Lake Seminole Restoration Dredging Presented by Rob Burnes MS, MAS - - PowerPoint PPT Presentation

lake seminole
SMART_READER_LITE
LIVE PREVIEW

Lake Seminole Restoration Dredging Presented by Rob Burnes MS, MAS - - PowerPoint PPT Presentation

Lake Seminole Restoration Dredging Presented by Rob Burnes MS, MAS Senior Environmental Scientist Pinellas County Public Works Background 684 acres 5.5 feet average depth Control structures regulate lake level Primarily used for


slide-1
SLIDE 1

Lake Seminole Restoration Dredging

Presented by Rob Burnes MS, MAS Senior Environmental Scientist Pinellas County Public Works

slide-2
SLIDE 2

Background

▪ 684 acres ▪ 5.5 feet average depth ▪ Control structures regulate lake

level

▪ Primarily used for recreation ▪ Fish community dominated by

sunfish family

▪ Healthy emergent and

submerged vegetation communities

slide-3
SLIDE 3

Lake Seminole History-1940’s

▪ Tidal estuarine system

Mangroves

Salt marshes

▪ Lake created in late-1940’s

Irrigation for orange groves

Potable water source

▪ Impounded an arm of Long

Bayou

▪ Flooded the system with

freshwater from Long Creek

slide-4
SLIDE 4

Lake Seminole History-1950’s & 1960’s

▪ Rapid expansion in the

area surrounding the lake

▪ Start of decline in

ecological conditions

▪ Lake Seminole Park

Constructed

▪ Current semi-circular weir

installed in late 1960’s

slide-5
SLIDE 5

Lake Seminole History-1970’s & 1980’s

Land use Switch

1976 Lake Seminole Bypass Canal created

By the mid to late 1980’s

Water quality was at an all-time low

Nuisance vegetation at an all time high

1989 Pinellas BOCC passes resolution of long-term management plan

slide-6
SLIDE 6

Lake Seminole History-1990’s to Present

▪ Built out watershed ▪ Poor water quality

Habitat loss

Decline of sport fishery

Harmful algal blooms

▪ Restoration efforts kick into

high gear

▪ Watershed management

plan finalized in 2001

slide-7
SLIDE 7

Lake Seminole Restoration Efforts

1971- Elimination of direct input from wastewater plant 1987- Grass Carp introduced 1990’s- Stormwater pond rehabilitations 2001- Lake Seminole WMP 2002- Littoral shelf sediment removal and revegetation 2006- Lake draw-down and nuisance vegetation removal, replanting, and drainage improvements 2007- Lake Seminole Reasonable Assurance Plan adopted 2010’s- Construction of alum stormwater treatment systems

slide-8
SLIDE 8

Reasonable Assurance Plan

▪ Developed in response to

being an impaired waterbody pursuant to section 303(d) of the federal Clean Water Act

▪ Plan finalized in 2007, updated

every 4 years

▪ Defined Structural,

Management, Legal, and Policy Components

slide-9
SLIDE 9

Organic Sediment Dredging

Number one recommended project in Reasonable Assurance Plan

Removal of 900,000 cubic yards

  • f organic sediments

Result in removal of ▪

416 tons of TN

77 tons of TP

Goal is to reduce lake’s internal nutrient loads

slide-10
SLIDE 10

In-Lake Dredging Timeline

▪ Dredge Material Management

Area (DMMA) construction started in January 2019

▪ Active dredging to began in

December 2019

▪ Dredging to be completed by

2021

slide-11
SLIDE 11

Hydraulic Dredging-How it Works

▪ Dredge barge moved

into place by tender vessels

▪ Dredge template loaded

  • nto barge GIS system

▪ Cutter head of barge

will loosen muck and vacuum will suck up sediment

slide-12
SLIDE 12

Hydraulic Dredging-How it Works

▪ Sediment then sent by pipe

to upland dewatering site

▪ Slurry in the pipe

approximately 5-8% solids

▪ Sediment and associate

debris separated at upland site

▪ Clean sediment-free water

returned to the lake

slide-13
SLIDE 13

Dredge Material Management Area

Example

Area where dredged sediment will be placed.

At the end of the project area will be capped with sand and sodded

Pinellas County Parks will take over for use as recreational fields

slide-14
SLIDE 14

Dredge Material Management Area

21 Acres at the top

50’ Deep

Will contain approx. 800,000 CY during

  • peration
slide-15
SLIDE 15

Why this Approach

Positive long-term environmental benefits (water quality, fisheries, beneficial habitats)

Increases recreational opportunities

Expanded youth sports in the unincorporated Seminole area

Expand upland recreational opportunities

Reduces traffic and impacts on schools and residents on 98th St.

Reduces project cost by nearly $20 million dollars

slide-16
SLIDE 16

The Good News-Recent Water Quality

▪ Time series analysis

shows significant decreasing trends

Chl-a (Both Lobes)

TP (Both Lobes)

TN (Both Lobes)

Turbidity (Both Lobes)

TSS (Both Lobes)

slide-17
SLIDE 17

Next Steps in Restoration

▪ Allow the DMMA site to settle and consolidate

for at least one year prior to capping

▪ Continue monitoring

▪ Surface water ▪ Groundwater wells around the DMMA ▪ Groundwater seepage into the lake

▪ Plant trees to offset removal from DMMA site ▪ Wetland restoration near DMMA site

slide-18
SLIDE 18

SWFWMD Project Video

slide-19
SLIDE 19

For additional project information and updates:

▪ Visit the project website at

www.pinellascounty.org/lake_Seminole_restoration.htm

  • r

www.pinellascounty.org/environment/watershed/watershed- lake-seminole.htm

▪ Contact the Project Manager

Rob Burnes Public Works Environmental Management 22211 US Hwy 19 N Bldg 10, Clearwater, FL 33765 Phone (727) 453-3149 Email rburnes@pinellascounty.org

slide-20
SLIDE 20

www.pinellascounty.org/publicworks

Special Thanks to our Funding Partners