORLD LANGUAGE  ENGLISH KEY DATES:  JANUARY 2020 START  AUGUST 2020 COMPLETION UPCOMING PROJECT – WING 200 MODERNIZATION MADI Soquel High School Bond Projects ARCHITECTS + PLANNERS

  45. THANK YOU! MADI ARCHITECTS + PLANNERS

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend