washington boulevard trail p phase 2
play

Washington Boulevard Trail (P (Phase 2) DES Transportation Phase 1 - PowerPoint PPT Presentation

Washington Boulevard Trail (P (Phase 2) DES Transportation Phase 1 Arlington Blvd. . to Walter Reed Dr. Phase 2 Connects for Bikeway System and Community Access North-South trail linkage; Connects with Arlington Blvd Trail &


  1. Washington Boulevard Trail (P (Phase 2) DES Transportation

  2. Phase 1 – Arlington Blvd. . to Walter Reed Dr.

  3. Phase 2 – Connects for Bikeway System and Community Access • North-South trail linkage; Connects with Arlington Blvd Trail & Columbia Pike route • Enhances community access to Towers Park for much of Penrose • 6th Street bicycle and pedestrian connection • Provides new access and use for Washington Blvd. corridor

  4. Recent Redesign • Thi hird & Fin inal redesign for project • North end of trail (Walter Reed to 6 th St.) now has curb and gutter rather than a wide paved shoulder • Trail is shifted into area where shoulder had been • Reduced impacts upon hillside and vegetation (trees) between roadway and residences • Less wall and barrier construction, reduced new pavement area Arlington Blvd Trail east of Courthouse Road- Curb and gutter without paved shoulder

  5. Existing, g, Prior & New Trail Section Designs Existing: • 11’ wide asphalt shoulder with gutter • 1.5’ wide guard rail Prior: • 10’ wide asphalt shoulder • 1.5’ wide concrete barrier & 2’ paved buffer • 10’ asphalt trail New: • No shoulder (north of 6 Th Street) • 2.5’ wide curb and gutter & 5’ wide landscaped buffer • 10’ asphalt trail

  6. Cross Section – Prior & New Designs

  7. Environmental Im Impacts Reduced

  8. Change in Tree Im Impacts • Original design = 198 trees to be removed • Feb 2013 Environmental Assessment = 128 trees • Current design = 84 trees, of which 23 are either invasive species (19) or dead (4) • Largest concentration between Walter Reed Dr and Second Street bridge

  9. Landscape is Degraded and Needs Restoration • Project includes invasive plant removal (applied for 3 years) • Substantial planting of new trees (3 for every 2 removed) • Native tree and shrub plantings • Trash removal

  10. Im Implementation Steps • March & April 2016 – Public Outreach (Penrose, advisory commissions, website) • March thru June – Final VDOT & County review and permitting • July – Advertise for Bids • October – County Board awards contract to selected bidder • Late Fall 2016 thru Spring/Summer 2017 – Construction (6 to 9 months) • Replanting – Spring and Fall 2017

  11. Replanting A Areas

  12. Slopes and Replanting

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend