5/15/17 Final Vanderbilt Drive Beautification MSTU FPL Utility Burial Project Vanderbilt Drive/Cul-de-sacs Public Utility Renewal Project (Water/Wastewater/Stormwater)
May 15, 2017
Vanderbilt Drive/Cul-de-sacs Vanderbilt Drive Public Utility - - PDF document
Vanderbilt Drive/Cul-de-sacs Vanderbilt Drive Public Utility Renewal Project Beautification MSTU FPL (Water/Wastewater/Stormwater) Utility Burial Project 5/15/17 Final May 15, 2017 2 1 4 5 6 3 7 Project Area Water Sewer / FM / PS*
5/15/17 Final Vanderbilt Drive Beautification MSTU FPL Utility Burial Project Vanderbilt Drive/Cul-de-sacs Public Utility Renewal Project (Water/Wastewater/Stormwater)
May 15, 2017
Project Area Water % Sewer / FM / PS* % Stormwater % Restoration 1st Lift Asphalt MSTU Energizing Flamingo Ave. 100 100 / 100 / 95 50 Mid-June to Mid-July 2017 May 2017 June thru August 2018 Heron Ave. 100 100 / 100 / 95 95 May to Mid-June 2017 May 2017 Egret Ave. 100 75 / 0 / 0 July to Mid- August 2017 July 2017 Conners Ave. 100 Moved to Phase 5 September 2018 (water) Moved to Phase 5 Vanderbilt
100 95 / 5 / NA July to Mid- August 2017 July 2017 June to August 2018 Vanderbilt
May 2017 through April 2018 March to April 2018 March 2018 February to March 2019 Vanderbilt
June 2017 through March 2018 March 2018 March 2018 September to October 2018 Phase 5 May 2018 through September 2018 July to Sept 2018 July to Sept 2018 September to October 2018 Phase 6 April 2018 through January 2019 Oct 2018 to Jan 2019 Oct 2018 to Jan 2019 February to March 2019 Phase 7 December 2018 through Feb 2019 Feb 2019 Feb 2019 April 2019
*FM = Force Main, PS = Pump Station
Conners Ave. moved to Phase 5 286 Heron Ave. staging moving to Conner Park New Phase 1 – 7 Staging Area
152 Heron Ave. paver storage to remain until September 2017 Flamingo Ave. & Heron Ave. 1st lift asphalt May 2017 Egret Ave. & Vanderbilt Dr. 1st lift asphalt July 2017
Anticipated May 2017 – April 2018 Anticipated June 2017 – March 2018
Anticipated April – May 2018 Anticipated May – June 2018
Anticipated June – Aug 2018 Anticipated May – September 2018
Anticipated Sept. – Oct. 2018 Anticipated April 2018 – January 2019
Anticipated Feb. – March 2019 Anticipated Dec. 2018 – Feb. 2019
Anticipated April 2019
Project Area MSTU Energizing Main Feeder (Vanderbilt Dr., Bluebill, & VBR) April - May 2018 Bluebill Ave. May 2018 VBR & GulfShore Dr. June 2018 Flamingo Ave., Heron Ave., & Egret Ave. June - August 2018 Conners Ave., Seabee Ave., Germain Ave., Seagull, & Willet September - October 2018 Tradewinds Ave., Lagoon Ave., Bayside Ave., Pine
February - March 2019 Palm Court, 9207 Vanderbilt Dr. & Chateau Vanderbilt April 2019
*FM = Force Main, PS = Pump Station