Virtual Public Hearing Vir ual Public Hearing Pre-Recorded Presentation Pre-R ecorded Presentation City of El Paso Central Business District City of El P so Central Business District Phase IV (CBD IV) Project Phase IV (CBD IV) Project CBD


slide-1
SLIDE 1

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

City of El P City of El Paso Central Business District so Central Business District Phase IV (CBD IV) Project Phase IV (CBD IV) Project

Campbell Stree Campbell Street, K , Kansas Stree nsas Street, Oregon Stree , Oregon Street, F , Father ther Rahm A Rahm Avenue, and 6 enue, and 6th

th Av

Avenue CSJ No. 092 CSJ No. 0924-06-562 4-06-562

Thur Thursda sday July 23, 2020 y July 23, 2020

Vir Virtual Public Hearing ual Public Hearing Pre-R Pre-Recorded Presentation ecorded Presentation

slide-2
SLIDE 2

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

In response to the COVID-19 outbreak, and consistent with current City and County orders, the City of El Paso will hold a virtual hearing. The virtual hearing will provide the same information as an in-person hearing, including:

  • project details
  • environmental studies
  • process for submitting comments

https://www.elpasotexas.gov/capital‐ improvement/virtual‐public‐hearing

Vir Virtual Public Hearing ual Public Hearing In R In Response t sponse to Public Health Public Health

slide-3
SLIDE 3

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Agenda

  • Purpose

Purpose of the he Public Public Hearing: Hearing: To present the proposed improvements

and to receive public feedback. The public hearing is being held as a courtesy to the public.

  • Hearing A

Hearing Agenda: enda:

  • Project Overview
  • Environmental Overview
  • Project Schedule and Phasing
  • Public Comment Process
  • Adjournment
slide-4
SLIDE 4

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by TxDOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 9, 2019, and executed by FHWA and TxDOT. La revisión ambiental, consultas y otras acciones requeridas por las leyes ambientales federales aplicables para este proyecto, están siendo o han sido realizadas por TxDOT de conformidad con la Reglamentación 23, Sección 327 del Código de Estados Unidos y un Memorando de Entendimiento con fecha del 9 de diciembre de 2019, ejecutado por la FHWA (Administración Federal de Carreteras) y TxDOT.

National En National Envir vironmental P nmental Policy A licy Act (NEP t (NEPA) A)

slide-5
SLIDE 5

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Public Hearing Notices

  • Publis

Published in ed in El P El Paso so Times Times – J – July 1 1st

st and

and 9th

th, 2020

, 2020

  • Publis

Published in ed in El P El Paso so Times Times Online Online – July uly 8th

th, 2020

, 2020

  • Publis

Published in ed in El Diari El Diario – J – July 8 8th

th, 2020

, 2020

  • Mailed no

Mailed noti tices t ces to elect elected of d offi ficials and als and adjacent p property ow

  • wners –

– July 6 6th

th, 2020

, 2020

  • Fly

Flyers rs post posted at tw ed at two Sun

  • Sun Metr

Metro bus st

  • bus stop
  • ps –

– July 9 July 9th

th, 2020

, 2020

  • City o

ty of El El Paso Paso C Consta

  • nstant

nt Contact Email blast Contact Email blast to member members of the public – s of the public – July 8 y 8th

th, 2020

, 2020

  • Social media post

Social media posts – – July 8 uly 8th

th, 2020

, 2020

slide-6
SLIDE 6

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

How to Submit Your Verbal Comments

Verbal T rbal Testimon stimony

Call (915) 201-0811 and leave your comment, starting on Thur Thursda sday July July 23, 2020 23, 2020 at at 5 p.m 5 p.m. until Frida iday, A , August 7, gust 7, 2020 2020 at at 5 p.m. 5 p.m. Please keep comments to 3 minutes for standard Public Hearing allotted time for verbal comments.

slide-7
SLIDE 7

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

How to Submit Your Written Comments

Comment forms are available for download on the public hearing website and can submitted via:

  • 1. Email: jgardner@blantonassociates.com

Attn: CBD IV

  • 2. Mail: Blanton & Associates

Attn: CBD IV 5 Lakeway Centre Court, Suite 200 Austin, TX 78734

slide-8
SLIDE 8

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Downtown El Paso Downtown El Paso

Roadway Improvements Landscape Improvements

Project Location

One‐Way to Two‐way Conversion

slide-9
SLIDE 9

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Project Description

The approximately 1.8-mile-long project would consist of roadway reconstruction and parkway improvements, including:

  • Sidewalks
  • Storm sewers and curbs and gutters
  • ADA improvements
  • Bicycle improvements
  • Driveways
  • Traffic Signals
  • Lighting, signing, and striping
  • Landscaping and irrigation

Improvements on Campbell Street from Paisano Drive to 8th Avenue and Kansas Street from Father Rahm Avenue to 8th Avenue would also include reconfiguring from three,

  • ne-way travel lanes to two, two-way travel lanes.

