Water & Environment Unit Design Safety Initiative Update and - - PowerPoint PPT Presentation

water environment unit design safety initiative update
SMART_READER_LITE
LIVE PREVIEW

Water & Environment Unit Design Safety Initiative Update and - - PowerPoint PPT Presentation

Water & Environment Unit Design Safety Initiative Update and Designing for Safe Maintenance Safety Stand Down, November 2010 Aims of Presentation WNE Design Safety Initiative: An update on progress: Guidance and information that has


slide-1
SLIDE 1

Water & Environment Unit Design Safety Initiative Update and Designing for Safe Maintenance

Safety Stand Down, November 2010

slide-2
SLIDE 2

Aims of Presentation

WNE Design Safety Initiative:  An update on progress: Guidance and information that has been generated as a result of the initiative to date.  Designing for safe operation and maintenance using examples from:

  • Yorkshire Water
  • Anglian Water
slide-3
SLIDE 3

Unit Design Safety Initiative Update

slide-4
SLIDE 4

Unit Design Safety Initiative 2010

Progress to Date

Reviewing effectiveness of design hazard elimination actions;

Producing guidance on achieving best practice;

Best practice examples and RAG list posted in BPTL on PIMs;

Link to this on Unit Safety home page

Health and Safety Design Leadership workshop.

slide-5
SLIDE 5

Planned Action to end of year

Project Safety Advisors (PSA) to review effectiveness of current designs in mitigating risks;

Implement suggestions from Design Leadership workshop;

WUD design processes to be reviewed to integrate safety interventions;

More best practice examples to be included in BPTL safety folder;

Review standard forms to include more prompts.

Unit Design Safety Initiative 2010

slide-6
SLIDE 6

Objective Be better at identifying, managing and communicating risks

Unit Design Safety Initiative 2011

slide-7
SLIDE 7

Actions

PSAs to be more involved and carry out spot checks of design decision forms;

Include all designers of all disciplines and stakeholders in design health and safety process;

Revise our design processes to include health and safety best practice;

Obtain and implement feedback from contractors/operators;

Continuous improvement of safety best practice library.

Unit Design Safety Initiative 2011

slide-8
SLIDE 8

Designing for Safe Operation and Maintenance

slide-9
SLIDE 9

How to achieve this?

Involve operators during the design and hazard elimination processes;

Use 3D model to undertake virtual walk through the works with operators;

Think from an operator’s perspective while designing;

Walk around with operators at end of job to identify good and bad practice and capture lessons learned in BPTL;

Incorporate lessons learnt into future designs.

Design for Safe Maintenance and Operation

slide-10
SLIDE 10

Keldgate WTW

A designer A designer’ ’s approach to mitigating s approach to mitigating

  • peration and maintenance risk
  • peration and maintenance risk
slide-11
SLIDE 11

Keldgate WTW

slide-12
SLIDE 12

Keldgate WTW Communication: Delivery Process

Design & commissioning delivery process specifically developed;

Design and commissioning review meetings undertaken with Client every two weeks;

Dedicated safety meetings integral part of delivery process:

2 nr. HAZOPs

HAZCON (construction)

HAZ-maintenance (lifting & access)

HAZCOM (commissioning)

Safety meetings undertaken using a HAZOP facilitator;

Safety meetings conducted with Client’s operational staff.

slide-13
SLIDE 13

3D model of building, plant and instrumentation produced

Operation of plant reviewed with Client’s staff

Maintenance (access & lifting) of plant reviewed with Client

Lighting Plan produced and evaluated

Fire/Emergency escape plan reviewed by Building Inspector

Access road evaluated using Autotrack

Keldgate WTW Co-ordination

slide-14
SLIDE 14

Keldgate WTW 3D Model

slide-15
SLIDE 15

Keldgate WTW Hazard Elimination/Operational

Lighting designed to avoid shadows

Valves positioned to ensure easy access and operation

Plant operation fully automated

Instruments and display monitors positioned at eye level

Access platforms provided for higher equipment

MCC Room has climate control to provide comfortable temperature

Access to bund (confined space) eliminated

slide-16
SLIDE 16

Keldgate WTW Hazard Elimination/Maintenance

Lifting beams installed for heavy equipment

Building floor has no steps to allow trolley access

Access to every item of plant provided

Lights positioned to allow them to be accessed by mobile platform

Valves located at level to facilitate access

Serviceable items in bunds and buried tanks located at surface

slide-17
SLIDE 17

Keldgate WTW Instruments and Valves

slide-18
SLIDE 18

Keldgate WTW Confined Space

slide-19
SLIDE 19

Kings Lynn H&S Review with Operations

slide-20
SLIDE 20

Poly electrolyte is extremely slippery when wet so design to avoid ponding on slabs;

Kings Lynn H&S Review with Operations Some Lessons Learnt

slide-21
SLIDE 21

Position valves for ease of operation

Kings Lynn H&S Review with Operations Some Lessons Learnt

slide-22
SLIDE 22

WESSO valve at the top of Monsal units produces toxic gasses, so do not provide permanent access to the valves

Kings Lynn H&S Review with Operations Some Lessons Learnt

slide-23
SLIDE 23

Avoid steep sloping access roofs – KL Digesters 25o slope

Kings Lynn H&S Review with Operations Some Lessons Learnt

slide-24
SLIDE 24

Challenge

What will you do differently in your designs to contribute to safe maintenance?

slide-25
SLIDE 25

www.mottmac.com

Committed to Safety

slide-26
SLIDE 26

AutoTrack/Truck Delivery

AutoTrack models the swept paths of steered vehicles, including articulated trucks in loading areas and junctions;

Can control a second steered axle at drive time using the mouse wheel;

Any number of camera viewpoints (including drivers eye views) and switch between them during animation playback;

Display full width tyre tracks.