agenda schedule budget design update schedule completed
play

Agenda Schedule Budget Design Update Schedule Completed Design - PowerPoint PPT Presentation

COLONIAL BEACH PUBLIC SCHOOLS NEW ELEMENTARY SCHOOL Progress Update February 17, 2016 Agenda Schedule Budget Design Update Schedule Completed Design Meeting January 11, 2016 Schematic Design Deliverable January


  1. COLONIAL BEACH PUBLIC SCHOOLS NEW ELEMENTARY SCHOOL Progress Update February 17, 2016

  2. Agenda • Schedule • Budget • Design Update

  3. Schedule – Completed − Design Meeting – January 11, 2016 − Schematic Design Deliverable – January 15, 2016 − Request for Qualifications for General Contractors – January 22, 2016 − Meeting with Dominion Power – January 28, 2016 − Site Plan submission and CUP application to Town – February 5, 2016 − Water Systems Design Meeting with Town – February 9, 2016

  4. Schedule – Upcoming − RFQ responses due February 18, 2016 − Design Development Submission – March 14, 2016 − Dominion Design Proposal for HS Power Line Relocation – TBD

  5. Budget − CBPS is working with the e-Rate program to obtain funding for IT- related items − Skanska and RRMM have worked together to identify cost savings measures that do not impact program in order to remain within budget − Project remains within budget of $8,500,000

  6. SITE / FLOOR PLAN

  7. FLOOR PLAN

  8. MAIN ENTRANCE

  9. SITE PLAN FOR TOWN REVIEW Site Plan Updates:  Emergency vehicle connection to First Street  Water connections to two locations  Sanitary sewer connection at Jackson Street  Dominion Va Power route for electrical service to ES  Dominion Va Power conduit for relocated HS service

  10. FLOOR PLAN

  11. FLOOR PLAN Artifacts:  School bell  Gym floor section with logo  Salvaged brick

  12. GYM AND CAFETERIA PLAN Artifacts:  School bell  Gym floor section with logo  Salvaged brick walls, with descriptive plaques

  13. TYPICAL CLASSROOMS TYPICAL CLASSROOMS

  14. TYPICAL CLASSROOMS

  15. ART & MUSIC ROOMS ENLARGED ART & MUSIC ROOMS

  16. HVAC SYSTEM HVAC System Design:  Cost-effective rooftop HVAC system  Very similar to high school  Units located over corridor for sound control  One unit per classroom with own thermostat

  17. ADMIN & MEDIA CENTER ENLARGED ADMINISTRATION & MEDIA CENTER WING

  18. GYM AND CAFETERIA PLAN

  19. KITCHEN PLAN

  20. NEXT STEPS Site Planning and Design:  Meet with the Colonial Beach Building Official and the state Fire Marshall.  Respond to any comments on the Site Plan submittal provided to the Town of Colonial Beach and to the DEQ.  Prepare for the Conditional Use Permit application meetings.  Continue to develop and update the Site and Landscape plans for the project.

  21. NEXT STEPS Building Planning and Design:  Continue with the development of the plans for the building design for submitting the Design Development package in mid-March.  Present the proposed Kitchen Design to the kitchen design committee, and update the Kitchen Plan with any changes.  Present the Proposed Designs for the Art classroom, Music classroom and Media Center to the Principal and teachers.

  22. Thank you!

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend