MADISON CENTRAL SCHOOL SUCCESS IS NOT A MATTER OF CHANCE BUT OF CHOICE MADISON CENTRAL SCHOOL EVOLUTION OF BUILDING ADDITIONS MADISON CENTRAL SCHOOL EXISTING FLOOR PLANS Educational Objectives Enhance Community Access Provide
EVOLUTION OF BUILDING ADDITIONS
MADISON CENTRAL SCHOOL
MADISON CENTRAL SCHOOL
EXISTING FLOOR PLANS
Current Seating for 264
- Enhance Community Access
- Provide Auditorium for
Dynamic Music Program
- Upgrade Locker Rooms,
Fitness Rooms, and Spectator Capacity for Physical Education
- Embrace Middle School
Concept (Grade 6-8)
- Provide Centrally Located
Special Education Spaces for Teaching and Learning
- Organize Elementary
Classrooms in Age Appropriate Plan
- Maximize Instructional
Space and Enhance Administrative Support Areas
Educational Objectives
MADISON CENTRAL SCHOOL
PROPOSED FLOOR PLANS
Seating for 385 (Currently 264)
- Space Changes
- New Kitchen /
Cafeteria
- New Auditorium
- Expanded
Gymnasium Seating
- Renovated Locker
Rooms
- Address
Improvements to Various Building Conditions
Main K-12 Building Work
Seating for 543 (Currently 357)
MADISON CENTRAL SCHOOL
PROPOSED P.E. UPGRADES
- New Locker Rooms
- New Public Rest Rooms
- New Fitness Room
- Bleacher Seating for 543
(Current Seating for 357)
P.E. Upgrades
First Floor Plan Second Floor Plan Section Through Seating
MADISON CENTRAL SCHOOL
PROPOSED KITCHEN / CAFETERIA UPGRADES
- New Kitchen
- Expanded Cafeteria for
254
- Multipurpose Room for
Home and Careers
- Senior Section / Dressing
Room
Kitchen / Cafeteria Upgrades
Proposed Cafeteria Plan
Auditorium First Floor Plan Auditorium Balcony Plan
MADISON CENTRAL SCHOOL
PROPOSED AUDITORIUM PLANS
Total Seating Capacity: 385
MADISON CENTRAL SCHOOL
VIEW FROM CENTER STAGE
MADISON CENTRAL SCHOOL
VIEW FROM BALCONY
MADISON CENTRAL SCHOOL
VIEW FROM ENTRANCE
MADISON CENTRAL SCHOOL
VIEW FROM STAGE RIGHT
- Athletic Field Upgrades
- Exterior Basketball
Court
- Repave Entrance Drive
- Playscape Fiber
- New Flagpole
- LED Entrance Sign
MADISON CENTRAL SCHOOL
SITEWORK
Sitework
General Scope of Work
Main K-12 Building ~ $6,104,000
- Space Changes
- New Kitchen / Cafeteria
- New Auditorium
- Expanded Gymnasium Seating
- Renovated Locker Rooms
- Address Improvements to Various
Building Conditions
Sitework ~ $1,000,000
- Athletic Field Upgrades
- Exterior Basketball Court
- Repave Entrance Drive
- Playscape Fiber
- New Flagpole
- LED Entrance Sign
Bus Garage ~ $23,000
- Seal Masonry
- Upgrade Temperature
Controls
Construction subtotal: $7,127,000 Incidental Costs: $1,425,400 Contingency & Escalation: $1,425,400 TOTAL PROJECT COST: $9,978,000
MADISON CENTRAL SCHOOL
TOTAL PROJECT COST: $9,978,000
4/15 3/1 10/21 10/21 10/25 –12/10 12/2 12/10 12/10 4/15 3/15 - 4/19 5/1 11/30 12/1 -12/31
MADISON CENTRAL SCHOOL
PROJECT TIMELINE