lake seminole
play

Lake Seminole Restoration Dredging Presented by Rob Burnes MS, MAS - PowerPoint PPT Presentation

Lake Seminole Restoration Dredging Presented by Rob Burnes MS, MAS Senior Environmental Scientist Pinellas County Public Works Background 684 acres 5.5 feet average depth Control structures regulate lake level Primarily used for


  1. Lake Seminole Restoration Dredging Presented by Rob Burnes MS, MAS Senior Environmental Scientist Pinellas County Public Works

  2. Background ▪ 684 acres ▪ 5.5 feet average depth ▪ Control structures regulate lake level ▪ Primarily used for recreation ▪ Fish community dominated by sunfish family ▪ Healthy emergent and submerged vegetation communities

  3. Lake Seminole History- 1940’s ▪ Tidal estuarine system ▪ Mangroves ▪ Salt marshes ▪ Lake created in late- 1940’s ▪ Irrigation for orange groves ▪ Potable water source ▪ Impounded an arm of Long Bayou ▪ Flooded the system with freshwater from Long Creek

  4. Lake Seminole History- 1950’s & 1960’s ▪ Rapid expansion in the area surrounding the lake ▪ Start of decline in ecological conditions ▪ Lake Seminole Park Constructed ▪ Current semi-circular weir installed in late 1960’s

  5. Lake Seminole History- 1970’s & 1980’s ▪ Land use Switch ▪ 1976 Lake Seminole Bypass Canal created ▪ By the mid to late 1980’s ▪ Water quality was at an all-time low ▪ Nuisance vegetation at an all time high ▪ 1989 Pinellas BOCC passes resolution of long-term management plan

  6. Lake Seminole History- 1990’s to Present ▪ Built out watershed ▪ Poor water quality ▪ Habitat loss ▪ Decline of sport fishery ▪ Harmful algal blooms ▪ Restoration efforts kick into high gear ▪ Watershed management plan finalized in 2001

  7. Lake Seminole Restoration Efforts 1971- Elimination of direct input from wastewater plant 1987- Grass Carp introduced 1990’s - Stormwater pond rehabilitations 2001- Lake Seminole WMP 2002- Littoral shelf sediment removal and revegetation 2006- Lake draw-down and nuisance vegetation removal, replanting, and drainage improvements 2007- Lake Seminole Reasonable Assurance Plan adopted 2010’s - Construction of alum stormwater treatment systems

  8. Reasonable Assurance Plan ▪ Developed in response to being an impaired waterbody pursuant to section 303(d) of the federal Clean Water Act ▪ Plan finalized in 2007, updated every 4 years ▪ Defined Structural, Management, Legal, and Policy Components

  9. Organic Sediment Dredging ▪ Number one recommended project in Reasonable Assurance Plan ▪ Removal of 900,000 cubic yards of organic sediments ▪ Result in removal of ▪ 416 tons of TN ▪ 77 tons of TP ▪ Goal is to reduce lake’s internal nutrient loads

  10. In-Lake Dredging Timeline ▪ Dredge Material Management Area (DMMA) construction started in January 2019 ▪ Active dredging to began in December 2019 ▪ Dredging to be completed by 2021

  11. Hydraulic Dredging-How it Works ▪ Dredge barge moved into place by tender vessels ▪ Dredge template loaded onto barge GIS system ▪ Cutter head of barge will loosen muck and vacuum will suck up sediment

  12. Hydraulic Dredging-How it Works ▪ Sediment then sent by pipe to upland dewatering site ▪ Slurry in the pipe approximately 5-8% solids ▪ Sediment and associate debris separated at upland site ▪ Clean sediment-free water returned to the lake

  13. Dredge Material Management Area ▪ Area where dredged sediment will be placed. ▪ At the end of the project area will be capped with sand and sodded Example ▪ Pinellas County Parks will take over for use as recreational fields

  14. Dredge Material Management Area ▪ 21 Acres at the top ▪ 50’ Deep ▪ Will contain approx. 800,000 CY during operation

  15. Why this Approach ▪ Positive long-term environmental benefits (water quality, fisheries, beneficial habitats) ▪ Increases recreational opportunities ▪ Expanded youth sports in the unincorporated Seminole area ▪ Expand upland recreational opportunities ▪ Reduces traffic and impacts on schools and residents on 98 th St. ▪ Reduces project cost by nearly $20 million dollars

  16. The Good News-Recent Water Quality ▪ Time series analysis shows significant decreasing trends ▪ Chl-a (Both Lobes) ▪ TP (Both Lobes) ▪ TN (Both Lobes) ▪ Turbidity (Both Lobes) ▪ TSS (Both Lobes)

  17. Next Steps in Restoration ▪ Allow the DMMA site to settle and consolidate for at least one year prior to capping ▪ Continue monitoring ▪ Surface water ▪ Groundwater wells around the DMMA ▪ Groundwater seepage into the lake ▪ Plant trees to offset removal from DMMA site ▪ Wetland restoration near DMMA site

  18. SWFWMD Project Video

  19. For additional project information and updates: ▪ Visit the project website at www.pinellascounty.org/lake_Seminole_restoration.htm or www.pinellascounty.org/environment/watershed/watershed- lake-seminole.htm ▪ Contact the Project Manager Rob Burnes Public Works Environmental Management 22211 US Hwy 19 N Bldg 10, Clearwater, FL 33765 Phone (727) 453-3149 Email rburnes@pinellascounty.org

  20. Special Thanks to our Funding Partners www.pinellascounty.org/publicworks

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend