Access to Excess Water Public Workshop Arizona Water Banking - - PDF document

access to excess water public workshop
SMART_READER_LITE
LIVE PREVIEW

Access to Excess Water Public Workshop Arizona Water Banking - - PDF document

Access to Excess Water Public Workshop Arizona Water Banking Authority October 22, 2008 Water Available to the AWBA 3,000 Thousand Acre-Feet AWBA AGRI 2,500 M&I & Tribes 2,000 1,500 On-River 1,000 2005 2010 2015 2020 2025


slide-1
SLIDE 1

Access to Excess Water Public Workshop

Arizona Water Banking Authority October 22, 2008

Water Available to the AWBA

On-River M&I & Tribes AGRI AWBA

1,000 1,500 2,000 2,500 3,000

Thousand Acre-Feet

2005 2010 2015 2020 2025 2030 2035

Year

slide-2
SLIDE 2

AWBA Performance

Volume of Water Delivered through 2008 ( 2008 forecasted)

219 251 294 295 346 213 286 213 361 385 325 243 3,430 2,229 2,442 1,943 1,730 1,384 1,089 795 544 2,803 3,188

500 1,000 1,500 2,000 2,500 3,000 3,500 4,000

1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008

Year Deliveries (1,000 Acre-Feet)

Annual Cumulative Volume

Arizona Water Settlements Act

  • AWBA statutes amended to make

Water Bank agent for the State

  • Agreement between the Secretary of

Interior and AWBA for the Firming

  • f Central Arizona Project Water -

November 15, 2007

slide-3
SLIDE 3

Indian Firming State’s responsibility:

  • firm 15,000 AF water reallocated to

Gila River Indian Community

  • firm 8,724 AF water reallocated to

AZ Indian tribes

  • assist Secretary in carrying out
  • bligations of Southern Arizona Water

Rights Settlement Act (Tohono O’odham)