All work would be conducted within existing City of El Paso Right-of-Way (ROW)

slide-10
SLIDE 10

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Existing Typical Section Campbell Street (Paisano Dr. to Loop 375)

Existing Cross Section

slide-11
SLIDE 11

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Proposed Typical Section Campbell Street (Paisano Dr. to Loop 375)

Proposed Cross Section

NOTE: This rendering is an artistic interpretation of the design. It is not meant to be an exact rendition of the final product.

slide-12
SLIDE 12

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Existing Typical Section Kansas Street (Father Rahm Ave. to Loop 375)

Existing Cross Section

slide-13
SLIDE 13

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Proposed Typical Section Kansas Street (Father Rahm Ave. to Loop 375)

Proposed Cross Section

NOTE: This rendering is an artistic interpretation of the design. It is not meant to be an exact rendition of the final product.

slide-14
SLIDE 14

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Existing Typical Section Oregon Street (Paisano Dr. to Sixth Ave.)

Existing Cross Section

slide-15
SLIDE 15

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Proposed Typical Section Oregon Street (Paisano Dr. to Sixth Ave.)

Proposed Cross Section

NOTE: This rendering is an artistic interpretation of the design. It is not meant to be an exact rendition of the final product.

slide-16
SLIDE 16

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Existing Typical Section Father Rahm Avenue (Kansas St. to Campbell St.)

Existing Cross Section

slide-17
SLIDE 17

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Proposed Typical Section Father Rahm Avenue (Kansas St. to Campbell St.)

Proposed Cross Section

NOTE: This rendering is an artistic interpretation of the design. It is not meant to be an exact rendition of the final product.

slide-18
SLIDE 18

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Existing Cross Section

Existing Typical Section 6th Avenue (El Paso St. to Campbell St.)

slide-19
SLIDE 19

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Proposed Cross Section

Proposed Typical Section 6th Avenue (El Paso St. to Campbell St.)

NOTE: This rendering is an artistic interpretation of the design. It is not meant to be an exact rendition of the final product.

slide-20
SLIDE 20

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Project Planning and Funding

  • Total estimated construction cost:

approximately $14.4 million

  • Funding source: Federal, state, and local

funds

  • Local funding = certificates of obligation
slide-21
SLIDE 21

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Environmental Overview

  • The project was processed as a categorical exclusion (CE)
  • Technical reports evaluated impacts to the human and

natural environment

  • Project would not result in impacts to threatened or

endangered species, water resources, historic resources, archeological resources, community features, hazardous materials, air quality, or traffic noise

  • Access would be maintained to adjacent businesses

throughout the project area during construction

slide-22
SLIDE 22

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Schedule

  • Project letting: Fall 2020
  • Begin project construction: Spring 2021
  • Project completed: Fall 2022
slide-23
SLIDE 23

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Construction Phases

slide-24
SLIDE 24

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

How to Submit Your Verbal Comments

Verbal T rbal Testimon stimony

Call (915) 201-0811 and leave your comment, starting on Thur Thursda sday July July 23, 2020 23, 2020 at at 5 p.m 5 p.m. until Frida iday A August 7, gust 7, 2020 2020 at at 5 p.m. 5 p.m. Please keep comments to 3 minutes for standard Public Hearing allotted time for verbal comments.

slide-25
SLIDE 25

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

How to Submit Your Written Comments

Comment forms are available for download on the public hearing website and can submitted via:

  • 1. Email: jgardner@blantonassociates.com

Attn: CBD IV

  • 2. Mail: Blanton & Associates

Attn: CBD IV 5 Lakeway Centre Court, Suite 200 Austin, TX 78734

slide-26
SLIDE 26

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

Stay Informed and Stay in Touch

  • Review the project materials on the City of El Paso Website
  • Contact Ismael Cepeda, Project Manager, at (915) 212‐1809 or by

email at cepedaji@elpasotexas.gov with questions about the project

  • Check back to the City’s Website in a month or two to review the

Public Hearing Summary and response to public comments

slide-27
SLIDE 27

“Delivering Outstanding Services”

CBD IV CSJ: 0924‐06‐562 Campbell Street, Kansas Street, Oregon Street, Father Rahm Avenue, and 6th Avenue

THANK YOU!

Thank y Thank you f u for w r watching! tching! Please don’t forget to submit comments by Friday August 7, 2020