v
FINAL DESIGN PRESENTATION SCHOOL BOARD ACTION ITEM
ABINGDON ELEMENTARY SCHOOL
ADDITION + RENOVATION
MARCH 3, 2016
v ABINGDON ELEMENTARY SCHOOL ADDITION + RENOVATION PROJECT - - PowerPoint PPT Presentation
MARCH 3, 2016 FINAL DESIGN PRESENTATION SCHOOL BOARD ACTION ITEM v ABINGDON ELEMENTARY SCHOOL ADDITION + RENOVATION PROJECT MILESTONES: Contractor Pre-qualification March 7, 2016 Final Design Submission to APS Board - Information
ADDITION + RENOVATION
MARCH 3, 2016
PROJECT MILESTONES:
2 OVERALL PROJECT SCHEDULE
589 – current capacity (building only) 729 – projected capacity 140 additional seats
3
ABINGDON ELEMENTARY SCHOOL: PROJECT SCOPE OVERVIEW EXHIBIT A
SITE PLAN
4
EXHIBIT B
Bus Drop-Off/Service
Transplanted trees
FLOOR PLAN
5 FINAL DESIGN Main Level & Second Level Lower Level Third Level
EXHIBIT C
6 FINAL DESIGN
FINAL DESIGN – FUNDING AVAILABLE
2014 Bond (Per FY 2015-2024 CIP) $28,750,000 Maintenance LTP & MC/MM Funding:*
$750,000
$800,000
$402,000
$103,000
$70,000
$115,365
$200,000
$51,000 Subtotal LTP & MC/MM $2,491,365 Capital Reserve*** $400,000 County/School Board Joint Fund
$619,603
$619,603 Subtotal Joint Fund $1,239,206
Grand Total Funding Available $32,880,571
Total APS Funding $32,260,968 Total County Funding $619,603 Notes: * LTP is Long Term Planning, MC/MM is Minor Construction / Major Maintenance ** Not included at the Schematic Design phase. *** Not included at the Schematic Design phase. APS Staff coverage for 33 months (July 2015 through March 2018).
EXHIBIT D
7 FINAL DESIGN
FINAL DESIGN – COST ESTIMATE
Construction Costs* $24,390,000 Construction Contingency $1,950,000 Soft Costs $6,140,571 APS Staff Costs $400,000 Estimated Total Project Cost $32,880,571 Total Funding Available $32,880,571 Over (Under) Funding Available $0
Note: * Based on two independent professional cost estimates; one from the A/E firm and one from the Construction Management firm.
EXHIBIT E
8 FINAL DESIGN
FINAL DESIGN – JOINT FUND ITEMS EXHIBIT F
Item Description Estimate* 1 Abingdon St. Traffic Calming $29,556 2 29th St. Crosswalk $53,349 3 29th / S. Abingdon St. Crosswalk $45,237 4 31st St. Trail Lighting $16,920 5 Sidewalk North of Abingdon St. Raised Crosswalk $143,556 6 Emergency Responder Network $204,981 7 29th St. Streetscape Improvements $52,337 8 Relocate County Owned Fencing at Trade Center $11,411 9 Fire Access Road $293,357 10 Demo Overhead Electric / Install New Underground Electric $257,337 11 Remove Invasive Species and Reforestation $39,921 12 Additional Geotechnical and Soil Investigations $91,244
Total $1,239,206
Note: * Includes construction, soft, and contingency costs
9