v
play

v ABINGDON ELEMENTARY SCHOOL ADDITION + RENOVATION PROJECT - PowerPoint PPT Presentation

MARCH 3, 2016 FINAL DESIGN PRESENTATION SCHOOL BOARD ACTION ITEM v ABINGDON ELEMENTARY SCHOOL ADDITION + RENOVATION PROJECT MILESTONES: Contractor Pre-qualification March 7, 2016 Final Design Submission to APS Board - Information


  1. MARCH 3, 2016 FINAL DESIGN PRESENTATION SCHOOL BOARD ACTION ITEM v ABINGDON ELEMENTARY SCHOOL ADDITION + RENOVATION

  2. PROJECT MILESTONES: • Contractor Pre-qualification – March 7, 2016 • Final Design Submission to APS Board - Information – February 18, 2016 • Final Design Submission to APS Board – Approval – March 3, 2016 • Invitation for Bid – March 9, 2016 • Bids Received – April 7, 2016 • APS Board Award of Contract – April 21, 2016 • Building Permit Received – May / June 2016 • Building packing and moving –June 27, 2016 • Start of Construction – July 5, 2016 • Building Fully Occupied – September 2017 (Construction phases continue between September & December) 2 OVERALL PROJECT SCHEDULE

  3. ABINGDON ELEMENTARY SCHOOL: PROJECT SCOPE OVERVIEW EXHIBIT A • Expanded Enrollment Capacity: 589 – current capacity (building only) 729 – projected capacity 140 additional seats • 27,000 SF Addition • 12 new classrooms & Support spaces • Gymnasium • Kitchen • Address existing space needs: • Library & Multi-purpose • Administration • Building systems improvements • Site improvements • Multi-modal transportation & Pedestrian access • Address traffic, drop-off/pick-up and parking • Phased construction keeping school fully operational 3

  4. EXHIBIT B Bus Drop-Off/Service Transplanted trees SITE PLAN 4

  5. FLOOR PLAN EXHIBIT C Third Level Lower Level Main Level & Second Level 5 FINAL DESIGN

  6. FINAL DESIGN – FUNDING AVAILABLE EXHIBIT D 2014 Bond (Per FY 2015-2024 CIP) $28,750,000 Maintenance LTP & MC/MM Funding:* • 2016 HVAC Bond Funding $750,000 • 2017 Roofing Bond Funding $800,000 • 2017 Infrastructure (Windows) Bond Funding** $402,000 • 2017 MC/MM Funding (Fields): $103,000 • 2017 MC/MM Funding (Flooring): $70,000 • 2017 MC/MM Funding (Painting) $115,365 • 2017 MC/MM Funding (Playground) $200,000 • 2017 MC/MM Funding (Plumbing) $51,000 Subtotal LTP & MC/MM $2,491,365 Capital Reserve*** $400,000 County/School Board Joint Fund • APS Funding $619,603 • County Funding $619,603 Subtotal Joint Fund $1,239,206 Notes: * LTP is Long Term Planning, MC/MM is Minor Construction / Grand Total Funding Available $32,880,571 Major Maintenance ** Not included at the Schematic Design phase. Total APS Funding $32,260,968 *** Not included at the Schematic Design phase. APS Staff coverage for 33 months (July 2015 through March 2018). Total County Funding $619,603 6 FINAL DESIGN

  7. FINAL DESIGN – COST ESTIMATE EXHIBIT E Construction Costs* $24,390,000 Construction Contingency $1,950,000 Soft Costs $6,140,571 APS Staff Costs $400,000 Estimated Total Project Cost $32,880,571 Total Funding Available $32,880,571 Over (Under) Funding Available $0 Note: * Based on two independent professional cost estimates; one from the A/E firm and one from the Construction Management firm. 7 FINAL DESIGN

  8. FINAL DESIGN – JOINT FUND ITEMS EXHIBIT F Item Description Estimate* Abingdon St. Traffic Calming 1 $29,556 2 29th St. Crosswalk $53,349 3 29th / S. Abingdon St. Crosswalk $45,237 4 31st St. Trail Lighting $16,920 5 Sidewalk North of Abingdon St. Raised Crosswalk $143,556 6 Emergency Responder Network $204,981 7 29th St. Streetscape Improvements $52,337 8 Relocate County Owned Fencing at Trade Center $11,411 9 Fire Access Road $293,357 10 Demo Overhead Electric / Install New Underground Electric $257,337 11 Remove Invasive Species and Reforestation $39,921 12 Additional Geotechnical and Soil Investigations $91,244 Total $1,239,206 Note: * Includes construction, soft, and contingency costs 8 FINAL DESIGN

  9. Thank You 9

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend