1 Project Update - Overview & Schedule Background 11 projects underway for improved airport access. Work initiated in 2017. Public workshop held on May 25, 2017. Presentation of concept designs on October 16, 2017. Presentation of


slide-1
SLIDE 1

1

slide-2
SLIDE 2

Project Update - Overview & Schedule

Integrity ∙ Excellence ∙ Respect

4/15/2019 2

Background

  • 11 projects underway for improved airport access. Work initiated in 2017.
  • Public workshop held on May 25, 2017. Presentation of concept designs on October 16,
  • 2017. Presentation of preferred alternative to Borough Assembly on May 14, 2018.

Construction Project 1 ‐ Revilla Uplands Project

  • Expanded uplands. More parking, improved vehicle & pedestrian flow, ticketing & vehicle

staging.

  • New passenger waiting building and covered pedestrian walkways.

Construction Project 2 ‐ Revilla / Gravina New Ferry Berths & Gravina Upland Improvements

  • Construct two new ferry berths at Revilla and Gravina shuttle ferry terminals.
  • Pedestrian and vehicle access improvements at Gravina ferry terminal uplands.

Schedule

  • Fall, 2019: Complete design/advertise construction contracts.
  • Fall, 2021: Complete construction.
slide-3
SLIDE 3

Project Introduction

Integrity ∙ Excellence ∙ Respect

4/15/2019 3

slide-4
SLIDE 4

All Projects - Estimates

4/15/2019 4

slide-5
SLIDE 5

Project Overview – Revilla Uplands

4/15/2019 5

VEHICLE STAGING DROP OFF ZONE TAXI LANES EXIT ENTRY WAITING BUILDING EXIT ENTRY/EXIT NEW FERRY BERTH EXISTING FERRY BERTH

slide-6
SLIDE 6

Gravina Walkw ay Improvements

4/15/2019 6

EXISTING BERTH NEW BERTH AIRPORT BUILDING EXISTING RAMP NEW DOCK AND COVERED CANOPIES

slide-7
SLIDE 7

Construction Phases & Schedule

4/15/2019 7

Phase 1: Nov 2019 thru May 2020 New generator building and deep utilities Phase 2: February 2020 thru mid‐June 2020 North Tongass Highway reconstruction. Phase 3: mid‐June 2020 thru March 2021 (partial winter shutdown) North parking lot expansion, new ferry loading lanes ‐ begin new passenger waiting building, north half of passenger drop‐off canopy. Phase 4: March 2021 thru July 2021 South half of parking reconstructed, passenger drop‐off canopy and passenger waiting building are completed. Phase 5: Aug 2021 thru Dec 2021 Ferry exit lane and passenger drop‐off lanes completed.

slide-8
SLIDE 8

Pedestrian Detours

4/15/2019 8

slide-9
SLIDE 9

Wayfinding & Signage

4/15/2019 9

PEDESTRIAN SIGNAGE PLACED NEXT TO KIOSK AND UNDER CANOPIES AS WINDBREAK FEATURES HIGHLY VISIBLE VEHICULAR SIGNAGE FERRY LANES & LOADING ZONES

slide-10
SLIDE 10

Kiosk Systems

4/15/2019 10

Luke 2 kiosk system

slide-11
SLIDE 11

Automated Ticketing Concept

4/15/2019 11

VEHICLE TICKETING KIOSKS & PROX CARD READERS PARKING & FERRY PASSENGER KIOSKS TICKET KIOSK

slide-12
SLIDE 12

Baggage Cart System

4/15/2019 12

Modified ADA Ford Transit

slide-13
SLIDE 13

Revilla Marine Work

4/15/2019 13

slide-14
SLIDE 14

Gravina Marine Work

4/15/2019 14

slide-15
SLIDE 15

Gravina Marine Work

4/15/2019 15

slide-16
SLIDE 16

Support Structures - Revilla

4/15/2019 16

  • 1. Waiting Building (Separate Gravina Access SEIS Project) – Provides interior

conditioned waiting space and restrooms. Ticket kiosk located in entry

  • vestibule. Provides luggage staging and support vehicle lane
  • 2. Storage Building – Houses Bobcat snowplow & attachments. Other site

maintenance items located in building. One ticket kiosk with wayfinding sign located on exterior of building.

  • 3. Generator Building – Houses emergency back up generator
slide-17
SLIDE 17

4/15/2019 17

Buildings & Site Elements - Revilla

STORAGE BUILDING CANOPIES WAITING BUILDING GENERATOR BUILDING SIGNAGE New Berth Existing Berth

slide-18
SLIDE 18

Drop-Off Canopies, Waiting Area & Queuing

4/15/2019 18

ADA DROP ZONE DROP‐OFF PICK‐UP CANOPIES RAMP TO NEW BERTH DRIVE LANE RAMP TO EXISTING BERTH TAXI PICK UP AREA

slide-19
SLIDE 19

Waiting Building

4/15/2019 19

ENTRY ENTRY WAITING ADA BAGGAGE DROP VESTIBULE KIOSKS

slide-20
SLIDE 20

SUPPORT BUILDINGS

4/15/2019 20

STORAGE BUILDING GENERATOR BUILDING

slide-21
SLIDE 21

Waiting Building Axo View

4/15/2019 21

RAMP TO NEW BERTH EXISTING BERTH

slide-22
SLIDE 22

View From Drive Lane @ Main Crossing

4/15/2019 22

slide-23
SLIDE 23

4/15/2019 23

Baggage Drop @ New Waiting

slide-24
SLIDE 24

4/15/2019 24

Canopy Renderings

slide-25
SLIDE 25

4/15/2019 25

Canopy Renderings

slide-26
SLIDE 26

4/15/2019 26

Drop-Off / Pick-up Seating

slide-27
SLIDE 27

4/15/2019 27

Staging Lanes & Storage Building

slide-28
SLIDE 28

Gravina Walkw ay Improvements

4/15/2019 28

EXISTING BERTH NEW BERTH AIRPORT BUILDING EXISTING RAMP NEW DOCK AND COVERED CANOPIES

slide-29
SLIDE 29

Gravina Walkw ay Improvements

4/15/2019 29

AIRPORT BUILDING BEYOND NEW DOCK & CANOPIES IMPROVED EXISTING CANOPIES

slide-30
SLIDE 30

Gravina Walkw ay Renderings

4/15/2019 30

AIRPORT BUILDING BEYOND NEW DOCK AND COVERED CANOPIES IMPROVE EXISTING CANOPIES

slide-31
SLIDE 31

Gravina Walkw ay Renderings

4/15/2019 31

NEW DOCK RAIN/WIND PROTECTED PASSENGER QUEUING

slide-32
SLIDE 32

END