Westbury UFSD Capital Improvements Program Construction Update July 10, 2019 Presentation Overview High School Program Review of Project Scope Renderings of Facility Construction Update Minority / Women / Local Business


  1. Westbury UFSD Capital Improvements Program Construction Update July 10, 2019

  2. Presentation Overview • High School Program – Review of Project Scope – Renderings of Facility – Construction Update – Minority / Women / Local Business Involvement • Middle School Program – Review of Project Scope – Renderings of Facility – Construction Update (Roofing Project / Additions & Alterations)

  3. Project Scope for HS • 14 classroom addition • Cafeteria addition with warming kitchen and connecting link to existing building • Science Lab Alterations • Boilers, pumps and controls • Floors and ceilings • Site Work – parking lot modifications • Masonry Restoration – areas of work impact • Upgrade Electrical Service

  4. T-1 T2 T3 T4 TERRAZZO BASIS OF DESIGN Terrazzo Basis of Design 1 3884 FROST -FORBO MARMOLEUM FRESCO 2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE 33736 GREEN SHIMMER -FORBO MARMOLEUM CONCRETE T-4 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE Enhance Vinyl Tile EVT-1 AD521 LIMO -ALTRO DOLCE TILE EVT-2 AD512 LECHE -ALTRO DOLCE TILE EVT-1 EVT-2 EVT-3 EVT-2 EVT-3 EVT-3 AD605 CILANTRO -ALTRO DOLCE TILE

  5. T-1 T2 T3 T4 TERRAZZO BASIS OF DESIGN Terrazzo Basis of Design 1 3884 FROST -FORBO MARMOLEUM FRESCO 2 3708 FOSSIL -FORBO MARMOLEUM CONCRETE 33736 GREEN SHIMMER -FORBO MARMOLEUM LS-1 LS-2 LS-3 CONCRETE T-43711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE Sheet Linoleum LS-1 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE LS-2 3240 WILLOW -FORBO MARMOLEUM CONCRETE LS-3 3711 CLOUDY SAND -FORBO MARMOLEUM CONCRETE

  6. Cladding Panel System PRODEX CREAM -PRODEMA PANELS Brick Veneer / Thin Brick PENNSYLVANIA MOLDED -BERKS WATSONTOWN BRICK COMPANY Thin Cast Limestone SMOOTH OAK RIDGE RENAISSANCE MASONRY UNITS ARRISCRAFT INTERNATIONAL BUILDING STONE

  7. Construction Update • Poured concrete for footings and foundation walls for Classroom Addition • Installed in-ground sanitary plumbing piping and electrical conduits in preparation of concrete slab at Classroom Addition • Placed and compacted soil and stone bed in preparation for concrete slab pour • Installed vapor barrier and slab reinforcement • Poured concrete slab for Classroom Addition • Received delivery for cold metal framing and commenced work on perimeter walls

  8. Construction Update • Performed abatement and demolition of boilers: 66% • Formed and poured concrete pads for new boilers: 66% • Received boiler sections and relocated material to boiler room for assembly • Existing sanitary system at Cafeteria Addition remediation: 100% • Installation of new sanitary structures and interconnecting piping at Cafeteria Addition: 95% • Commenced excavation for foundation walls at Cafeteria Addition

  9. Construction Update • Termination of feeders at new transformer in driveway: 60% • PSEG installed pole for new electrical service to transformer • Delivered new panelboards to electric room in basement • Commenced asbestos abatement operations at 2 nd floor classrooms • New Storm Drainage Installation: 60% • Working on drainage system for new courtyard by locker room • Completed foundations and concrete slab for East Connecting Corridor

  10. Classroom Addition – Prep for Pour

  11. Classroom Addition – Slab Pour

  12. Cafeteria Addition – Sanitary System

  13. Boiler Room Operations – Demo & Assembly

  14. Classroom Addition – Interior and Exterior Wall Framing

  15. Electrical Service – Installation of New Transformer Vault

  16. Electrical Service – Switchgear and Conduit Runs

  17. Minority / Women / Local Business Involvement

  18. Minority / Women / Local Business Involvement Elite Construction has been actively meeting with each contractor on a weekly basis to examine their contract and workforce program. The contractors and consultants affiliated with the project are making a “Good Faith Effort” to achieve the District’s goals. • As the project continues, different skills will be required and personnel currently assigned to the project will be modified accordingly. • Individuals are required to obtain their OSHA 10 hour certification and provide to our office. • Individuals are also required to be part of the Local Unions that will man this project: (Carpenters, Brick Masons, Laborers, Abatement, Plumbing, Mechanical, Electrical )

  19. Minority / Women / Local Business Involvement • VRD Contracting, Inc. – General Construction (WBE) – A&S Rebar, Inc. – Rebar Supplier (WBE) – Baybrent Construction – Ceramic Tiling (MBE) – Linda Lee Construction - Taping (WBE) – Park Ave Building Materials – Bldg Materials (MBE) – Island Nursery – Landscaping (WBE)

  20. Minority / Women / Local Business Involvement • Thermo Tech Combustion – Mechanical (HVAC) – DemoTec Mechanical – Boiler Demolition (WBE) • WHM Plumbing & Heating, Inc.– Plumbing – AMG Demolition – Hot Water Tank Removal (WBE) • Roland’s Electric, Inc. – Electrical & Fire Alarm – Advance Sound Co – PA/ Clocks / Smartboards (WBE) – CMT Lighting Co. – Lighting Supplies (WBE)

  21. Project Scope for MS • 12 classroom addition with connection to existing building • Café addition-standard construction • Alterations to existing kitchen/cafeteria • Roof replacement and masonry • Mechanical system: replacement and abatement • Plumbing with abatement • Alterations-Increase corridor width, handicapped toilets and handicapped access throughout building

  22. Project Scope for MS • P/A intercom, clocks, security, F/A • Ceilings, floors, and casework in all spaces • Site Work to include parking lot reconstruction • Upgrade Electrical Service • Abatement in Crawl Space, Floors & Ceilings

  23. Wiedersum Associates Architects PERSPECTIVE VIEW 1

  24. Wiedersum Associates Architects PERSPECTIVE VIEW 2

  25. Wiedersum Associates Architects PERSPECTIVE VIEW 3

  26. Construction Update • Middle School Existing Roof Replacement Project – Contract was awarded to Niko K Construction – Work is scheduled to commence on July 15, 2019 – Contract is scheduled for Summers of 2019 and 2020 – Contract requires abatement, masonry reconstruction and roof replacement of all existing surfaces – Requires coordination with prime contractors on Middle School Additions and Alterations Project • Middle School Additions and Alterations Project – Project is currently out of bidding – Bids due date to be established; Anticipate bid opening prior to August 31, 2019

  27. Westbury UFSD Capital Improvements Program Construction Update Question and Answer

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.