WECC Reliability Coordination Familiarization
WECC Reliability Coordinators WECC Reliability Coordination - - PowerPoint PPT Presentation
WECC Reliability Coordinators WECC Reliability Coordination - - PowerPoint PPT Presentation
WECC Reliability Coordinators WECC Reliability Coordination Familiarization Glossary of Terms WECC Western Electricity Coordinating Council Formed 14 August 1967 WECC continues to be responsible for coordinating and promoting electric
Glossary of Terms
WECC – Western Electricity Coordinating Council Formed 14 August 1967 WECC continues to be responsible for coordinating and promoting electric system reliability. NERC - Since 1968, the North American Electric Reliability Corporation (NERC) has been committed to ensuring the reliability of the bulk power system in North America. FERC – Federal Energy Regulatory Commission EHV – Extra High Voltage ≥ 345 kV
- Extreme COLD weather
- I nadequate Energy Resources
- I nsufficient Fuel (Deliveries hampered)
January 1994 Eastern I nterconnection experienced significant power outages (including WASHI NGTON DC…) After-the-Fact investigations revealed:
- There were resources available in the Midwest, but…
- Frequency was low, but…
Not everybody knew Why!
I NADEQUATE COMMUNI CATI ON!
1994 - NERC Blue Ribbon Task Force commissioned, which recommended creation of the NERC Security Process Task Force (SPTF).
RELIABILITY COORDINATION
1996 – NERC SPTF Recommended Creating Regional Reliability Plan for EACH region in NERC!
RELIABILITY COORDINATION
Eastern Interconnection Western Interconnection ERCOT
8 NERC Reliability Entities
“WECC”
Largest of the 8 NERC Regions
(1.8 million square miles)
14 Western states, 2 Canadian provinces, 1 Mexican state (Portion) 153 member systems 33 Control Areas 71 million people
- Peak Demand
(S) 125,040 MW (W) 114,680 MW
- Generation
169,208 MW
- Transmission
115,743 Circuit Miles
Stats based on 2001 data
35 Balancing Authorities (BAs)
1996 – WECC experiences I nterconnection break up!
(July 2 and August 10)
RELIABILITY COORDINATION
January 1997 WECC Security Process Task Force published the Regional Reliability Plan.
CMRC (CI SO) PNSC (BPA) RDRC (WACM)
RELIABILITY COORDINATION
- Implementation of the WECC EHV Data Pool
- Approved by WECC BOT December 1997, and implemented
- n January 1, 1998.
- Created Regional Reliability Coordinators in each of the three
(3) WECC Sub regions
Rocky Mtn. (WAPA) Desert SW (APS) MAY 1999 COMBI NED Rocky Mtn. (WAPA) Desert SW (APS)
I NDEPENDENCE The Reliability Coordinator Serves the interest of the Interconnection. Acts in the interests of the overall Interconnection before any other entity (Control Area, etc.).
Three (3) Sub-Regions
Pacific Northwest (PNSC) California/Mexico (CMRC) Rocky Mountain/Desert Southwest (RDRC)
CMRC
RELIABILITY COORDINATOR AREAS
RDRC PNSC
38% 26% 36% LOAD 33% 22% 45% GENERATION 23% 23% 54% TRANSMISSION
(Circuit Miles)
RELIABILITY COORDINATION
- FREQUENCY
– Reliable Sources – Key Points in the System
Voltage Generation Frequency
WECC EHV Data Pool
- VOLTAGE
– 500 kV – 345 kV – 230 kV
- GENERATION
– > 200 MW
Voltage Frequency Generation
FIGURE 2
EXISTING WSCC KEY TRANSMISSION LINES & PATHS
(See WSCC-Wide Key Facility List-Transmission for path description.)345 KV
500 KV
KEY TRANSFER PATHS
- SCHEDULES
WECC EHV Data Pool
- LIMITS
- ACTUALS
Responsibilities (NERC Policy 9; Appendix 9B)
- Planning for next-day operations, including reliability analyses and
identifying special operating procedures that might be needed.
- Analyzing current day operating conditions,
- Adequate Resources (RESERVES)
- I mplementing I NTERCONNECTI ON-wide relief procedure
(TLR- Eastern & USF-WECC), or local procedures to mitigate overloads
- n the transmission system.
- Notification.
Interconnection facility status, “Energy Emergency Alert Levels.”
- Provide Coordination & Direction during restoration efforts
impacting the I nterconnection.
RELIABILITY COORDINATION
Authority to provide emergency assistance.
- Each RELIABILITY COORDINATOR must have the authority to take or
direct whatever action is needed to mitigate an energy emergency within their Reliability Area. I NDEPENDENCE - STANDARDS OF CONDUCT – CONFI DENTI ALI TY The Reliability Coordinator Serves the interest of Reliability Area and Interconnection. Must act in the interests of the reliability of the overall Reliability Area / Interconnection before any other entity (Control Area, Purchasing-Selling Entity, etc.).
- WECC EHV Data Pool –10 to 60 second refresh rate
- EMS / SCADA Systems –10 second scan rate
- WAMS –Wide Area Monitoring System / Phasor
Measurement System 0.05 second scan rate
- PI Displays & Data Historian (65,000 ICCP)
- State Estimator Model (1Min)
- Contingency Analysis (5 Min)
- Voltage Stability / VAR Management
- Real Time Dynamic Stability Analysis
Tools to Monitor the WECC System
RELIABILITY COORDINATION
Electric System Security Data
- Transmission data.
- Status
- MW or ampere loadings
- MVA capability
- Transformer tap and phase angle settings
- Key voltages
- Generator data.
- Status
- MW and MVAR capability
- MW and MVAR net output
- Status of automatic voltage control facilities
- Operating reserve
- CONTROL AREA Demand
- Interchange (Scheduled and Actual)
- Area Control Error (ACE) and Frequency
Operational I nformation
Frequency Disturbances and Excursions
- 1.782
System Voltage
WECC EHV SYSTEM VOLTAGES
Regional Perspective
Big Picture Perspective Operating Reserves Key Transfer paths
Conclusion
RELIABILITY COORDINATION
What do Reliability Coordinators do?
Monitor & Analyze:
- Reliability “Health of the system”
- Established NERC & WECC
Criteria (Rules)
- Evaluate
- Predict
- and COMMUNICATE.