Mission Hill Middle School Santa Cruz High School SANTA CRUZ - - PowerPoint PPT Presentation

mission hill middle school
SMART_READER_LITE
LIVE PREVIEW

Mission Hill Middle School Santa Cruz High School SANTA CRUZ - - PowerPoint PPT Presentation

Gault Elementary School Westlake Elementary School Mission Hill Middle School Santa Cruz High School SANTA CRUZ CITY SCHOOLS | BOARD MEETING 18 OCTOBER 2017 Measure A | B Update: GWMS Process Meetings with Site


slide-1
SLIDE 1

SANTA CRUZ CITY SCHOOLS | BOARD MEETING – 18 OCTOBER 2017

  • Gault Elementary School
  • Westlake Elementary School
  • Mission Hill Middle School
  • Santa Cruz High School
slide-2
SLIDE 2

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n | s u s t a i n a b i l i t y

Process

  • Meetings with Site “planning review committees” to review site needs and

priorities

  • On site existing conditions documentation
  • Development of “projects”
  • Define Projects
  • Scope
  • Schedules
  • Anticipated economic need (costs)

Measure A | B Update: GWMS

slide-3
SLIDE 3

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n | s u s t a i n a b i l i t y

Site Planning | Prioritization Meetings

Measure A | B Update: GWMS

  • 11 May 2017
  • 30 May 2017
  • 05 Sept 2017
  • 16 Oct 2017
  • 13 June 2017
  • 28 August 2017
  • 11 Oct 2017
  • TBD Oct 2017
  • 16 March 2017
  • 06 June 2017
  • 28 August 2017
  • 19 Oct 2017
  • 01 June 2017
  • 11 Sept 2017
  • 02 Oct 2017
  • TBD Oct 2017

Westlake SCHS

slide-4
SLIDE 4

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Gault Elementary School GAULT ELEMENTARY SCHOOL

slide-5
SLIDE 5

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Site/Project Planning

Measure A | B Update Gault Elementary School

slide-6
SLIDE 6

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Site/Project Planning

Measure A | B Update Gault Elementary School

slide-7
SLIDE 7

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Site/Project Planning

Measure A | B Update Gault Elementary School

slide-8
SLIDE 8

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Gault Elementary School

slide-9
SLIDE 9

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Initiating Project Status

Miscellaneous/Utilities/Life Cycle

  • Initial basement water intrusion repair: Procurement process

Roofing

  • Main Building Tile Roof replacement: DSA Review. Bid Late fall for construction summer 2018

HVAC

  • Main building AC/heat improvements: Scope development

Main building modernization

  • Project scope under development

Potential New building (replace portables)

  • Project scope, feasibility, program under development in consultation with site team

Measure A | B Update Gault Elementary School

slide-10
SLIDE 10

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Roof Replacement Phase 1

Measure A | B Update Gault Elementary School

Tile Roof Replacement

slide-11
SLIDE 11

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

WESTLAKE ELEMENTARY SCHOOL Measure A | B Update Westlake Elementary School

slide-12
SLIDE 12

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Westlake Elementary School

Site/Project Planning

slide-13
SLIDE 13

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Site/Project Planning

Measure A | B Update Westlake Elementary School

slide-14
SLIDE 14

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Westlake Elementary School

slide-15
SLIDE 15

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Westlake Elementary School

Initiating Project Status

Miscellaneous site projects:

  • Accessible walkway to upper classroom wing: Schematic Design
  • Accessible lift/walkways between levels. Schematic Design

Modernization:

  • Lower building and upper building: project scope, program under development in consultation

with site team

Portable Replacement/New classrooms

  • Proposed lower building and upper building addition: project scope, program under

development in consultation with site team

slide-16
SLIDE 16

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Mission Hill Middle School MISSION HILL MIDDLE SCHOOL

slide-17
SLIDE 17

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Mission Hill Middle School

Site/Project Planning

slide-18
SLIDE 18

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Mission Hill Middle School

Site/Project Planning

slide-19
SLIDE 19

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Mission Hill Middle School

slide-20
SLIDE 20

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Initiating Project Status

Main Entrance Improvements

  • Front Lawn Landscaping : Bids due October 24
  • Monument Sign: Final design / procurement phase
  • Covered waiting area: Final design/procurement phase

Roofing

  • Main Building Tile Roof replacement: DSA Review. Bid Late fall for construction summer 2018
  • Main Building flat roof replacement: Design

HVAC

  • Main building AC/heat improvements (in conjunction with roofing): Design, Construction

summer 2018

Gymnasium

  • Initial locker room improvements. Floor finishes. Anticipated construction winter break

Main building modernization

  • Initial project scope under development

Potential New building

  • Project scope, feasibility, program under development in consultation with site team

Measure A | B Update Mission Hill Middle School

slide-21
SLIDE 21

1 8 O c t o b e r 2 0 1 7

Front Lawn Landscape Improvements

c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

  • Accessible Walkway
  • Plaza and Landscaping
  • Tree Planters/Benches
  • New side entrance stair
  • Waiting area trellis
  • Monument sign

Measure A | B Update Mission Hill Middle School

slide-22
SLIDE 22

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Roof Replacement Phase 1

Measure A | B Update Mission Hill Middle School

slide-23
SLIDE 23

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Santa Cruz High School SANTA CRUZ HIGH SCHOOL

slide-24
SLIDE 24

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Santa Cruz High School

Site/Project Planning

slide-25
SLIDE 25

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Santa Cruz High School

Site/Project Planning

slide-26
SLIDE 26

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Santa Cruz High School

slide-27
SLIDE 27

1 8 O c t o b e r 2 0 1 7 c o l l a b o r a t i o n | a d v o c a c y | r e s e a r c h | e d u c a t i o n

Measure A | B Update Santa Cruz High School

Miscellaneous site projects:

  • Water intrusion improvements. Program under development. Potential construction summer 2018
  • Miscellaneous site fencing repair. Construction winter 2017-18
  • Site fencing improvements: Schematic design study underway. Potential improvements during

2017-18 school year

Gymnasium:

  • Cosmetic improvements: Program development, schematic design and procurement: Construction

winter 2017/18 and summer 2018

  • Improvements: Program development/schematic design initiated

Modernization:

  • Science Building: Program development in consultation with site team under way. Construction

summer 2018

  • Main building modernization: Program/scope under development with site team. (plumbing/utilities)

Initiating Project Status