Amendment to Application for 28-30 East 92nd Street: Change in Brownstone Repair and Replacement Scope Due to Field Conditions Nightingale-Bamford School Facade of 28-30 East 92nd Street, New York BRB Architects October 20, 2015 Summary of


slide-1
SLIDE 1

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York October 20, 2015

Amendment to Application for 28-30 East 92nd Street: Change in Brownstone Repair and Replacement Scope Due to Field Conditions

slide-2
SLIDE 2

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

Summary of Application

October 20, 2015

slide-3
SLIDE 3

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

Front View from E 92nd Street View from Far Corner of Madison Ave. & E 92nd Street

October 20, 2015

slide-4
SLIDE 4

October 20, 2015

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

6th Floor Terrace Guardrail Stair Bulkhead Acoustic Screen 1b Acoustic Canopy Acoustic Screen 2 Acoustic Screen 1a

Existing Proposed

slide-5
SLIDE 5

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York October 20, 2015

Existing Proposed

slide-6
SLIDE 6

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

Proposed Front Elevation

October 20, 2015

slide-7
SLIDE 7

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

Brownstone Field Conditions

October 20, 2015

slide-8
SLIDE 8

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

PHOTO DOCUMENTATION

October 20, 2015

slide-9
SLIDE 9

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

PHOTO DOCUMENTATION

October 20, 2015

slide-10
SLIDE 10

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

PHOTO DOCUMENTATION

October 20, 2015

slide-11
SLIDE 11

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

PHOTO DOCUMENTATION

October 20, 2015

slide-12
SLIDE 12

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

VIDEO DOCUMENTATION

Video Link

October 20, 2015

slide-13
SLIDE 13

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

B

LEGEND

Pieces that must be replaced with precast Pieces that must be taken down, scratch-coated and fully patched, and reinstalled Pieces to remain in place Area where original material was lost, to be replaced with precast Pieces that must be taken down, partially patched, and reinstalled Pieces that must be taken down and reinstalled Pieces that must be scratch-coated and fully patched in place

Scope of Brownstone Repair & Replacement Maximizing Retention of Original Material and Substrates

MASONRY CORNICE

October 20, 2015

slide-14
SLIDE 14

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

Proposed Solution

October 20, 2015

slide-15
SLIDE 15

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

A

Scope of Brownstone Repair & Replacement per Original Application

October 20, 2015

MASONRY CORNICE MASONRY CORNICE

B

Scope of Brownstone Repair & Replacement Maximizing Retention of Original Material and Substrates

LEGEND

Pieces that must be replaced with precast Pieces that must be taken down, scratch-coated and fully patched, and reinstalled Pieces to remain in place Area where original material was lost, to be replaced with precast Pieces that must be taken down, partially patched, and reinstalled Pieces that must be taken down and reinstalled Pieces that must be scratch-coated and fully patched in place

slide-16
SLIDE 16

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

A

LEGEND

Pieces that were to be replaced with precast Pieces that were to be unaltered Area where original material was lost, that were to be replaced with precast Pieces that were to be scratch-coated and fully patched in place

Scope of Brownstone Repair & Replacement per Original Application

MASONRY CORNICE

October 20, 2015

slide-17
SLIDE 17

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

B

LEGEND

Pieces that must be replaced with precast Pieces that must be taken down, scratch-coated and fully patched, and reinstalled Pieces to remain in place Area where original material was lost, to be replaced with precast Pieces that must be taken down, partially patched, and reinstalled Pieces that must be taken down and reinstalled Pieces that must be scratch-coated and fully patched in place

Scope of Brownstone Repair & Replacement Maximizing Retention of Original Material and Substrates

MASONRY CORNICE

October 20, 2015

slide-18
SLIDE 18

Nightingale-Bamford School

BRB Architects Facade of 28-30 East 92nd Street, New York

MASONRY CORNICE

October 20, 2015

C

Proposed Scope of 100% Brownstone Replacement with Cast Stone (See Samples)