Implementing TOD Challenges and opportunities for Railway Stations Redevelopment WRI Workshop Thursday, February 18, 2016 www.irsdc.com PM SHRI NARENDRA MODI ON RAILWAY STATIONS Monday, February 29, 2016 2 A WORLD CLASS STATION


slide-1
SLIDE 1

Implementing TOD – Challenges and opportunities for Railway Stations Redevelopment WRI Workshop

Thursday, February 18, 2016

www.irsdc.com

slide-2
SLIDE 2

PM SHRI NARENDRA MODI ON RAILWAY STATIONS

Monday, February 29, 2016 2

slide-3
SLIDE 3

A WORLD CLASS STATION …

Monday, February 29, 2016 3

…will provide state of the art facilities to the passengers… …by leveraging the real estate potential of the land and air space in and around the station. …will incorporate architecture that shall reflect the culture and the character of the city. …will integrate development for a comfortable and efficient passenger experience. …will be self financing and would also generate revenue for railway.

slide-4
SLIDE 4

MAIN FEATURES

Monday, February 29, 2016 4

Iconic Structure Segregation: Arrival/ Departure Planning for next 40 years To act as a multi modal transit hub Integrating both sides

  • f the city

Energy efficient Disabled friendly Enhancing passengers’ delight

slide-5
SLIDE 5

STAKEHOLDERS IN STATION DEVELOPMENT

Monday, February 29, 2016 5

Station Development

Indian Railway Tourism Dept State Govt City Corporations Contiguous Landowners Investors / Developers Local communities

slide-6
SLIDE 6

BENEFITS TO STAKEHOLDERS

Monday, February 29, 2016 6

Opportunity to create an iconic structure High brand visibility with benefits for your other business Enhanced credibility and goodwill Create a gateway as part of a holistic tourist experience Rise in property value around stations

Station redevelopment projects are TOD projects in which the central station complex becomes more multifunctional, and the linkage system is more thematic to satisfy a diversity of needs. Station areas as places for exchange of ideas and promotion of lifestyle, within a physical framework that incorporates innovations in building and space technology. The railway stations are in effect becoming nerve centres for the so-called ‘Smart’ city, in which the transportation function plays a supportive role and no longer a central role.

slide-7
SLIDE 7

SWOT ANALYSIS

Monday, February 29, 2016 7

Ownership of land Strategically placed Studied well for implementation Model under implementation Real Estate component– Complex formalities Competition from upcoming/planned projects in the cities Volatility in real estate valuations. Huge potential, growing system FDI – 100% Strengths Threats Weaknesses Opportunities

slide-8
SLIDE 8

KEY CHALLENGES

Monday, February 29, 2016 8

Located in congested areas in city centres. Commercial development around these stations may add to the congestion and the capacity of approach road infrastructure may be a constraint. Extensive discussions with local authorities/bodies: permissible FAR, multi-modal integration, approach infrastructure. Station specific issues i.e. Heritage clearances etc. Most stations are brown field ones where redevelopment works have to be executed under running train conditions. Different financial models required for viability. Financial viability depends on real estate market which is cyclical in nature.

slide-9
SLIDE 9

GLOBAL EXAMPLES

Monday, February 29, 2016 9

The station’s conversion is part of an urban renewal project centring on the area north of the station. The locus of this project is the renovation of the central station, which now forms the focal point of this area. The new urban complex will comprise an international congress centre, hotels, housing, offices, public space, etc.

Seoul, South Korea

slide-10
SLIDE 10

GLOBAL EXAMPLES

Monday, February 29, 2016 10

View of Tokyo Station in 2000, before redevelopment Tokyo Station renovation - Marunouchi side, Nov 2009

Tokyo, Japan

slide-11
SLIDE 11

GLOBAL EXAMPLES

Monday, February 29, 2016 11

Tokyo Station Yaesu Side, with the new Grand Tokyo South Tower completed in 2007 The front of Tokyo Station lit up at night, taken from the Marunouchi Oazo side

Tokyo, Japan

slide-12
SLIDE 12

GLOBAL EXAMPLES

Monday, February 29, 2016 12

In St. Pancras, 9,000 square meters (97,000 square feet) of retail space are directly connected to passenger flows. The land between and behind the two stations (St. Pancras & Kings Cross) has been redeveloped with nearly 2,000 new homes, 5.3 million sqft of office space and new roads as King's Cross Central. The St. Pancras Renaissance London Hotel was opened in 2011.

  • St. Pancras Station, London, UK
slide-13
SLIDE 13

GLOBAL EXAMPLES

Monday, February 29, 2016 13

Kings Cross Station London, UK

Office 3.4 million sq ft Retail 500,000 sq ft Hotel 91 rooms 30,000 sq ft Residential 2,000 units Parking 865 spaces Open space 26 acres Total gross building area planned 6 million sq ft Total site area 67 acres (27 ha)

slide-14
SLIDE 14

GLOBAL EXAMPLES

Monday, February 29, 2016 14

The station redevelopment has been the catalyst for one of the largest regeneration schemes in Europe, attracting £2.2bn of private investment. 67 acres of brown-field land is being developed into offices (3.4 million sq ft), Retail (500,000 sq ft) and 2,000 homes. The project was completed with the revealing of the original station facade and the opening of the 75,000 sq ft King's Cross Square in front of the station.

Kings Cross Station London, UK

slide-15
SLIDE 15

GLOBAL EXAMPLES

Monday, February 29, 2016 15

Kuala Lumpur Sentral (KL Sentral) is a transit-oriented development that houses the main railway station of Kuala Lumpur. KL Sentral replaced the old Kuala Lumpur railway station as the city's main intercity railway station. KL Sentral refers to the entire 290,000 square metres of development built on the former KTM marshalling yard. The development includes the transport hub, hotels, office towers, condominiums and shopping malls.

