Capital Planning Process FY 2015-17
Joint Legislative Committee on Capital Improvements
January 13, 2016
Capital Planning Process FY 2015-17 Joint Legislative Committee - - PowerPoint PPT Presentation
Capital Planning Process FY 2015-17 Joint Legislative Committee on Capital Improvements January 13, 2016 Capital Planning Process FY 2015-17 1. UNC Board of Governors 2015-17 Operating and Capital Budget Priorities December 2014 2.
Joint Legislative Committee on Capital Improvements
January 13, 2016
2015-17 Operating and Capital Budget Priorities
December 2014
Capital Planning Process
FY 2015-17
2015-17 Operating and Capital Budget Priorities
December 2014 Capital Planning Process
FY 2015-17
2015-17 Capital Priorities 2015-2021 Six-Year Strategic Capital Plan
Capital Planning Process
FY 2015-17
General Fund Projects
(Strategic Appropriated Capital Projects
Targeted Capital Renewal Projects
(R & R)
Repair and Renovation Allocation
Plan
Capital Planning Process
FY 2015-17
Previously Priority Institution/Project Request Authorized 2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 NORTH CAROLINA STATE UNIVERSITY 1 Engineering Building Oval 77,000,000 7,000,000 7,000,000 63,000,000 2 Science Commons Building 53,000,000 2,300,000 3,000,000 31,800,000 15,900,000 3 Plant Sciences Building 53,400,000 8,000,000 8,000,000 37,400,000 4 Broughton Hall Renovation & Addition (Chemistry) 117,900,000 5,895,000 5,895,000 70,740,000 35,370,000 5 Dabney Hall Renovation 57,800,000 2,890,000 2,890,000 34,680,000 17,340,000 6 Page Hall Renovation 10,000,000 7 Mann Hall Renovation and Addition 41,400,000 8 Gardner Hall Renovation & Addition 60,000,000 9 Williams Hall Renovation 42,000,000 10 Daniels Hall Renovation, Phase II 15,000,000 11 Polk Hall Renvoation, Phase II 20,500,000 12 Data Center III, Centennial Biomedical Campus 19,600,000 13 CVM Education Building 103,500,000 14 Management Teaching Facility 70,000,000 15 Poe Hall Renvovation 30,500,000 16 DesignTeaching Facility 65,000,000 17 Joyner Visitor Center Addition 9,200,000 18 Hillsborough Building Renovation 15,000,000 19 Engineering Building North 113,000,000 20 Burlington Labs Renovation 22,600,000 21 Teaching & Research Building (Hodges Site) 44,000,000 22 Facilities Services Building (Centennial Campus) 10,000,000 Totals 1,050,400,000 0 17,300,000 23,895,000 140,985,000 89,530,000 70,050,000 17,340,000
THE UNIVERSITY OF NORTH CAROLINA 2015-2021 Six-Year General Fund Capital Improvements Plan
Funding Plan
Capital Planning Process
FY 2015-17
Strategic Appropriated Capital Priorities Fund Request 1-ASU College of Nursing and Health Sciences $70,781,681 2-NCSU Engineering Building - Oval $77,000,000 3-UNCC Science Building $120,064,206 4-UNCW Allied Health/Human Sciences $67,338,504 5-NCSSM Discovery Center's Reynolds East Residence Hall $7,600,000 6-ECU Life Sciences and Biotechnology Building $187,135,750 7-UNCG Nursing and Instructional Building $124,765,400 8-UNCCH Medical Education Building-Berryhill Replacement $70,600,000 9-NCAT New College of Engineering Facility $99,155,300 10-WCU Science / STEM Facility $114,932,235 11-WSSU Sciences Building $53,853,600 Total: $993,226,676
Board of Governors Strategic Appropriated Capital Priorities FY 2015-2017 Capital Planning Process
FY 2015-17
Strategic Appropriated Capital Priorities Fund Request 1-ASU College of Nursing and Health Sciences $70,781,681 2-NCSU Engineering Building - Oval $77,000,000 3-UNCC Science Building $120,064,206 4-UNCW Allied Health/Human Sciences $67,338,504 5-NCSSM Discovery Center's Reynolds East Residence Hall $7,600,000 6-ECU Life Sciences and Biotechnology Building $187,135,750 7-UNCG Nursing and Instructional Building $124,765,400 8-UNCCH Medical Education Building-Berryhill Replacement $70,600,000 9-NCAT New College of Engineering Facility $99,155,300 10-WCU Science / STEM Facility $114,932,235 11-WSSU Sciences Building $53,853,600 Total: $993,226,676
Board of Governors Strategic Appropriated Capital Priorities FY 2015-2017 Capital Planning Process
FY 2015-17
Capital Planning Process
FY 2015-17
28% of NC average annual Debt Capacity required by UNC GF Capital Plan
Capital Planning Process
FY 2015-17
Capital Planning Process
FY 2015-17
Criteria For Priority Evaluation :
Capital Planning Process
FY 2015-17
Total Project Value Submitted: $650,620,907
Appalachian State University University of North Carolina at Chapel Hill
Sanford Hall - Comprehensive Renovation & Modernization $19,616,000 Hamilton Hall Envelope Restoration $18,000,000 College of Education Annex-Comprehensive Renovation & Modernization $3,500,000 Kenan Laboratories HVAC Replacement $12,000,000 Masonry, Waterproofing, Ext. Glass Wall, Stair Repairs-Raley Hall $3,800,000 Morehead Planetarium and Science Center HVAC Replacement $6,000,000East Carolina University University of North Carolina at Charlotte
Brewster Building B-C-D Classroom Wings Renovations $14,700,000 Academic Complex Modernization $8,611,574 Whichard Building Comprehensive Renovation $6,100,000 Cedar, Sycamore, and Hickory Halls Repurposing $10,500,000 Austin Building Comprehensive Renovation $15,500,000 Cone Center Renovation $26,000,000Elizabeth City State University University of North Carolina at Greensboro
Moore Hall-Complete Building Renovation $8,510,000 Jackson Library Renovation $29,975,760 GR Little Library-Complete Building Renovation $4,500,000 HHP Building HVAC and Fire Alarm Renovation $15,746,413 Vaughan Center-Complete Building Renovation $8,000,000 Steam Pipe Infrastructure Improvements $12,538,000Fayetteville State University University of North Carolina at Pembroke
Lyons Science Building-Comprehensive Renovation $10,616,373 West Hall - Comprehensive Rehabilitation $10,000,000 Storm Water & Sewer Infrastructure Improvements $7,930,094 New School of Business $34,550,680 G.L. Butler Building-Comprehensive Renovation $13,554,766 Givens Performing Arts Center Modernization & Addition $12,893,358North Carolina A & T State University University of North Carolina School of the Arts
Carver Hall Renovation $8,597,560 Old Library Renovation $7,350,000 Police Station-Brown Hall Renovation $7,597,560 Performance Place Misc Renovations $2,130,000 Price Hall Renovation $8,602,200 High Point Studio Renovation $9,560,000North Carolina Central University University of North Carolina at Wilmington
Taylor Education Building - Comprehensive Renovation $7,500,000 New Science Building $29,980,500 Hubbard-Totten Building/Lee Biology Building Comprehensive Renovation $10,000,000 DeLoach Hall Renovation $15,000,000 Fine Arts Building-Comprehensive Renovation $8,454,000 Bear Hall Renovation $14,706,720North Carolina School of Science and Mathmatics Western Carolina University
Discovery Center Dining Facilities, Dining Room, Student Center(partial) $13,500,000 Energy Production Facility $37,908,769 Renovations to Academic Buildings $5,129,000 Moore Building Renovation $25,793,580 Student Transportation & Furniture $782,800Winston Salem State University North Carolina State University
Restore the Core Ph II - Hauser Hall for Music $12,000,000 Thermal Utilities and Infrastructure Upgrades $6,980,000 Restore the Core Ph II - Physical Plant for Arts+Design Studies $15,000,000 Bureau of Mines Building Renovation $6,000,000UNC Center for Public Television
Ricks Hall Renovation 3 $8,500,000 Technology Replacement Phase 1 $5,000,000University of North Carolina at Asheville
Technology Replacement Phase 2 $5,000,000 Replace Carmichael Hall and University Lecture Hall $33,900,000 Spectrum Incentive Auction $5,000,000 Renovation and Addition to Owen Hall $15,150,000 Lipinsky Hall Modernization $12,355,200Targeted Capital Renewal Project Submittals
Targeted Capital Renewal Projects
2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 Institution Value $40,340,000 $40,616,373 $41,279,000 $39,654,000 $42,827,574 $46,597,560 ASU Sanford Hall - Comprehensive Renovation & Modernization $19,616,000 $19,616,000 ECU Brewster Building B-C-D Classroom Wings Renovations $14,700,000 $14,700,000 ECU Whichard Building Comprehensive Renovation $6,100,000 $6,100,000 ECSU Moore Hall-Complete Building Renovation $8,510,000 $8,510,000 ECSU GR Little Library-Complete Building Renovation $4,500,000 $4,500,000 FSU Lyons Science Building-Comprehensive Renovation $10,616,373 $10,616,373 NCAT Carver Hall Renovation $8,597,560 $8,597,560 NCCU Taylor Education Building-Comprehensive Renovation $7,500,000 $7,500,000 NCCU Fine Arts Building-Comprehensive Renovation $8,454,000 $8,454,000 NCSSM Renovations to Academic Buildings $5,129,000 $5,129,000 NCSU Thermal Utilities and Infrastructure Upgrades $6,980,000 $6,980,000 NCSU Bureau of Mines Building Renovation $6,000,000 $6,000,000 NCSU Ricks Hall Renovation $8,500,000 $8,500,000 UNCA Renovation and Addition to Owen Hall $15,150,000 $15,150,000 UNCCH Hamilton Hall Envelope Restoration $18,000,000 $18,000,000 UNCC Academic Complex Modernization $8,611,574 $8,611,574 UNCG Jackson Library Renovation $20,000,000 $20,000,000 UNCP West Hall - Comprehensive Rehabilitation $10,000,000 $10,000,000 UNCSA Old Library Renovation $7,350,000 $7,350,000 UNCW DeLoach Hall Renovation $15,000,000 $15,000,000 WCU Energy Production Facility $30,000,000 $30,000,000 WSSU Restore the Core Ph II - Hauser Hall for Music $12,000,000 $12,000,000
Total Value of Targeted Capital Renewal Projects:
251,314,507
Capital Planning Process
FY 2015-17
Targeted Capital Renewal Projects
2015-16 2016-17 2017-18 2018-19 2019-20 2020-21 Institution Value $40,340,000 $40,616,373 $41,279,000 $39,654,000 $42,827,574 $46,597,560 ASU Sanford Hall - Comprehensive Renovation & Modernization $19,616,000 $19,616,000 ECU Brewster Building B-C-D Classroom Wings Renovations $14,700,000 $14,700,000 ECU Whichard Building Comprehensive Renovation $6,100,000 $6,100,000 ECSU Moore Hall-Complete Building Renovation $8,510,000 $8,510,000 ECSU GR Little Library-Complete Building Renovation $4,500,000 $4,500,000 FSU Lyons Science Building-Comprehensive Renovation $10,616,373 $10,616,373 NCAT Carver Hall Renovation $8,597,560 $8,597,560 NCCU Taylor Education Building-Comprehensive Renovation $7,500,000 $7,500,000 NCCU Fine Arts Building-Comprehensive Renovation $8,454,000 $8,454,000 NCSSM Renovations to Academic Buildings $5,129,000 $5,129,000 NCSU Thermal Utilities and Infrastructure Upgrades $6,980,000 $6,980,000 NCSU Bureau of Mines Building Renovation $6,000,000 $6,000,000 NCSU Ricks Hall Renovation $8,500,000 $8,500,000 UNCA Renovation and Addition to Owen Hall $15,150,000 $15,150,000 UNCCH Hamilton Hall Envelope Restoration $18,000,000 $18,000,000 UNCC Academic Complex Modernization $8,611,574 $8,611,574 UNCG Jackson Library Renovation $20,000,000 $20,000,000 UNCP West Hall - Comprehensive Rehabilitation $10,000,000 $10,000,000 UNCSA Old Library Renovation $7,350,000 $7,350,000 UNCW DeLoach Hall Renovation $15,000,000 $15,000,000 WCU Energy Production Facility $30,000,000 $30,000,000 WSSU Restore the Core Ph II - Hauser Hall for Music $12,000,000 $12,000,000
