IRVR Improvement (AGL Credit) UK Flight Safety Committee Briefing 12 - - PowerPoint PPT Presentation

irvr improvement agl credit
SMART_READER_LITE
LIVE PREVIEW

IRVR Improvement (AGL Credit) UK Flight Safety Committee Briefing 12 - - PowerPoint PPT Presentation

IRVR Improvement (AGL Credit) UK Flight Safety Committee Briefing 12 th November 2013 Kevin Wilkins IEng, MRAeS Consultant XPX Consulting Ltd. kevin.wilkins@xpxconsulting.com Agenda Introduction/Agenda Current (Historical)


slide-1
SLIDE 1

Kevin Wilkins IEng, MRAeS Consultant XPX Consulting Ltd. kevin.wilkins@xpxconsulting.com

IRVR Improvement (“AGL Credit”)

UK Flight Safety Committee Briefing 12th November 2013

slide-2
SLIDE 2

Agenda

  • Introduction/Agenda
  • Current (Historical) IRVR Scenario
  • AGL Cleaning Trial - Summary & Summary Results
  • Proposed Operational Model for Winter 2013/14
  • Resultant IRVR Scenario & Futures
  • Questions
slide-3
SLIDE 3

Current (Historical) IRVR Scenario

  • Current calculations of Instrumented Runway Visual Range provide unduly

pessimistic figures, this results in Low Visibility procedures being enacted more often than is operationally necessary (when IRVR <600m)1

  • This is due to an assumption that Runway Aeronautical Ground Lighting
  • perates at no greater than 20% of design maximum luminescence. This

assumed performance (used in automatic IRVR calculations) is far less than actual performance due to Heathrow’s superior AGL maintenance & cleaning regimes

  • Recent changes to CAP670 (with input from Heathrow) now allow for an

assumed minimum AGL luminescence performance of 40% of design maximum, up to a maximum of 80%, if appropriate evidence is provided

1 - Study by TMS for HAL shows a potential reduction of 37 minutes per LVP day, equating to approx. 24 landings per LVP day (at an assumed luminescence of 75%)

slide-4
SLIDE 4

AGL Luminescence Degradation Trial at LHR – Summary

  • Two week trial conducted in March 2013
  • Plan was to deep clean all Runway AGL on day 0 of the trial and then conduct

MALMS (Mobile Airfield Light Monitoring System) check runs every two nights with no cleaning or maintenance during the trial to monitor luminescence degradation over time

  • However, due to operational safety requirements (adverse weather & Anti/De-

Icing operations) cleaning was unavoidable

  • Although disruptive to the trial, a reasonable amount of data had been

collected

  • Anti/De-Icing impacts provided valuable learning
slide-5
SLIDE 5

AGL Luminescence Degradation Trial – Summary Results Ave Beam Intensity (smoothed)

slide-6
SLIDE 6

Required Cleaning Regime in Anti/De-Icing Conditions

If Anti/De-Icing occurs ≥ 3 days before a scheduled 7 day AGL cleaning run an additional run must be performed within 2 days

slide-7
SLIDE 7

AGL Luminescence Degradation Trial – Summary Findings

  • Degradation immediately following full deep-clean on day 0 appears to confirm ICAO &

CAA assumption of a maximum performance of approx. 80%

  • Subsequent degradation appears largely linear (if impacts of adverse operations are

ignored)

  • Average Peak Beam Intensity across all four runways for the duration of the trial (with

cleaning interventions) measures approx. 65%

– However, Average Peak Beam Intensity did not consistently exceed 52% for all four runway directions within a seven day cleaning cycle, however adverse conditions make this difficult to assess

  • Based on very limited data the average Degradation Rate across the trial was approx. -

5%/day (or -2.75%/day if smoothed)

– Assuming a 100% situation at day 0, after day 6 AGL will have degraded to 84% Ave Peak Beam Intensity (best case) or 70% (worst case)

slide-8
SLIDE 8

Proposed Extended Operational Trial for Winter 2013/14

  • Pending imminent final approval from CAA SARG, Heathrow will run a further extended
  • perational trial during Winter 2013/14 (Nov 2013 – April 2014)
  • NATS are producing a Safety Assessment assuming the use of an initial AGL de-rating

factor of 60% (i.e. 40% degradation from CAP168 maxima) for the trial, based on: – Weekly Cleaning of Runway Edge AGL – Monthly MALMS checks (with provided Average Peak Beam Intensity readings) – Monitoring of aircrew and controller feedback during trial via FLOPSC – Post Anti/De-Icing cleaning of AGL as soon as is practicable and within 2 days if no scheduled clean will occur for 3 or more days from Anti/De-Icing activity

– Non-water based option if ambient temp. <40C

– Additional cleaning maintained in accordance with aerodrome SMS if required

  • Subsequent further improvements should be expected to be achievable based on the

results of this further trial, cost/benefit analysis may be appropriate

slide-9
SLIDE 9

Questions?

slide-10
SLIDE 10