SLIDE 1
1 14 15 16 Coring to determine peat layer - Sediment testing at - - PDF document
1 14 15 16 Coring to determine peat layer - Sediment testing at - - PDF document
1 14 15 16 Coring to determine peat layer - Sediment testing at samples taken at two deps 19 20 11/21/2014 - Access alternatives were evaluated. It was determined the least impact to the marsh and conservation area was utilizing an
SLIDE 2
SLIDE 3
15
SLIDE 4
16
SLIDE 5
SLIDE 6
SLIDE 7
19 Coring to determine peat layer
- Sediment testing at …samples taken at two deps
SLIDE 8
20
SLIDE 9
- Access alternatives were evaluated. It was determined the least impact to the
marsh and conservation area was utilizing an existing access road and construction of temporary access into the marsh to employ conventional dredging techniques for removal of material
- First iteration of site plans broke project up into 7 distinct cells so the project
could be completed as time and resources allowed Four Alternatives including Do Nothing Preferred Alternative selected by Rattray Marsh Steering Committee Alternative One: Removal of Mineral soils, Management of Invasive Outlet structure to control Carp Alternative Two: Dyke/Levy System to restrict movement of carp from creek and lake Preferred Alternative: Phased removal of mineral soil 11/21/2014 21
SLIDE 10
First Three Cells. 11/21/2014 22
SLIDE 11
23
SLIDE 12
24 Constructed to a width of 9m and height of approximately 1m above grade 1900 tones of stone, 130k project contribution
SLIDE 13
25
- Prior to beginning any of the sediment removal CVC installs wildlife exclusion
fencing around the preimiter of the project boundary.
SLIDE 14
26 CVC times installation of exclusion fencing with the drawdown of the marsh leaving areas of groundwater discharge open and installs exits doors at strategic locations to allow fish and wildlife out of the project area before marsh is drawn down to mud flat as lake levels recede for the winter.
- Active and passive removal of fish and wildlife is also conducted.
SLIDE 15
27
SLIDE 16
28 Trapped and tagged 5 and tracked 5 snapping turtles for two seasons to determine preferred over wintering areas for turtles to minimize and potential impacts.
SLIDE 17
29
SLIDE 18
- Sediment removal occurs in the winter months when the marsh is frozen and
in low water condition.
- Frozen conditions helps to support the heavy equipment that is required to
conduct the work.
- Contractors also utilize the ice and steel plates to construct temporary access
roads into the marsh.
- Working in the winter also minimizes impacts to sensitive fish and wildlife that
use the marsh during the warm weather months.
- Phase I project stats
Approx 13 days on site Approx 9 Days trucking 154 trucks + 31 trailers for a total of 185 loads taken out. 27 trucks with 6 having trailers was most sediment removed in one day 11/21/2014 30
SLIDE 19
Trucking and peat 11/21/2014 31
SLIDE 20
32
SLIDE 21
11/21/2014 33
- Aquatic plants sourced from Native nursery
- Top right shows one season growth – filled in completely 1 square metre
- TOP – submergent; Bottom - sedges
SLIDE 22
11/21/2014 34
- Aquatic plants sourced from Native nursery
- Top right shows one season growth – filled in completely 1 square metre
- TOP – submergent; Bottom - sedges
SLIDE 23
With the assistance of Canadian Wildlife Service -Pre restoration Monitoring – 2010 Durham Region Coastal Wetland Monitoring Protocol 2013 – Great lakes Coastal Wetland Monitoring Plan 2014 – Post construction monitoring plan **2010** Durham Region Coastal Wetland Monitoring Protocol 11/21/2014 35
SLIDE 24
Carp Vandallistm
- Monitoring data – visibility
11/21/2014 36
SLIDE 25
37 EA also recommended carp control as part of the restoration plan CVC
SLIDE 26
38 EA also recommended carp control as part of the restoration plan CVC
SLIDE 27
11/21/2014 39
SLIDE 28
11/21/2014 40
SLIDE 29
- Shale/Sediment bar continues to form at the mouth of Sheridan Creek, a
portion of this bar was orginally slated to be dredged
- Revisited this with Geomorphologist and determined that it would
continue to function as an area of deposition and any gains obtained from dredgeing would be short lived.
- Some of the material deposited here moves out to the lake during high
flows.
- Also identified in the EA as a desirable area for shorebirds
- Helping to naturally isolate the southern basin of the marsh during low
water levels.
- Phragmites has continued to expand into the southern basin and water level
making chemical treatments difficult
- Modified site plans to omit areas of continued deposition, preserve stands of
cattails not infested prhramites,
- Increase depth to dredging to 1-1.5m in highest phragmites density (Cell A)
- Approx 6000m3i in total
11/21/2014 41
SLIDE 30
11/21/2014 42
SLIDE 31
11/21/2014 43
SLIDE 32