Total Value of Targeted Capital Renewal Projects:
251,314,507
Capital Planning Process
FY 2015-17
Capital Planning Process
FY 2015-17
Capital Planning Process
FY 2015-17
Capital Planning Process
FY 2015-17
Capital Improvement Projects Over $500K
Capital Planning Process
FY 2015-17
Repair and Renovation Allocation FY 2015-16
Joint Legislative Committee on Capital Improvements
January 13, 2016
Capital Planning Process
FY 2015-17
Capital Planning Process
FY 2015-17
Capital Planning Process
FY 2015-17
Capital Planning Process
FY 2015-17
Capital Planning Process
FY 2015-17
Capital Planning Process
FY 2015-17
Capital Planning Process
FY 2015-17 Funds for Repairs and Renovations projects are appropriated by the General Assembly to the Board of Governors for allocation to the institutions. This appropriation is included in the 2015 Appropriations Act (House Bill 97 - S.L. 2015-241). By statute, the Board is directed to allocate such funds in accordance with guidelines developed in the UNC Funding Allocation Model for Repairs and Renovations and in accordance with any specifications in the Appropriations Act. Further, the 2015 Appropriations Act (House Bill 97 - S.L. 2015-241) Section 31.5.(d) requires “In making campus allocations of funds allocated to the Board
the Board of Governors shall negatively weight the availability of non-State resources and carryforward funds available for repair and renovations and shall include information about the manner in which this subsection was complied with in any report submitted pursuant to G.S. 143C-4-3(d).”.
Capital Planning Process
FY 2015-17
METHODOLOGY A Baseline is R & R Allocation Model Required by Statute B GSF Analysis of Each Institution
C Total Receipts Analysis of Each Institution
Capital Planning Process
FY 2015-17
METHODOLOGY D Established 4 Tier-Levels for Institutions
E Developed Re-Allocation Models with Tier Levels
F Developed 4% Re-Allocation Model Based on A thru E Analysis G 2015-16 Allocations – Reserve for Repair and Renovation
Capital Planning Process
FY 2015-17
INSTITUTION $ Allocation ASU 2,311,700 ECU 4,826,500 ECSU 1,410,300 FSU 1,410,300 NCA&T 2,015,300 NCCU 1,502,500 NCSSM 1,410,300 NCSU 8,013,500 UNCA 1,410,300 UNC-CH 8,766,500 UNCC 3,453,900 UNCG 3,292,800 UNCP 1,410,300 UNCW 2,119,200 UNCSA 1,410,300 WCU 1,826,000 WSSU 1,410,300 Reserve for Affiliated Institutions and Contingencies (Historically 4%) 2,000,000 Total 50,000,000
UNC 2015 Repairs & Renovations Allocation
Capital Planning Process
FY 2015-17
Institution Renewal Project
Enrollment (Fall-2014)
ECSU Moore Hall-Complete Building Renovation $8,510,000 $8,500,000 ECSU GR Little Library-Complete Building Renovation $4,500,000 $4,500,000
$13,010,000 $13,000,000 1,767
UNCA Owen Hall Renovation $15,150,000 $21,100,000
$15,150,000 $21,100,000 3,496
UNCSA Old Library Renovation $7,350,000 $8,000,000 UNCSA Performance Place Renovation $2,130,000 $2,900,000
$9,480,000 $10,900,000 1,219 $37,640,000 Total: $45,000,000 Total:
Allocation Request
TARGETED CAPITAL RENEWAL PROJECTS
( $45 Million Available )