Detailed Design of the Crescent Lake Causeway Presentation to City - - PowerPoint PPT Presentation

detailed design of the crescent lake causeway
SMART_READER_LITE
LIVE PREVIEW

Detailed Design of the Crescent Lake Causeway Presentation to City - - PowerPoint PPT Presentation

Detailed Design of the Crescent Lake Causeway Presentation to City Council Presented By: Eric Loewen, P.Eng. & Felipe Tabet, P.Eng. - AECOM January 14, 2019 OUTLINE OF PRESENTATION Roundabout Geometry, Refinements since the


slide-1
SLIDE 1

Presented By: Eric Loewen, P.Eng. & Felipe Tabet, P.Eng. - AECOM

Detailed Design of the Crescent Lake Causeway

Presentation to City Council

January 14, 2019

slide-2
SLIDE 2

OUTLINE OF PRESENTATION

  • Roundabout Geometry, Refinements since the

Preliminary Design and Safety

  • Construction Staging
  • Truck Movements
  • Structural Design
  • Landscape Architecture
  • Roadway and Pathway Signs
  • Cost Estimate
  • Video Presentation
slide-3
SLIDE 3

ROUNDABOUT GEOMETRY AND REFINEMENTS TO THE PRELIMINARY DESIGN

Roundabouts:

  • Reduce conflict points
  • Reduce vehicle speeds
  • Reduce collision angles
slide-4
SLIDE 4

CONSTRUCTION STAGING: STAGE 1 - 2019

slide-5
SLIDE 5

CONSTRUCTION STAGING: STAGE 2 - 2019

slide-6
SLIDE 6

CONSTRUCTION STAGING: STAGE 3 - 2020

slide-7
SLIDE 7

CONSTRUCTION STAGING: STAGE 4 - 2020

slide-8
SLIDE 8

NORTH-SOUTH TRUCK MOVEMENTS

slide-9
SLIDE 9

EAST-WEST TRUCK MOVEMENTS

slide-10
SLIDE 10

STRUCTURAL DESIGN

slide-11
SLIDE 11

LANDSCAPE ARCHITECTURE

slide-12
SLIDE 12

LANDSCAPE ARCHITECTURE

slide-13
SLIDE 13

LANDSCAPE ARCHITECTURE

slide-14
SLIDE 14

ROADWAY AND PATH SIGNS

slide-15
SLIDE 15

ROADWAY AND PATH SIGNS

slide-16
SLIDE 16

ROADWAY AND PATH SIGNS

slide-17
SLIDE 17

COST ESTIMATE

Item Cost ($)

Mobilization, Demobilization & Traffic Diversion 260,000 Roadway 3,350,000 Structural 740,000 Landscaping 270,000 Municipal, Electrical, Utilities, Environmental Mitigation 500,000 Sub-Total 5,120,000 Contingency (20%) 1,024,000 Construction Cost 6,144,000 Engineering 500,000 Inflation 350,000 Total 7,000,000

slide-18
SLIDE 18

Video Presentation

slide-19
SLIDE 19

Thank You