Why Do the Lights Go Out? Daniel Kirschen Close Professor of - - PowerPoint PPT Presentation

why do the lights go out
SMART_READER_LITE
LIVE PREVIEW

Why Do the Lights Go Out? Daniel Kirschen Close Professor of - - PowerPoint PPT Presentation

Why Do the Lights Go Out? Daniel Kirschen Close Professor of Electrical Engineering University of Washington How do we get electricity? Load Generation Transmission Distribution Power System How is a Power System Structured? One-line diagram


slide-1
SLIDE 1

Why Do the Lights Go Out?

Daniel Kirschen Close Professor of Electrical Engineering University of Washington

slide-2
SLIDE 2

How do we get electricity?

Load Generation Distribution Power System Transmission

slide-3
SLIDE 3

How is a Power System Structured?

One-line diagram representation

slide-4
SLIDE 4

Components

Generators Transformers Transmission lines Loads (Consumers) Busbars Distribution feeders

slide-5
SLIDE 5

Generating units

Multiple generators are connected to the system

slide-6
SLIDE 6

Transmission network

Multiple path across the transmission network

slide-7
SLIDE 7

Distribution network

Single path across the distribution network Distribution network is radial

slide-8
SLIDE 8

Faults

  • Breakdown of the

insulation around the electric cable

  • Creates a short circuit
  • Large current that must

be interrupted quickly

– Safety – Destroy the equipment

slide-9
SLIDE 9

What causes faults?

  • People digging up the street
  • Rats chewing up cables
  • Aging of the insulation
  • Branches flying into the lines
  • Squirrels jumping from one conductor to

another

slide-10
SLIDE 10

What causes faults?

Wind…

slide-11
SLIDE 11

What causes faults?

Lightning…

slide-12
SLIDE 12

What causes faults?

Snow and ice…

slide-13
SLIDE 13

What causes faults?

Too much current…

slide-14
SLIDE 14

Fault in the distribution network

Because distribution network is radial, a single fault makes the lights go out

slide-15
SLIDE 15

Getting the power back on

The utility company re-energizes the blacked out part

  • f the system by closing a normally open switch

Normally open switch

slide-16
SLIDE 16

Fault in the transmission network

slide-17
SLIDE 17

Fault in the transmission network

Because the transmission network is meshed (multiple paths), a single faults does not cause the lights to go out

slide-18
SLIDE 18

What if it happens on a day when the load is high?

The current that was flowing in the faulted line goes through the remaining lines

slide-19
SLIDE 19

What if it happens on a day when the load is high?

The overloaded line is disconnected The system is split in two parts Will the lights stay on?

slide-20
SLIDE 20

Balancing consumption and production

Electrical energy Consumer Producer Conservation of energy: Power input = power output

slide-21
SLIDE 21

Analogy: Bicycle on a Hill

Power input: human effort Power output: climbing the hill Speed of the bike: stored kinetic energy

slide-22
SLIDE 22

Analogy: Bicycle on a Hill

Power input: human effort Power output: climbing the hill Power produced by generators Power consumed by loads Speed of the bike: stored kinetic energy Frequency of the ac voltage: stored kinetic energy

slide-23
SLIDE 23

Bicycle in steady state

Human effort = rate of climb speed is constant Generation = load frequency is constant

slide-24
SLIDE 24

Slope suddenly gets steeper…

Human effort < rate of climb speed decreases (until human effort increases) Generation < load frequency decreases (until generation increases)

slide-25
SLIDE 25

Slope suddenly gets less steep…

Human effort > rate of climb speed increases (until human effort decreases) Generation > load frequency increases (until generation decreases)

slide-26
SLIDE 26

Cyclist suddenly start pedaling less hard…

Human effort < rate of climb speed decreases (until human effort increases) Generation < load frequency decreases (until generation increases)

slide-27
SLIDE 27

Extending the analogy to multiple generators

Each cyclist is like a generator The transmission system is like the chain on the bike

slide-28
SLIDE 28

Generator failure

Generator failure equivalent to cyclist stopping to pedal Generation < load frequency decreases

slide-29
SLIDE 29

What happens when the speed of a bicycle decreases too much?

slide-30
SLIDE 30

What happens when the frequency decreases too much?

slide-31
SLIDE 31
slide-32
SLIDE 32

Frequency limits

  • The power system is much less stable than a

bike

  • Normal frequency: 60 Hz
  • Normal limits: 59.5 Hz to 60.5 Hz
  • Emergency limits: 59 Hz to 61 Hz
  • System collapse: 57.5 Hz
slide-33
SLIDE 33

How do we prevent blackouts?

  • Mostly preventive security

– Operate the system with a safety margin big enough to handle the loss of one component – N‐1 security criterion – Loss of one generator  reserve generation capacity – Loss of one transmission line  limit on the flow allowed

  • n each line
  • On‐line contingency analysis

– Check all N‐1 conditions using a power flow calculations – Adjust operating conditions if needed

slide-34
SLIDE 34

Failure of a large generating unit

49.20 49.30 49.40 49.50 49.60 49.70 49.80 49.90 50.00 50.10 12:24:00 12:24:30 12:25:00 12:25:30 12:26:00 12:26:30 12:27:00 12:27:30 12:28:00 12:28:30 12:29:00 12:29:30

National Grid managed to increase the output of the remaining generators fast enough

slide-35
SLIDE 35

European incident of 4 November 2006

slide-36
SLIDE 36

Line disconnected to let the ship pass safely Other lines disconnected

European incident of 4 November 2006

slide-37
SLIDE 37

European incident of 4 November 2006

slide-38
SLIDE 38

Frequency in the Western part

Automatic Load Shedding

More load than generation frequency decreases System collapse avoided by disconnecting loads

slide-39
SLIDE 39

European incident of 4 November 2006

  • Bad news

– 15 million consumers disconnected – In Italy, France, Spain, Belgium, Netherlands

  • Good news

– All consumers reconnected in 45 minutes – The system did not collapse… but it was close!

  • If the system had collapsed, reconnecting it

would probably have taken a day or so…

slide-40
SLIDE 40

North East US Blackout of 2003

  • Normal summer day
  • State estimator at control center in Cleveland

stops working

– Operators lose “situation awareness”

  • Operators do not realize that the state estimator

is not working

  • One line overloads and trips
  • Other lines overload and trip
  • System collapses, dragging down all of the North

East USA

slide-41
SLIDE 41
slide-42
SLIDE 42
slide-43
SLIDE 43

Consequences of the blackout of 15 August 2003

  • 50 million people affected
  • Restoration not completed for 4 days
  • Cost: ~ $5 to $11 billion
slide-44
SLIDE 44

Getting the power back on after a blackout

  • Can’t just reclose the switch
  • All of the power plants have shut down to avoid

damage

  • They all need to be restarted
  • But to restart a power plant… you need electricity!
  • Where do you get it?

– Small diesel generators – Hydro power plants – Neighboring power systems

  • Slow and complex process
  • Takes at least 8 hours to complete for a large system
slide-45
SLIDE 45

Research directions

  • Why do we get blackouts even when the

system is “N‐1 secure”?

– Use Monte Carlo simulations – Understand blackout mechanisms – Develop a proper measure of risk

  • Develop techniques to implement corrective

security measures

– React after a fault has taken place – Cheaper and more flexible

  • Understand impact of information failures
slide-46
SLIDE 46

Conclusions

  • We have gotten used to a high level of

reliability from the power system

  • Very costly, large scale incidents can still

happen

  • Keeping the lights on remains a big challenge
  • A good example of “systems engineering”

– Study the various components – Study how they fit together – Mathematical modeling