Westbury UFSD Capital Improvements Program Construction Update - - PowerPoint PPT Presentation
Westbury UFSD Capital Improvements Program Construction Update - - PowerPoint PPT Presentation
Westbury UFSD Capital Improvements Program Construction Update July 10, 2019 Presentation Overview High School Program Review of Project Scope Renderings of Facility Construction Update Minority / Women / Local Business
- High School Program
– Review of Project Scope – Renderings of Facility – Construction Update – Minority / Women / Local Business Involvement
- Middle School Program
– Review of Project Scope – Renderings of Facility – Construction Update (Roofing Project / Additions & Alterations)
Presentation Overview
- 14 classroom addition
- Cafeteria addition with warming kitchen and connecting
link to existing building
- Science Lab Alterations
- Boilers, pumps and controls
- Floors and ceilings
- Site Work – parking lot modifications
- Masonry Restoration – areas of work impact
- Upgrade Electrical Service
Project Scope for HS
EVT-1 EVT-2 T-1 T2
TERRAZZO BASIS OF DESIGN
T4 EVT-2 EVT-3 T3 EVT-3
Terrazzo Basis of Design
1 3884 FROST -FORBO MARMOLEUM FRESCO 2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE 33736 GREEN SHIMMER -FORBO MARMOLEUM CONCRETE T-4 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE
Enhance Vinyl Tile
EVT-1 AD521 LIMO -ALTRO DOLCE TILE EVT-2 AD512 LECHE -ALTRO DOLCE TILE EVT-3 AD605 CILANTRO -ALTRO DOLCE TILE
TERRAZZO BASIS OF DESIGN
T4 LS-1 T3Terrazzo Basis of Design
1 3884 FROST -FORBO MARMOLEUM FRESCO 2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE 33736 GREEN SHIMMER -FORBO MARMOLEUM CONCRETE T-43711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE
Sheet Linoleum
LS-1 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE LS-2 3240 WILLOW -FORBO MARMOLEUM CONCRETE LS-3 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE
Cladding Panel System
PRODEX CREAM -PRODEMA PANELS
Brick Veneer / Thin Brick
PENNSYLVANIA MOLDED -BERKS WATSONTOWN BRICK COMPANY
Thin Cast Limestone
SMOOTH OAK RIDGE RENAISSANCE MASONRY UNITS ARRISCRAFT INTERNATIONAL BUILDING STONE
- Poured concrete for footings and foundation walls for Classroom
Addition
- Installed in-ground sanitary plumbing piping and electrical
conduits in preparation of concrete slab at Classroom Addition
- Placed and compacted soil and stone bed in preparation for
concrete slab pour
- Installed vapor barrier and slab reinforcement
- Poured concrete slab for Classroom Addition
- Received delivery for cold metal framing and commenced work
- n perimeter walls
Construction Update
- Performed abatement and demolition of boilers: 66%
- Formed and poured concrete pads for new boilers: 66%
- Received boiler sections and relocated material to boiler room
for assembly
- Existing sanitary system at Cafeteria Addition remediation: 100%
- Installation of new sanitary structures and interconnecting
piping at Cafeteria Addition: 95%
- Commenced excavation for foundation walls at Cafeteria
Addition
Construction Update
- Termination of feeders at new transformer in driveway: 60%
- PSEG installed pole for new electrical service to transformer
- Delivered new panelboards to electric room in basement
- Commenced asbestos abatement operations at 2nd floor
classrooms
- New Storm Drainage Installation: 60%
- Working on drainage system for new courtyard by locker room
- Completed foundations and concrete slab for East Connecting
Corridor
Construction Update
Classroom Addition – Prep for Pour
Classroom Addition – Slab Pour
Cafeteria Addition – Sanitary System
Boiler Room Operations – Demo & Assembly
Classroom Addition – Interior and Exterior Wall Framing
Electrical Service – Installation of New Transformer Vault
Electrical Service – Switchgear and Conduit Runs
Minority / Women / Local Business Involvement
Elite Construction has been actively meeting with each contractor on a weekly basis to examine their contract and workforce program. The contractors and consultants affiliated with the project are making a “Good Faith Effort” to achieve the District’s goals.
- As the project continues, different skills will be required and
personnel currently assigned to the project will be modified accordingly.
- Individuals are required to obtain their OSHA 10 hour certification and
provide to our office.
- Individuals are also required to be part of the Local Unions that will
man this project: (Carpenters, Brick Masons, Laborers, Abatement, Plumbing, Mechanical, Electrical )
Minority / Women / Local Business Involvement
- VRD Contracting, Inc. – General Construction (WBE)
– A&S Rebar, Inc. – Rebar Supplier (WBE) – Baybrent Construction – Ceramic Tiling (MBE) – Linda Lee Construction - Taping (WBE) – Park Ave Building Materials – Bldg Materials (MBE) – Island Nursery – Landscaping (WBE) Minority / Women / Local Business Involvement
- Thermo Tech Combustion – Mechanical (HVAC)
– DemoTec Mechanical – Boiler Demolition (WBE)
- WHM Plumbing & Heating, Inc.– Plumbing
– AMG Demolition – Hot Water Tank Removal (WBE)
- Roland’s Electric, Inc. – Electrical & Fire Alarm
– Advance Sound Co – PA/ Clocks / Smartboards (WBE) – CMT Lighting Co. – Lighting Supplies (WBE) Minority / Women / Local Business Involvement
- 12 classroom addition with connection to existing building
- Café addition-standard construction
- Alterations to existing kitchen/cafeteria
- Roof replacement and masonry
- Mechanical system: replacement and abatement
- Plumbing with abatement
- Alterations-Increase corridor width, handicapped toilets
and handicapped access throughout building Project Scope for MS
- P/A intercom, clocks, security, F/A
- Ceilings, floors, and casework in all spaces
- Site Work to include parking lot reconstruction
- Upgrade Electrical Service
- Abatement in Crawl Space, Floors & Ceilings
Project Scope for MS
Wiedersum Associates Architects
PERSPECTIVE VIEW 1
Wiedersum Associates Architects
PERSPECTIVE VIEW 2
Wiedersum Associates Architects
PERSPECTIVE VIEW 3
- Middle School Existing Roof Replacement Project
– Contract was awarded to Niko K Construction – Work is scheduled to commence on July 15, 2019 – Contract is scheduled for Summers of 2019 and 2020 – Contract requires abatement, masonry reconstruction and roof replacement of all existing surfaces – Requires coordination with prime contractors on Middle School Additions and Alterations Project
- Middle School Additions and Alterations Project