WECC Reliability Coordinators WECC Reliability Coordination - - PowerPoint PPT Presentation

wecc reliability coordinators
SMART_READER_LITE
LIVE PREVIEW

WECC Reliability Coordinators WECC Reliability Coordination - - PowerPoint PPT Presentation

WECC Reliability Coordinators WECC Reliability Coordination Familiarization Glossary of Terms WECC Western Electricity Coordinating Council Formed 14 August 1967 WECC continues to be responsible for coordinating and promoting electric


slide-1
SLIDE 1

WECC Reliability Coordination Familiarization

WECC Reliability Coordinators

slide-2
SLIDE 2

Glossary of Terms

WECC – Western Electricity Coordinating Council Formed 14 August 1967 WECC continues to be responsible for coordinating and promoting electric system reliability. NERC - Since 1968, the North American Electric Reliability Corporation (NERC) has been committed to ensuring the reliability of the bulk power system in North America. FERC – Federal Energy Regulatory Commission EHV – Extra High Voltage ≥ 345 kV

slide-3
SLIDE 3
  • Extreme COLD weather
  • I nadequate Energy Resources
  • I nsufficient Fuel (Deliveries hampered)

January 1994 Eastern I nterconnection experienced significant power outages (including WASHI NGTON DC…) After-the-Fact investigations revealed:

  • There were resources available in the Midwest, but…
  • Frequency was low, but…

Not everybody knew Why!

I NADEQUATE COMMUNI CATI ON!

1994 - NERC Blue Ribbon Task Force commissioned, which recommended creation of the NERC Security Process Task Force (SPTF).

RELIABILITY COORDINATION

1996 – NERC SPTF Recommended Creating Regional Reliability Plan for EACH region in NERC!

slide-4
SLIDE 4

RELIABILITY COORDINATION

Eastern Interconnection Western Interconnection ERCOT

slide-5
SLIDE 5

8 NERC Reliability Entities

slide-6
SLIDE 6

“WECC”

Largest of the 8 NERC Regions

(1.8 million square miles)

14 Western states, 2 Canadian provinces, 1 Mexican state (Portion) 153 member systems 33 Control Areas 71 million people

  • Peak Demand

(S) 125,040 MW (W) 114,680 MW

  • Generation

169,208 MW

  • Transmission

115,743 Circuit Miles

Stats based on 2001 data

slide-7
SLIDE 7

35 Balancing Authorities (BAs)

slide-8
SLIDE 8

1996 – WECC experiences I nterconnection break up!

(July 2 and August 10)

RELIABILITY COORDINATION

slide-9
SLIDE 9

January 1997 WECC Security Process Task Force published the Regional Reliability Plan.

CMRC (CI SO) PNSC (BPA) RDRC (WACM)

RELIABILITY COORDINATION

  • Implementation of the WECC EHV Data Pool
  • Approved by WECC BOT December 1997, and implemented
  • n January 1, 1998.
  • Created Regional Reliability Coordinators in each of the three

(3) WECC Sub regions

Rocky Mtn. (WAPA) Desert SW (APS) MAY 1999 COMBI NED Rocky Mtn. (WAPA) Desert SW (APS)

I NDEPENDENCE The Reliability Coordinator Serves the interest of the Interconnection. Acts in the interests of the overall Interconnection before any other entity (Control Area, etc.).

slide-10
SLIDE 10

Three (3) Sub-Regions

Pacific Northwest (PNSC) California/Mexico (CMRC) Rocky Mountain/Desert Southwest (RDRC)

CMRC

RELIABILITY COORDINATOR AREAS

RDRC PNSC

38% 26% 36% LOAD 33% 22% 45% GENERATION 23% 23% 54% TRANSMISSION

(Circuit Miles)

RELIABILITY COORDINATION

slide-11
SLIDE 11
slide-12
SLIDE 12
  • FREQUENCY

– Reliable Sources – Key Points in the System

Voltage Generation Frequency

WECC EHV Data Pool

  • VOLTAGE

– 500 kV – 345 kV – 230 kV

  • GENERATION

– > 200 MW

Voltage Frequency Generation

slide-13
SLIDE 13

FIGURE 2

EXISTING WSCC KEY TRANSMISSION LINES & PATHS

(See WSCC-Wide Key Facility List-Transmission for path description.)

345 KV

500 KV

KEY TRANSFER PATHS

  • SCHEDULES

WECC EHV Data Pool

  • LIMITS
  • ACTUALS
slide-14
SLIDE 14

Responsibilities (NERC Policy 9; Appendix 9B)

  • Planning for next-day operations, including reliability analyses and

identifying special operating procedures that might be needed.

  • Analyzing current day operating conditions,
  • Adequate Resources (RESERVES)
  • I mplementing I NTERCONNECTI ON-wide relief procedure

(TLR- Eastern & USF-WECC), or local procedures to mitigate overloads

  • n the transmission system.
  • Notification.

Interconnection facility status, “Energy Emergency Alert Levels.”

  • Provide Coordination & Direction during restoration efforts

impacting the I nterconnection.

RELIABILITY COORDINATION

Authority to provide emergency assistance.

  • Each RELIABILITY COORDINATOR must have the authority to take or

direct whatever action is needed to mitigate an energy emergency within their Reliability Area. I NDEPENDENCE - STANDARDS OF CONDUCT – CONFI DENTI ALI TY The Reliability Coordinator Serves the interest of Reliability Area and Interconnection. Must act in the interests of the reliability of the overall Reliability Area / Interconnection before any other entity (Control Area, Purchasing-Selling Entity, etc.).

slide-15
SLIDE 15
  • WECC EHV Data Pool –10 to 60 second refresh rate
  • EMS / SCADA Systems –10 second scan rate
  • WAMS –Wide Area Monitoring System / Phasor

Measurement System 0.05 second scan rate

  • PI Displays & Data Historian (65,000 ICCP)
  • State Estimator Model (1Min)
  • Contingency Analysis (5 Min)
  • Voltage Stability / VAR Management
  • Real Time Dynamic Stability Analysis

Tools to Monitor the WECC System

slide-16
SLIDE 16

RELIABILITY COORDINATION

Electric System Security Data

  • Transmission data.
  • Status
  • MW or ampere loadings
  • MVA capability
  • Transformer tap and phase angle settings
  • Key voltages
  • Generator data.
  • Status
  • MW and MVAR capability
  • MW and MVAR net output
  • Status of automatic voltage control facilities
  • Operating reserve
  • CONTROL AREA Demand
  • Interchange (Scheduled and Actual)
  • Area Control Error (ACE) and Frequency

Operational I nformation

slide-17
SLIDE 17
slide-18
SLIDE 18

Frequency Disturbances and Excursions

  • 1.782
slide-19
SLIDE 19

System Voltage

WECC EHV SYSTEM VOLTAGES

Regional Perspective

slide-20
SLIDE 20

Big Picture Perspective Operating Reserves Key Transfer paths

slide-21
SLIDE 21

Conclusion

RELIABILITY COORDINATION

What do Reliability Coordinators do?

Monitor & Analyze:

  • Reliability “Health of the system”
  • Established NERC & WECC

Criteria (Rules)

  • Evaluate
  • Predict
  • and COMMUNICATE.
slide-22
SLIDE 22

Questions

RELIABILITY COORDINATION