Whitehorse, March 18, 2013 Sonny Banjac Manager, Northern Projects - - PowerPoint PPT Presentation

whitehorse march 18 2013 sonny banjac manager northern
SMART_READER_LITE
LIVE PREVIEW

Whitehorse, March 18, 2013 Sonny Banjac Manager, Northern Projects - - PowerPoint PPT Presentation

Yukon Energy Corporation: Wind Workshop Wind Energy Development and Integration in the Yukon Whitehorse, March 18, 2013 Sonny Banjac Manager, Northern Projects Overview 1. Intro to Sea Breeze Power Corp. & the Cape Scott Wind Farm 2.


slide-1
SLIDE 1

Yukon Energy Corporation: Wind Workshop Wind Energy Development and Integration in the Yukon

Whitehorse, March 18, 2013

Sonny Banjac Manager, Northern Projects

slide-2
SLIDE 2

Overview

  • 1. Intro to Sea Breeze Power Corp.

& the Cape Scott Wind Farm

  • 2. Steps of Wind Power Development
slide-3
SLIDE 3

Company Overview: Sea Breeze Power Corp.

  • Developer of renewable energy and

transmission projects, mostly in BC and pacific US

  • Office in Vancouver, ~20 employees
  • Publicly traded company on TSX.V
  • Developed first wind farm on the BC coast at

Cape Scott (99MW)

slide-4
SLIDE 4
slide-5
SLIDE 5

Status of Global Wind Power Installation

http://www.gwec.net/fileadmin/documents/NewsDocuments/Annual_report_2011_lowres.pdf

slide-6
SLIDE 6

Wind Power in Canada

http://www.canwea.ca/farms/wind-farms_e.php

slide-7
SLIDE 7
slide-8
SLIDE 8
  • 55 Vestas V100 1.8MW wind

turbines

  • 99 MW capacity

(electricity for 100,000 people)

  • 80m hub height, 50m blades.
  • Sold to IPR-GDF-Suez
  • Currently under

construction

  • COD in Summer 2015
  • 300 person yrs of

employment during construction

  • Similar amount spread
  • ver 20 yrs of
  • perations.
slide-9
SLIDE 9

Wind Development: Starting Point

  • A hunch, desktop

scouting

  • Desktop data

review

  • Site visit
  • Obtaining

land rights

slide-10
SLIDE 10

Target End Point

  • A project that can be

financed and built

  • Wind resource well

mapped

  • Costs and risks well

established

  • Absence of critical flaws

– no surprises!

  • Relationships
slide-11
SLIDE 11

Steps in the Development Process

1. Site identification & land rights 2. Pre-feasibility 3. Feasibility 4. Marketing-Financing 5. Detailed design & permitting 6. Construction 7. Operation 8. Decommissioning

slide-12
SLIDE 12

Steps in the Development Process

1. Site identification & land rights 2. Pre-feasibility 3. Feasibility 4. Marketing-Financing 5. Detailed design & permitting 6. Construction 7. Operation 8. Decommissioning

  • Increasing confidence =

decreasing risk

  • Increasing external

support

  • Increasing cost
  • Increasing value
  • Prioritization &

Go / No-Go

slide-13
SLIDE 13

http://www.al.gov.bc.ca/clad/IPP_guidebook.pdf

slide-14
SLIDE 14

Steps in the Development Process

1. Site identification & land rights 2. Pre-feasibility 3. Feasibility 4. Marketing-Financing 5. Detailed design & permitting 6. Construction 7. Operation 8. Decommissioning

DESKTOP:

  • Expected wind resource
  • Ease of access
  • Transmission
  • Synergies
  • Market opportunities
  • Environmental setting
  • Land status
  • First Nations
  • Community support

SITE VISIT:

  • Locations for met towers
  • Environmental screening
  • Engineering screening
slide-15
SLIDE 15

Steps in the Development Process

1. Site identification & land rights 2. Pre-feasibility 3. Feasibility 4. Marketing-Financing 5. Detailed design & permitting 6. Construction 7. Operation 8. Decommissioning

  • 1st meteorological tower
  • Wind speed analysis over

12 months

slide-16
SLIDE 16

Met Tower Installation

Courtesey of Sea Breeze Power Corp. http://www.wagonerwind.com/images/60-meter-met-tower-mast-and-vanes.jpg

slide-17
SLIDE 17

Steps in the Development Process

1. Site identification & land rights 2. Pre-feasibility 3. Feasibility 4. Marketing-Financing 5. Detailed design & permitting 6. Construction 7. Operation 8. Decommissioning

  • Additional met towers
  • Turbine suitability
  • Geotechnical studies
  • Optimal capacity (transmission

constrains)

  • Layout Optimization Energy

production estimate

  • Preliminary BOP studies
  • Financial modeling
  • Negotiations with turbine

suppliers

  • Targeted environmental

studies

  • Consultation
slide-18
SLIDE 18

Steps in the Development Process

1. Site identification & land rights 2. Pre-feasibility 3. Feasibility 4. Marketing-Financing 5. Detailed design & permitting 6. Construction 7. Operation 8. Decommissioning

  • Business model
  • Negotiation with a financial

partner

  • Buyer (e.g. Electricity

Purchase Agreement from Yukon Energy)

  • Green attributes
slide-19
SLIDE 19

Steps in the Development Process

1. Site identification & land rights 2. Pre-feasibility 3. Feasibility 4. Marketing-Financing 5. Detailed design & permitting 6. Construction 7. Operation 8. Decommissioning

  • Environmental assessment
  • Detailed engineering
  • Interconnection studies
  • Financial close
  • Construction permits
  • Contracting & supply
slide-20
SLIDE 20

Steps in the Development Process

1. Site identification & land rights 2. Pre-feasibility 3. Feasibility 4. Marketing-Financing 5. Detailed design & permitting 6. Construction 7. Operation 8. Decommissioning

  • Site preparation
  • Transportation
  • Construction: Roads,

foundations, electrical, turbine installation

  • Commissioning
  • Environmental monitoring
slide-21
SLIDE 21

Steps in the Development Process

1. Site identification & land rights 2. Pre-feasibility 3. Feasibility 4. Marketing-Financing 5. Detailed design & permitting 6. Construction 7. Operation 8. Decommissioning

  • Plant operation
  • Wind forecasting
  • Scheduled & Unscheduled

Maintenance

  • Environmental monitoring
slide-22
SLIDE 22

Steps in the Development Process

1. Site identification & land rights 2. Pre-feasibility 3. Feasibility 4. Marketing-Financing 5. Detailed design & permitting 6. Construction 7. Operation 8. Decommissioning

  • Environmental remediation
  • Residual value of assets?
slide-23
SLIDE 23