Agency Models Transmission Arrangements for Distributed Generation - - PowerPoint PPT Presentation

agency models
SMART_READER_LITE
LIVE PREVIEW

Agency Models Transmission Arrangements for Distributed Generation - - PowerPoint PPT Presentation

Agency Models Transmission Arrangements for Distributed Generation Glasgow: 26 October 2006 Structure Review Agency Model Options Focus on Gross Nodal Supplier Agency Model Review issues raised For NGET Issues raised in TADG


slide-1
SLIDE 1

Agency Models

Transmission Arrangements for Distributed Generation

Glasgow: 26 October 2006

slide-2
SLIDE 2

Structure

Review Agency Model Options Focus on Gross Nodal Supplier Agency Model Review issues raised

For NGET Issues raised in TADG meetings

How the GNSAM addresses these issues

slide-3
SLIDE 3

What do we mean by “Agency”?

‘business or service authorised to act for others ‘ Single point of contact / interface Aggregator of capacity and energy Controller of despatch Who? Options:

DNOs– DNO Agency Supplier interface – Supplier Agency

The current model is an agent model

slide-4
SLIDE 4

Flavours of agency

Gross vs. Net

“Gross” for most cost reflective charging of

transmission costs

Nodal vs. Zonal

Operational requirement is nodal GNSAM - Charging arrangements is a zonal

tariffs, but nodal charge

DNO vs. Supplier

Supplier least change commercially An operational interface with the DNO

slide-5
SLIDE 5

Agency Model Matrix

Gross of Gross of Net of Net of GSP GSP Group GSP GSP Group

Supplier Agency DNO Agency

“TODAY” (sort of)

Very Difficult, SVA at GSP Group level, Would need to Re-register 23m meters “Interconnector model” Possible, but involves a lot

  • f change

GNSAM

slide-6
SLIDE 6

Gross Nodal Supplier Agency Model (GNSAM)

GSP GSP GSP GROUP EG D D EG Distribution Network Transmission Network

NHHd2 HHd1 HHg1 HHg2 NHHd1 HHg2

M1 M2 Today GNSAM

Netted off

HH £/kW Zonal Dem Tariff NHH p/kWh Zonal Dem Tariff

∑HHd

+ ∑NHHd

HH £/kW Zonal Dem Tariff NHH p/kWh Zonal Dem Tariff

For a Supplier, Each embedded generator above a given threshold might be offered to the SO as a single BMU

HHg1

£/kW Gen TNUoS Tariff

Generation BMU

Demand

Generation BMU +

Generation

£/kW Gen TNUoS Tariff £/kW Gen TNUoS Tariff

TEC

HHg2

£/kW Gen TNUoS Tariff

+

TEC ∑HHd - ∑HHg+ ∑NHHd

slide-7
SLIDE 7

GSNAM with consolidation

GSP GSP GSP GROUP EG D D EG Distribution Network Transmission Network

NHHd2 HHd1 HHg1 HHg2 NHHd1 HHg2

M1 M2 EG

HHg1 HHg3

EG ∑HHd

+ ∑NHHd

HH £/kW Zonal Dem Tariff NHH p/kWh Zonal Dem Tariff

HHg1

£/kW Gen TNUoS Tariff

Demand

Generation BMU +

Generation

£/kW Gen TNUoS Tariff

TEC

HHg3

+

HHg2 HHg4

£/kW Gen TNUoS Tariff

TEC

slide-8
SLIDE 8

NGET issues (1)

Investment planning

All generation impacts on transmission Investment is driven by change No access product - clarity required Queue avoidance

Locational signals

Current signal perceived as not cost reflective Strong incentive to embed Size of ‘benefit’ is largely arbitrary Position forecast to worsen

slide-9
SLIDE 9

NGET issues (2)

Operational

Nodal control required Access to services

Specific issues in Scotland

Nature of transmission Small generators discount, C13 Efficient Interface Minimise interfaces where ever practicable

slide-10
SLIDE 10

Industry issues (1)

Why do we need to change? Cost benefit required for any change Scope of change Impact on new and existing parties Interaction with Distribution Arrangements Subjectivity of a de-minimis level Over burdensome relationship with GBSO

Requirement to be party to industry codes Cap97 / LEEMPS

slide-11
SLIDE 11

Industry issues (2)

Clarification of rights

Who should have them Gross / net TEC / DEC

Nature of agreement with NGET

BEGA / BELLA / BCA / DNO exit

Double accounting GB queue Embedded generation is it negative

demand?

slide-12
SLIDE 12

How an Agency model addresses the issues (1)

Firstly, need to accept a need for change

  • change needs to be beneficial
  • There may need to be changes to other arrangements

Different flavours address different issues

  • NGET believes GNSAM is balanced approach

An agency model provides the most efficient interface Supplier agency model draws largely upon existing

arrangements

Agency model allows a level of aggregation Cost reflective transmission signals for all generation

slide-13
SLIDE 13

How an Agency model addresses the issues (2)

Agency model can address de-minimis issue

  • Nodal Net
  • Gross at lower level (HH)

Codification of access rights and obligations Clarifies GB queue arrangements

slide-14
SLIDE 14

Summary

Many issues common None of the agency models are simple But they are ‘doable’ NGET think “gross” and “nodal” are important No preference which agent Supplier least change - evolution GNSAM addresses the main NGET issues many of the industry issues