Los Alamos County Walkup Aquatic Center - Kiddie Pool Addition Schematic Design Presentation AUGUST 28, 2019 Schedule Kiddie Pool Addition WORKPLAN & COMMUNICATION PROCESS Los Alamos County Walkup Aquatic Center 2019 2020 2021 June


slide-1
SLIDE 1

Walkup Aquatic Center - Kiddie Pool Addition

Schematic Design Presentation

AUGUST 28, 2019

Los Alamos County

slide-2
SLIDE 2

SCHEMATIC DESIGN DESIGN DEVELOPMENT

CONSTRUCTION DOCS/SPECS

Program Verification Budget Schedule Schematic

BIDDING/ PERMIT CONST.

Materials Budget Systems Utilities Fire Marshal Design Budget Utilities Systems

PERIODIC PROGRESS MEETINGS PROJECT CLOSEOUT

  • 100% Schematic

Design Review

  • Begin Peer Review
  • Geotech Progress
  • Survey Update
  • Estimate of Probable

Construction Cost

  • Schedule IDRC, P&Z,

ACAS submittal

  • Schedule site plan

amendment, parking waiver, plat approval

  • HVAC life cycle costs

PARTICIPANTS:

  • OWNER
  • FBT

August 5

  • 60% DD Progress
  • Los Alamos County

AHJ

  • Los Alamos County

Fire Marshal

  • Meet With County

O+M Staff

  • Pool Consultant
  • Utilities
  • Building Envelope

PARTICIPANTS:

  • OWNER
  • FBT
  • LAC FM
  • AGI

TBD

  • DD Progress
  • Public Information

Meeting

  • Review With Owner
  • HVAC Options
  • Budget/ Schedule
  • Pool Consultant

PARTICIPANTS:

  • OWNER
  • FBT
  • B+P
  • CHH2O

TBD

  • 90% DD Progress
  • Discuss Comments

From FM + AHJ

  • Building Envelope

Meeting

  • Review Layout
  • Pool Consultant
  • MEP

PARTICIPANTS:

  • OWNER
  • FBT
  • AGI

TBD

  • 100% DD

Document Submission

  • Peer/ Owner Review
  • Estimate of

Probable Cost

  • Present to Aquatics

Center Advisory Committee (ACAS)

  • Present to Parks +

Recreation Board (PRB)

  • Building Envelope

PARTICIPANTS:

  • OWNER
  • FBT
  • ACAS
  • PRB

TBD

  • 90% CD Progress
  • Public Information

Meeting

  • Finalize Building

Systems

  • Finalize Building

Envelope

  • Estimate Update

PARTICIPANTS:

  • OWNER
  • FBT

TBD

  • 60% CD Progress
  • Fire Marshal

Meeting

  • County Utility

Meeting

  • MEP Review
  • Building Envelope
  • Estimate Update

PARTICIPANTS:

  • OWNER
  • FBT
  • LAC FM

TBD

  • CD Begin
  • Finalize Finishes
  • Finalize HVAC

Systems

  • Pool Consultant
  • Site
  • Building Envelope

PARTICIPANTS:

  • OWNER
  • FBT

TBD

Bidding Construction Warranty

Kiddie Pool Addition

Los Alamos County

Walkup Aquatic Center

Schedule

WORKPLAN & COMMUNICATION PROCESS

  • Punch List
  • Review of

Operations

  • Final

Documentation (release of liens)

  • Confirm Classroom

Layouts & Furnishings

  • 12 Month Warranty

Walk

PARTICIPANTS:

  • OWNER
  • FBT
  • General Contractor

TBD

  • CD Final
  • Submit Plans/ Specs

to County

  • Public Information

Meeting

  • Page Turning Session

With Owner

  • Estimate
  • Present to Aquatics

Center Advisory Committee (ACAS)

  • Present to Parks +

Recreation Board (PRB)

PARTICIPANTS:

  • OWNER
  • FBT
  • ACAS
  • PRB

TBD

June 10

2019

August 20

2019

August 20

2019

October 29

2019

October 29

2019

February 4

2020

April 2

2020

May 4

2020

June 4

2021

DD START

7

60% DD PROGRESS

8

90% DD PROGRESS

9 10

100% DD FINAL CD START

12

60% CD PROGRESS

13

90% CD PROGRESS

14 15

100% CD FINAL 75% SD PROGRESS

3 4

100% SD FINAL PROJECT KICK-OFF

1

  • Review Program &

Building Areas

  • Budget/ Schedule
  • Discuss Overall

Milestones

  • Site Walk-Through

PARTICIPANTS:

  • OWNER
  • FBT

June 10

  • Preliminary Designs
  • Schematic Design

Progress: Site Plan, Floor Plan, Elevations

  • Survey

PARTICIPANTS:

  • OWNER
  • FBT

June 24

50% SD PROGRESS

2

  • 75% SD Progress
  • SD cost estimates
  • Code analysis
  • Survey Update
  • Geotech Progress
  • Parking Variance

(P&Z update)

  • Pool Consultant

PARTICIPANTS:

  • OWNER
  • FBT
  • CHH2O

July 15

slide-3
SLIDE 3

Los Alamos County -

Larry Walkup Aquatic Center Pool Addition Project Site Plan & Program - August 28, 2019

POOL ADDITION PROGRAM ELEMENTS

  • 2,000 SF zero-entry pool, with spray

features, lazy river, and an area for swim lessons.

  • Water slide with run-out area

separate from main pool.

  • (3) family changing rooms
  • Pool support spaces, including

mechanical, chemical storage, and electrical rooms.

  • Total project budget: $6.5 million
  • Construction is slated to begin in

May 2020 and last for a year.

slide-4
SLIDE 4

NEW SEWER LINE EXISTING SEWER LINE EXISTING MANHOLE

slide-5
SLIDE 5

NEW SEWER LINE EXISTING SEWER LINE EXISTING MANHOLE

slide-6
SLIDE 6

Los Alamos County -

Larry Walkup Aquatic Center Pool Addition Project Aquatic Features - August 28, 2019

slide-7
SLIDE 7

A

WALL BLOCKOUTS, CLOSURE PANELS, AND SEALING AROUND THE SLIDE AT WALL PENETRATIONS IS BY OTHERS (TYP) STAIR START BELOW 29'-0 5 16 " 8'-103 8" START DECK

  • EL. 119.25'

POOL DECK

  • EL. 100.00'

RUNOUT DECK

  • EL. 100.00'

19'-3"

Los Alamos County -

Larry Walkup Aquatic Center Pool Addition Project Aquatic Features - August 28, 2019

slide-8
SLIDE 8
slide-9
SLIDE 9
slide-10
SLIDE 10
slide-11
SLIDE 11

Los Alamos County -

Larry Walkup Aquatic Center Pool Addition Project Entrance Design - August 28, 2019

LOBBY VESTIBULE EXISTING FINISH NEW FINISH

NEW ENTRANCE DESIGN EXISTING ENTRANCE

VESTIBULE 118 SF LOBBY 373 SF VESTIBULE 190 SF LOBBY 415 SF

slide-12
SLIDE 12

Los Alamos County -

Larry Walkup Aquatic Center Pool Addition Project Comment Cards - August 28, 2019

Your Input is Important!

Please drop comment cards in the box or hand to staff. Comments can also be sent to lacpw@lacnm.us

slide-13
SLIDE 13

Questions / Comments?

Los Alamos County -

Larry Walkup Aquatic Center Pool Addition Project Questions / Comments - August 28, 2019