20/06/2016 Agenda Site News Shaping the Organisation Life Time Plan 2015 Care & Maintenance Programme Socio Economics Magnox in the Community Final Thoughts John Grierson, Chapelcross Closure Director Site


slide-1
SLIDE 1

20/06/2016 1

Chapelcross

John Grierson, Chapelcross Closure Director Site Stakeholder Group Presentation 10 June 2016

Chapelcross

  • Site News
  • Shaping the Organisation
  • Life Time Plan 2015
  • Care & Maintenance Programme
  • Socio Economics
  • Magnox in the Community
  • Final Thoughts

Agenda

Chapelcross

  • EHSS&Q Performance

– Overall Safety Performance – ‘Target Zero’ – Demonstration Exercise & EOD – Heat Exchanger Safety Pause – SEPA Warning Letter – Being Magnox Values – Standards and Expectations

  • Business

– 2015/16 SPI = 0.90, CPI = 1.24, EAC - £38.5M

  • Workforce

– Employees 217, ASW 19, CSW 11, Contractors ~60 - 80

Site News

Chapelcross

  • Transformation progress

– Final stages of process – Revised organisation implemented on 09/05/16 under MoC8 – Maintaining focus on displaced list, looking to secure opportunities

  • Preparing MoC to support implemented

Contingency Emergency Arrangements

  • Sellafield Academic Requirements
  • Parent Organisation Vacancies

Shaping the Organisation

Chapelcross

  • Requirement of the NDA following the PBO change

(Consolidation Period)

  • Incorporates new technologies introduced by the new PBO
  • There is an opportunity for the site to enter C&M earlier than

forecast, if funding can support

  • Phase 1 & 2 of the contract deliverable may negate the need to

enter an Interim C&M configuration

  • Resource curves predict a continuous reduction in resource

requirements based on completion of hazard reduction

  • Assessing the benefits of delayed demolition of CXPP following

retrieval and storage of ILW

Life Time Plan 2015

Chapelcross

20 June 2016 6

PLANT & STRUCTURES (P&S)

  • Risk-based assessment of plant to determine what can remain during Care

and Maintenance (C&M)

  • Leads to safestore hazard reduction through Risk based de-planting
  • Maintain and repair of Safestore cladding
  • Zonal demolition later in decommissioning timeline
  • Assessing the benefits of delayed demolition of CXPP following retrieval

and storage of ILW PONDS

  • ILW waste removal & preparation for transfer to waste operations
  • MAETP installation and operation
  • Drain and stabilise pond 2
  • Decommission ponds building to meet transfer criteria to P&S

Decommissioning Overall Approach

slide-2
SLIDE 2

20/06/2016 2

Chapelcross

20 June 2016 7

  • CXPP Design-Commissioning, retrieval and packaging and export
  • B141 – Design- Commissioning of equipment to Over pack TSV’s

and export

  • Construction of Encapsulation facility in Flask Handling Building

including pre processing of sludge's

  • Construction of AVDS Facility for MAC and Cobalt DCIC’s
  • Construction of ISF
  • Higher Active Waste Conditioning including AVDS, Encapsulation

facility, B141 over packing, XST and ISF

  • Container Purchase, Transport and Disposal
  • Low Active Waste Conditioning

Waste Programme Overall Approach

Chapelcross

8

Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 LTP15 Bid P48 Extant LTP15 Bid P48 Extant LTP15 Bid P48 Extant LTP15 Bid P48 Extant LTP15 Bid P48 Extant LTP15 LTP15 P48 Extant LTP15 LTP15 Bid P48 Extant LTP15 LTP15 DV Title: L33701 Chapelcross ‐ Higher Active Waste Conditioning DV Title: L33618 Chapelcross ‐ Build ILW Store DV Title: L33609 Chapelcross ‐ Encap Plant D&B DV Title: L33501 Chapelcross ‐ Site Restoration DV Title: L33603 Chapelcross ‐ CXPP DV Title: L33406 L33405 2030 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029

Chapelcross

2018 Chapelcross ‐ Pre ‐ Processing Facility Design and Build DV Title: L33616 2015 2016 2017 DV Title: L33402 Non ISB Clearance DV Title: L33201 Chapelcross Pond Decommissioning DV Title: L33301 Chapelcross Reactor and Reactor Building C&M Preparations DV Title: L33408 Land Remediation ISB Clearance M112 M113 SLCA 135 M114 & M115 M110 M109 SLCA133 LC35.04 LC35.07 LC35.08 LC35.09 LC35.10 LC35.12 SLCA136 SLCA134 End of site physical works 28/11/2025 End of Effluent Pipeline Physical works 25/03/2026

Management Summary Schedule (MSS)

Chapelcross

9

Key Dates

Milestone Date No.2 Pond Drained July 2021 Mobile Active Effluent Treatment Plant – available April 2018 Heat Exchanger Steelwork Removal & Top Duct October 2018 Heat Exchanger Boiler Removal March 2024 Reactor Building Preparations for C&M September 2023 ISB Building Demolition October 2025 Non ISB Building Demolition December 2025 Land Remediation December 2026 CXPP Waste Retrieval and Passivation August 2021 Interim Storage Facility February 2019 Enter Care & Maintenance Phase December 2025

Chapelcross

What’s being done now….

Chapelcross

What’s being done now….

Chapelcross

What’s being done now….

slide-3
SLIDE 3

20/06/2016 3

Chapelcross

What’s being done now….

Chapelcross

What’s being done now….

Chapelcross

Magnox Socio-Economic Scheme

Chapelcross Applications 2015/16

Applications Pending 5 Applications Rejected Application Withdrawn Applications Successful 3 Total Applications to Date 8 Funding Under £1K Schemes Awarded £1,100 Funding Over £1K Schemes Awarded £0 TOTAL AMOUNT OF FUNDING AWARDED £1,100 Chapelcross

Chapelcross Stakeholder Activity

Chapelcross

BUT . . .

Safety of the workers, public and the environment has always been, and always will be, this industry’s No 1 Priority

Final Thoughts….