Westbury UFSD Capital Improvements Program Construction Update - - PowerPoint PPT Presentation

westbury ufsd capital improvements program construction
SMART_READER_LITE
LIVE PREVIEW

Westbury UFSD Capital Improvements Program Construction Update - - PowerPoint PPT Presentation

Westbury UFSD Capital Improvements Program Construction Update July 10, 2019 Presentation Overview High School Program Review of Project Scope Renderings of Facility Construction Update Minority / Women / Local Business


slide-1
SLIDE 1

Westbury UFSD Capital Improvements Program Construction Update July 10, 2019

slide-2
SLIDE 2
  • High School Program

– Review of Project Scope – Renderings of Facility – Construction Update – Minority / Women / Local Business Involvement

  • Middle School Program

– Review of Project Scope – Renderings of Facility – Construction Update (Roofing Project / Additions & Alterations)

Presentation Overview

slide-3
SLIDE 3
  • 14 classroom addition
  • Cafeteria addition with warming kitchen and connecting

link to existing building

  • Science Lab Alterations
  • Boilers, pumps and controls
  • Floors and ceilings
  • Site Work – parking lot modifications
  • Masonry Restoration – areas of work impact
  • Upgrade Electrical Service

Project Scope for HS

slide-4
SLIDE 4

EVT-1 EVT-2 T-1 T2

TERRAZZO BASIS OF DESIGN

T4 EVT-2 EVT-3 T3 EVT-3

Terrazzo Basis of Design

1 3884 FROST -FORBO MARMOLEUM FRESCO 2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE 33736 GREEN SHIMMER -FORBO MARMOLEUM CONCRETE T-4 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE

Enhance Vinyl Tile

EVT-1 AD521 LIMO -ALTRO DOLCE TILE EVT-2 AD512 LECHE -ALTRO DOLCE TILE EVT-3 AD605 CILANTRO -ALTRO DOLCE TILE

slide-5
SLIDE 5 LS-3 LS-2 T-1 T2

TERRAZZO BASIS OF DESIGN

T4 LS-1 T3

Terrazzo Basis of Design

1 3884 FROST -FORBO MARMOLEUM FRESCO 2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE 33736 GREEN SHIMMER -FORBO MARMOLEUM CONCRETE T-43711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE

Sheet Linoleum

LS-1 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE LS-2 3240 WILLOW -FORBO MARMOLEUM CONCRETE LS-3 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE

slide-6
SLIDE 6

Cladding Panel System

PRODEX CREAM -PRODEMA PANELS

Brick Veneer / Thin Brick

PENNSYLVANIA MOLDED -BERKS WATSONTOWN BRICK COMPANY

Thin Cast Limestone

SMOOTH OAK RIDGE RENAISSANCE MASONRY UNITS ARRISCRAFT INTERNATIONAL BUILDING STONE

slide-7
SLIDE 7
  • Poured concrete for footings and foundation walls for Classroom

Addition

  • Installed in-ground sanitary plumbing piping and electrical

conduits in preparation of concrete slab at Classroom Addition

  • Placed and compacted soil and stone bed in preparation for

concrete slab pour

  • Installed vapor barrier and slab reinforcement
  • Poured concrete slab for Classroom Addition
  • Received delivery for cold metal framing and commenced work
  • n perimeter walls

Construction Update

slide-8
SLIDE 8
  • Performed abatement and demolition of boilers: 66%
  • Formed and poured concrete pads for new boilers: 66%
  • Received boiler sections and relocated material to boiler room

for assembly

  • Existing sanitary system at Cafeteria Addition remediation: 100%
  • Installation of new sanitary structures and interconnecting

piping at Cafeteria Addition: 95%

  • Commenced excavation for foundation walls at Cafeteria

Addition

Construction Update

slide-9
SLIDE 9
  • Termination of feeders at new transformer in driveway: 60%
  • PSEG installed pole for new electrical service to transformer
  • Delivered new panelboards to electric room in basement
  • Commenced asbestos abatement operations at 2nd floor

classrooms

  • New Storm Drainage Installation: 60%
  • Working on drainage system for new courtyard by locker room
  • Completed foundations and concrete slab for East Connecting