Kuala Lumpur Sentral, Malaysia

slide-16
SLIDE 16

OUR STRATEGY

Monday, February 29, 2016 16

8 stations by IRSDC.

Project development by IRSDC prior to bidding.

400 (A1 & A category) stations on Swiss Challenge method.

Bidding on “as is where is basis”.

slide-17
SLIDE 17

IRSDC PROJECTS: METHODOLOGY

Monday, February 29, 2016 17

Invitation of proposal for ATC Appointment of Arch & Tech consultant Appointment of Financial & Bid advisory consultant Preparation of Master Plan & Feasibility report Approval of Master plan by Zonal Railway Approval of Master plan by Local bodies Invitation of RFQ Finalisation of RFQ Invitation of RTP Finalisation of RTP incl. Normalization Invitation of RFP ( Financial Bid) Finalisation of RFP Issue of LOA

slide-18
SLIDE 18

IMPLEMENTATION STRATEGY

Monday, February 29, 2016 18

Developer Real Estate Railway Station

Development in 3 yrs O&M for 5 years

Transfer

IRSDC/ Railway Premium Lease, Development Rights and Right of Way IRSDC

The developer will fund the development of station and operation & maintenance for 5 years, using the revenues from real estate. Developer will transfer station assets to railways and operate the station for 5 years through a O&M contract. Before completion of station development, developer will not be permitted to earn revenues from real estate.

Develop in 8 yrs max Lease 45 yrs

slide-19
SLIDE 19

STATUS OF STATIONS ENTRUSTED TO IRSDC

Monday, February 29, 2016 19

Station Current Status

Habibganj

RFQ and RTP finalised RFP (Financial Bid) invited on 14.12.2015 Award of Development contract by 28.02.2016

Anand Vihar

In-principle approval of Master Plan received from Unified Traffic and Transportation

  • Infrastructure. (Planning & Engineering) Centre (UTTIPEC); RFQ invited, to be opened on

22.02.2016.

Bijwasan

In-principle approval of Master Plan received from UTTIPEC Increase in height of building from 10.39 m to 21.57 m obtained from Airport Authority of India. RFQ invited, to be opened on 22.02.2016.

Chandigarh

In principle approval of Master Plan received from UT Administration, Chandigarh. Revision of drawings in process. RFQ invitation – Planned in February2016.

slide-20
SLIDE 20

STATUS OF STATIONS ENTRUSTED TO IRSDC

Monday, February 29, 2016 20

Station Current Status

Shivajinagar

Application for approval of Master Plan by local authorities submitted. Heritage clearance obtained. Master plan approval being pursued at Chief Secretary, Govt. of Maharashtra level.

Surat

An Integrated Multi-Modal Hub to be developed duly encompassing Rly’s master plan. SMC and Gujarat State Road Transport Corporation (GSRTC) have appointed their Consultants and their plans are yet to be finalized. Last meeting held at Surat on 11.01.2016 to finalise multimodal plan.

Gandhinagar (RLDA)

Feasibility Report and Master Plan prepared. Plan finalised broadly. Financial modelling being done. MOU with state govt being drafted.

slide-21
SLIDE 21

400 STATIONS REDEVELOPMENT - PRESENT STATUS

Monday, February 29, 2016 21

400 stations on as is where is basis. General Guidelines issued to Zonal Railways and Standing Groups constituted to facilitate interaction with prospective bidders. (www.indianrailways.gov.in) List of stations proposed, general data and indicative list of facilities uploaded on Zonal railways website. Rail Land Development Authority (RLDA) has appointed a consultant for preparation of Model tender document, which is being finalised after stakeholders’ consultations in January’ 2016. IRSDC entrusted to appoint a consultant for providing Strategic / transaction Advisory Services for this project; Bids under finalisation.

slide-22
SLIDE 22

“SWISS CHALLENGE” METHODOLOGY

Monday, February 29, 2016 22

Seeking initial proposal Submission of Proposal Examination by STC Examination by SFC Examination by ICEE Approval from GM Submission of detailed proposal Normalization & Inviting open bids Submission of proposals Bid evaluation Time for matching highest bid Award

slide-23
SLIDE 23

FINANCING MODEL

Monday, February 29, 2016 23

Self-Financing Mechanism:

capital and

  • perating cost of the project is financed through

the project revenues and “station facility” revenues.

Project Revenues: revenue from commercial

development on vacant land & air rights.

slide-24
SLIDE 24

8

REAL ESTATE DEVELOPMENT

Monday, February 29, 2016 24

Vacant land and air rights Model Development Agreement (www.irsdc.com) SPV to be formed for Station Development Maximum lease period in years

3

years within which station development is to be accomplished years within which commercial development is envisaged

45

slide-25
SLIDE 25

REAL ESTATE DEVELOPMENT

Monday, February 29, 2016 25

Land cannot be mortgaged: ownership always with Railways Commissioning of Commercial Development: after commissioning of station development Advance Marketing: permitted through Escrow mechanism No residential development permitted

slide-26
SLIDE 26

Welcome to partner in world’s largest TOD and PPP programme

For more information email at

info@irsdc.com

slide-27
SLIDE 27

Habibganj (Bhopal)

Monday, February 29, 2016 27

slide-28
SLIDE 28

Anand vihar

Monday, February 29, 2016 28

slide-29
SLIDE 29

Bijwasan

Monday, February 29, 2016 29

slide-30
SLIDE 30

Chandigarh

Monday, February 29, 2016 30

slide-31
SLIDE 31

Shivaji Nagar (Pune)

Monday, February 29, 2016 31

slide-32
SLIDE 32

Surat

Monday, February 29, 2016 32

slide-33
SLIDE 33

Gandhinagar

Monday, February 29, 2016 33