Water & Environment Unit Design Safety Initiative Update and Designing for Safe Maintenance Safety Stand Down, November 2010
Aims of Presentation WNE Design Safety Initiative: An update on progress: Guidance and information that has been generated as a result of the initiative to date. Designing for safe operation and maintenance using examples from: - Yorkshire Water - Anglian Water
Unit Design Safety Initiative Update
Unit Design Safety Initiative 2010 Progress to Date Reviewing effectiveness of design hazard elimination actions; Producing guidance on achieving best practice; Best practice examples and RAG list posted in BPTL on PIMs; Link to this on Unit Safety home page Health and Safety Design Leadership workshop.
Unit Design Safety Initiative 2010 Planned Action to end of year Project Safety Advisors (PSA) to review effectiveness of current designs in mitigating risks; Implement suggestions from Design Leadership workshop; WUD design processes to be reviewed to integrate safety interventions; More best practice examples to be included in BPTL safety folder; Review standard forms to include more prompts.
Unit Design Safety Initiative 2011 Objective Be better at identifying, managing and communicating risks
Unit Design Safety Initiative 2011 Actions PSAs to be more involved and carry out spot checks of design decision forms; Include all designers of all disciplines and stakeholders in design health and safety process; Revise our design processes to include health and safety best practice; Obtain and implement feedback from contractors/operators; Continuous improvement of safety best practice library.
Operation and Maintenance Designing for Safe
Design for Safe Maintenance and Operation How to achieve this? Involve operators during the design and hazard elimination processes; Use 3D model to undertake virtual walk through the works with operators; Think from an operator’s perspective while designing; Walk around with operators at end of job to identify good and bad practice and capture lessons learned in BPTL; Incorporate lessons learnt into future designs.
Keldgate WTW A designer’ ’s approach to mitigating s approach to mitigating A designer operation and maintenance risk operation and maintenance risk
Keldgate WTW
Keldgate WTW Communication: Delivery Process Design & commissioning delivery process specifically developed; Design and commissioning review meetings undertaken with Client every two weeks; Dedicated safety meetings integral part of delivery process: 2 nr. HAZOPs – HAZCON (construction) – HAZ-maintenance (lifting & access) – HAZCOM (commissioning) – Safety meetings undertaken using a HAZOP facilitator; Safety meetings conducted with Client’s operational staff.
Keldgate WTW Co-ordination 3D model of building, plant and instrumentation produced Operation of plant reviewed with Client’s staff Maintenance (access & lifting) of plant reviewed with Client Lighting Plan produced and evaluated Fire/Emergency escape plan reviewed by Building Inspector Access road evaluated using Autotrack
Keldgate WTW 3D Model
Keldgate WTW Hazard Elimination/Operational Lighting designed to avoid shadows Valves positioned to ensure easy access and operation Plant operation fully automated Instruments and display monitors positioned at eye level Access platforms provided for higher equipment MCC Room has climate control to provide comfortable temperature Access to bund (confined space) eliminated
Keldgate WTW Hazard Elimination/Maintenance Lifting beams installed for heavy equipment Building floor has no steps to allow trolley access Access to every item of plant provided Lights positioned to allow them to be accessed by mobile platform Valves located at level to facilitate access Serviceable items in bunds and buried tanks located at surface
Keldgate WTW Instruments and Valves
Keldgate WTW Confined Space
Kings Lynn H&S Review with Operations
Kings Lynn H&S Review with Operations Some Lessons Learnt Poly electrolyte is extremely slippery when wet so design to avoid ponding on slabs;
Kings Lynn H&S Review with Operations Some Lessons Learnt Position valves for ease of operation
Kings Lynn H&S Review with Operations Some Lessons Learnt WESSO valve at the top of Monsal units produces toxic gasses, so do not provide permanent access to the valves
Kings Lynn H&S Review with Operations Some Lessons Learnt Avoid steep sloping access roofs – KL Digesters 25 o slope
Challenge What will you do differently in your designs to contribute to safe maintenance?
Committed to Safety www.mottmac.com
AutoTrack/Truck Delivery AutoTrack models the swept paths of steered vehicles, including articulated trucks in loading areas and junctions ; Can control a second steered axle at drive time using the mouse wheel ; Any number of camera viewpoints (including drivers eye views) and switch between them during animation playback ; Display full width tyre tracks .
Recommend
More recommend