Corridor

Construction Update

slide-10
SLIDE 10

Classroom Addition – Prep for Pour

slide-11
SLIDE 11

Classroom Addition – Slab Pour

slide-12
SLIDE 12

Cafeteria Addition – Sanitary System

slide-13
SLIDE 13

Boiler Room Operations – Demo & Assembly

slide-14
SLIDE 14

Classroom Addition – Interior and Exterior Wall Framing

slide-15
SLIDE 15

Electrical Service – Installation of New Transformer Vault

slide-16
SLIDE 16

Electrical Service – Switchgear and Conduit Runs

slide-17
SLIDE 17

Minority / Women / Local Business Involvement

slide-18
SLIDE 18

Elite Construction has been actively meeting with each contractor on a weekly basis to examine their contract and workforce program. The contractors and consultants affiliated with the project are making a “Good Faith Effort” to achieve the District’s goals.

  • As the project continues, different skills will be required and

personnel currently assigned to the project will be modified accordingly.

  • Individuals are required to obtain their OSHA 10 hour certification and

provide to our office.

  • Individuals are also required to be part of the Local Unions that will

man this project: (Carpenters, Brick Masons, Laborers, Abatement, Plumbing, Mechanical, Electrical )

Minority / Women / Local Business Involvement

slide-19
SLIDE 19
  • VRD Contracting, Inc. – General Construction (WBE)

– A&S Rebar, Inc. – Rebar Supplier (WBE) – Baybrent Construction – Ceramic Tiling (MBE) – Linda Lee Construction - Taping (WBE) – Park Ave Building Materials – Bldg Materials (MBE) – Island Nursery – Landscaping (WBE) Minority / Women / Local Business Involvement

slide-20
SLIDE 20
  • Thermo Tech Combustion – Mechanical (HVAC)

– DemoTec Mechanical – Boiler Demolition (WBE)

  • WHM Plumbing & Heating, Inc.– Plumbing

– AMG Demolition – Hot Water Tank Removal (WBE)

  • Roland’s Electric, Inc. – Electrical & Fire Alarm

– Advance Sound Co – PA/ Clocks / Smartboards (WBE) – CMT Lighting Co. – Lighting Supplies (WBE) Minority / Women / Local Business Involvement

slide-21
SLIDE 21
  • 12 classroom addition with connection to existing building
  • Café addition-standard construction
  • Alterations to existing kitchen/cafeteria
  • Roof replacement and masonry
  • Mechanical system: replacement and abatement
  • Plumbing with abatement
  • Alterations-Increase corridor width, handicapped toilets

and handicapped access throughout building Project Scope for MS

slide-22
SLIDE 22
  • P/A intercom, clocks, security, F/A
  • Ceilings, floors, and casework in all spaces
  • Site Work to include parking lot reconstruction
  • Upgrade Electrical Service
  • Abatement in Crawl Space, Floors & Ceilings

Project Scope for MS

slide-23
SLIDE 23

Wiedersum Associates Architects

PERSPECTIVE VIEW 1

slide-24
SLIDE 24

Wiedersum Associates Architects

PERSPECTIVE VIEW 2

slide-25
SLIDE 25

Wiedersum Associates Architects

PERSPECTIVE VIEW 3

slide-26
SLIDE 26
slide-27
SLIDE 27
  • Middle School Existing Roof Replacement Project

– Contract was awarded to Niko K Construction – Work is scheduled to commence on July 15, 2019 – Contract is scheduled for Summers of 2019 and 2020 – Contract requires abatement, masonry reconstruction and roof replacement of all existing surfaces – Requires coordination with prime contractors on Middle School Additions and Alterations Project

  • Middle School Additions and Alterations Project

– Project is currently out of bidding – Bids due date to be established; Anticipate bid opening prior to August 31, 2019

Construction Update

slide-28
SLIDE 28

Westbury UFSD Capital Improvements Program Construction Update Question and Answer