Washington Boulevard Trail (P (Phase 2) DES Transportation Phase 1 - - PowerPoint PPT Presentation

washington boulevard trail p phase 2
SMART_READER_LITE
LIVE PREVIEW

Washington Boulevard Trail (P (Phase 2) DES Transportation Phase 1 - - PowerPoint PPT Presentation

Washington Boulevard Trail (P (Phase 2) DES Transportation Phase 1 Arlington Blvd. . to Walter Reed Dr. Phase 2 Connects for Bikeway System and Community Access North-South trail linkage; Connects with Arlington Blvd Trail &


slide-1
SLIDE 1

Washington Boulevard Trail (P (Phase 2)

DES Transportation

slide-2
SLIDE 2

Phase 1 – Arlington Blvd. . to Walter Reed Dr.

slide-3
SLIDE 3

Phase 2 – Connects for Bikeway System and Community Access

  • North-South trail linkage;

Connects with Arlington Blvd Trail & Columbia Pike route

  • Enhances community access to

Towers Park for much of Penrose

  • 6th Street bicycle and pedestrian

connection

  • Provides new access and use for

Washington Blvd. corridor

slide-4
SLIDE 4

Recent Redesign

  • Thi

hird & Fin inal redesign for project

  • North end of trail (Walter Reed to 6th

St.) now has curb and gutter rather than a wide paved shoulder

  • Trail is shifted into area where

shoulder had been

  • Reduced impacts upon hillside and

vegetation (trees) between roadway and residences

  • Less wall and barrier construction,

reduced new pavement area

Arlington Blvd Trail east of Courthouse Road- Curb and gutter without paved shoulder

slide-5
SLIDE 5

Existing, g, Prior & New Trail Section Designs

Existing:

  • 11’ wide asphalt shoulder with gutter
  • 1.5’ wide guard rail

Prior:

  • 10’ wide asphalt shoulder
  • 1.5’ wide concrete barrier & 2’ paved buffer
  • 10’ asphalt trail

New:

  • No shoulder (north of 6Th Street)
  • 2.5’ wide curb and gutter & 5’ wide

landscaped buffer

  • 10’ asphalt trail
slide-6
SLIDE 6

Cross Section – Prior & New Designs

slide-7
SLIDE 7

Environmental Im Impacts Reduced

slide-8
SLIDE 8

Change in Tree Im Impacts

  • Original design = 198 trees to be

removed

  • Feb 2013 Environmental

Assessment = 128 trees

  • Current design = 84 trees, of

which 23 are either invasive species (19) or dead (4)

  • Largest concentration between

Walter Reed Dr and Second Street bridge

slide-9
SLIDE 9

Landscape is Degraded and Needs Restoration

  • Project includes invasive plant

removal (applied for 3 years)

  • Substantial planting of new trees

(3 for every 2 removed)

  • Native tree and shrub plantings
  • Trash removal
slide-10
SLIDE 10

Im Implementation Steps

  • March & April 2016 – Public Outreach (Penrose, advisory commissions,

website)

  • March thru June – Final VDOT & County review and permitting
  • July – Advertise for Bids
  • October – County Board awards contract to selected bidder
  • Late Fall 2016 thru Spring/Summer 2017 – Construction (6 to 9

months)

  • Replanting – Spring and Fall 2017
slide-11
SLIDE 11

Replanting A Areas

slide-12
SLIDE 12

Slopes and Replanting