irvr improvement agl credit
play

IRVR Improvement (AGL Credit) UK Flight Safety Committee Briefing 12 - PowerPoint PPT Presentation

IRVR Improvement (AGL Credit) UK Flight Safety Committee Briefing 12 th November 2013 Kevin Wilkins IEng, MRAeS Consultant XPX Consulting Ltd. kevin.wilkins@xpxconsulting.com Agenda Introduction/Agenda Current (Historical)


  1. IRVR Improvement (“AGL Credit”) UK Flight Safety Committee Briefing 12 th November 2013 Kevin Wilkins IEng, MRAeS Consultant XPX Consulting Ltd. kevin.wilkins@xpxconsulting.com

  2. Agenda • Introduction/Agenda • Current (Historical) IRVR Scenario • AGL Cleaning Trial - Summary & Summary Results • Proposed Operational Model for Winter 2013/14 • Resultant IRVR Scenario & Futures • Questions

  3. Current (Historical) IRVR Scenario • Current calculations of Instrumented Runway Visual Range provide unduly pessimistic figures, this results in Low Visibility procedures being enacted more often than is operationally necessary (when IRVR <600m) 1 • This is due to an assumption that Runway Aeronautical Ground Lighting operates at no greater than 20% of design maximum luminescence. This assumed performance (used in automatic IRVR calculations) is far less than actual performance due to Heathrow’s superior AGL maintenance & cleaning regimes • Recent changes to CAP670 (with input from Heathrow) now allow for an assumed minimum AGL luminescence performance of 40% of design maximum, up to a maximum of 80%, if appropriate evidence is provided 1 - Study by TMS for HAL shows a potential reduction of 37 minutes per LVP day, equating to approx. 24 landings per LVP day (at an assumed luminescence of 75%)

  4. AGL Luminescence Degradation Trial at LHR – Summary • Two week trial conducted in March 2013 • Plan was to deep clean all Runway AGL on day 0 of the trial and then conduct MALMS (Mobile Airfield Light Monitoring System) check runs every two nights with no cleaning or maintenance during the trial to monitor luminescence degradation over time • However, due to operational safety requirements (adverse weather & Anti/De- Icing operations) cleaning was unavoidable • Although disruptive to the trial, a reasonable amount of data had been collected • Anti/De-Icing impacts provided valuable learning

  5. AGL Luminescence Degradation Trial – Summary Results Ave Beam Intensity (smoothed)

  6. Required Cleaning Regime in Anti/De-Icing Conditions If Anti/De-Icing occurs ≥ 3 days before a scheduled 7 day AGL cleaning run an additional run must be performed within 2 days

  7. AGL Luminescence Degradation Trial – Summary Findings • Degradation immediately following full deep-clean on day 0 appears to confirm ICAO & CAA assumption of a maximum performance of approx. 80% • Subsequent degradation appears largely linear (if impacts of adverse operations are ignored) • Average Peak Beam Intensity across all four runways for the duration of the trial (with cleaning interventions) measures approx. 65% – However, Average Peak Beam Intensity did not consistently exceed 52% for all four runway directions within a seven day cleaning cycle, however adverse conditions make this difficult to assess • Based on very limited data the average Degradation Rate across the trial was approx. - 5%/day (or -2.75%/day if smoothed) – Assuming a 100% situation at day 0, after day 6 AGL will have degraded to 84% Ave Peak Beam Intensity (best case) or 70% (worst case)

  8. Proposed Extended Operational Trial for Winter 2013/14 • Pending imminent final approval from CAA SARG, Heathrow will run a further extended operational trial during Winter 2013/14 (Nov 2013 – April 2014) • NATS are producing a Safety Assessment assuming the use of an initial AGL de-rating factor of 60 % (i.e. 40% degradation from CAP168 maxima) for the trial, based on: – Weekly Cleaning of Runway Edge AGL – Monthly MALMS checks (with provided Average Peak Beam Intensity readings) – Monitoring of aircrew and controller feedback during trial via FLOPSC – Post Anti/De-Icing cleaning of AGL as soon as is practicable and within 2 days if no scheduled clean will occur for 3 or more days from Anti/De-Icing activity – Non-water based option if ambient temp. <4 0 C – Additional cleaning maintained in accordance with aerodrome SMS if required • Subsequent further improvements should be expected to be achievable based on the results of this further trial, cost/benefit analysis may be appropriate

  9. Questions?

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend