aeronautical ground lighting agl at klia
play

Aeronautical Ground Lighting (AGL) at KLIA Presented by: Mohd Sabri - PowerPoint PPT Presentation

Aeronautical Ground Lighting (AGL) at KLIA Presented by: Mohd Sabri Abd Aziz 1. INTRODUCTION FACILITATORS PROFILE Name : Mohd Sabri Abd Aziz Company : Malaysia Airports (Sepang) Sdn Bhd Designation : Manager, AGL/EPS KLIA Qualification :


  1. Aeronautical Ground Lighting (AGL) at KLIA Presented by: Mohd Sabri Abd Aziz

  2. 1. INTRODUCTION

  3. FACILITATOR’S PROFILE Name : Mohd Sabri Abd Aziz Company : Malaysia Airports (Sepang) Sdn Bhd Designation : Manager, AGL/EPS KLIA Qualification : Bachelor of Electrical Engineering, Gannon University, USA ; Graduate Diploma in Business Administration, National University of Singapore; Work Experience : Operation & Maintenance of Airport Facilities since 2001

  4. GROUP CORPORATE STRUCTURE

  5. AIRPORTS OPERATED BY MALAYSIA AIRPORTS 39 Airports in Malaysia: - 5 International - 16 Domestic - 18 STOL ports

  6. KLIA INFO • 10,000 Hectares or LAND AREA • 25,000 Acres • 2 Parallel Runways NOS OF RUNWAY • 4000 m x 60 m FIRE CATEGORY • Category 9 • 46 Contact Bays NOS OF AIRCRAFT BAYS • 59 Remote Bays • 1 VVIP Parking Bays TERMINAL DESIGN • 25 MPPA CAPACITY • MTB (241,000 SQM) TOTAL FLOOR AREA • Contact Pier (95,000 SQM) • Satellite (143,404 SQM) • 6 Check In Island CHECK IN COUNTER • 144 Counters for Int. Dprt & 72 Counters for Dom. Dprt

  7. AGL UNIT ENGINEERING STRUCTURE Airfield Ground Lighting Manager (1) Operation Reliability Improvement Senior Exec –Engineer Senior Exec –Engineer Maintenance (1) (1) Executive –Engineer (1) Admin/Floating Executive –Engineer Executive –Engineer Shift (1) (1) Executive –Technical (1x4)=4 Admin/Floating Chargeman A4 (1) Chargeman A4 KLIA klia2 (1x4)=4 Technical Officer Technical Officer Technical Officer Technical Officer (3x4)=12 (1) (1) (1) Admin Technician Technician Technician Technician Admin/Ops Assistant (6) (3) (4x4)=16 (1) (1)

  8. INTRODUCTION At the end of the briefing participant will be able to know and understand what is AGL KLIA unit core activities and operations all about.

  9. CORE ACTIVITIES The objective is meeting the Customer requirements with the priority on Continuous Improvement Emergency/ Unplanned Breakdown Maintenance Maintenance Planned Corrective Preventative Maintenance Maintenance Condition Capital Based Works Maintenance Core Minor Inspection Works Activities

  10. SCOPE OF SERVICE This scope for operation and maintenance services of KLIA AGL system are managed by KLIA AGL Unit . The requirements specified are aimed primarily at meeting the contractual obligations of the KLIA Operation and achieving customer satisfaction by preventing non-conformity with regard to the operation and maintenance services specification.

  11. SCOPE OF OPERATION AND MAINTENANCE SERVICE LIGHT FITTINGS CABLES Insulation Resistance Fittings cleaning Measurement Ground Resistance Replacement faulty lamps Measurement Fittings alignment

  12. SCOPE OF OPERATION AND MAINTENANCE SERVICE • Electrical system • Maintain and replenish maintenance consumable items (i.e. printer paper, cartridges) • A/C maintenance • Maintain Video Display • Replenish fuel tank Unit (VDU) • Maintain generator set • Maintain/calibrate • Maintain CO2 system stopbar sensors SUBSTATION CMS

  13. FACILITIES MANAGEMENT Processes to ensure that the services provided is effective to support the overall airport operations in supporting and contributing to the objective of the company Financial Continuous Analysis Improvement (5S / WCM) (SAP) Customer Technology Needs Application Evaluation (MALMS/SAP) (KPI / Surveys) FACILITIES MANAGEMENT

  14. KNOWLEDGE DEVELOPMENT AND ENHANCEMENT Training provision based on the Competency enhancement gap exist in yearly performance through oversea training by the appraisal. manufacturer for executives KNOWLEDGE DEVELOPMENT Exposure to the staffs during SIRIM (ISO 9001:2008, ISO 14001 - Chargeman training and Environment & ISO 18001 – Safety examination arrangement and Health) audit and DCA audit

  15. AGL - Maintenance • 24 hours day to day Operation and Maintenance • Lighting and signage on approach, apron, taxiways and runways maintenance • Maintain 5 units of substations -128 numbers of circuits • Comprise 4 groups of staff which working on Shift and 1 group Office Hour maintenance • Shift personnel as front-liner, carried out schedule maintenance, control and monitor all facilities via Maintenance Working Position (MWP) • Office Hour personnel focused on primary cable maintenance maintenance

  16. AGL - Maintenance • 750 KVA Generator • 300 KVA Generator (UPS) and Battery bank • Constant Current Regulator, Transformer MONTHLY Module • Air-conditioning, Fire Protection • All inset and elevated fittings • Control and Monitoring lamps via MWP • 5 nos. 11kV Substation – LV • Movement Sensor 6 MONTHLY • Primary Cable Insulation Test • Low Voltage (LV) Maintenance at all Substations 18 MONTHLY

  17. 2. CONSTANT CURRENT REGULATORS (CCR)

  18. CONSTANT CURRENT REGULATORS (CCR)

  19. CONSTANT CURRENT REGULATORS (CCR) HONEYWELL ADB ? NOS ? NOS YEAR YEAR PURCHASED PURCHASED (1997) (2013)

  20. CONSTANT CURRENT REGULATORS (CCR) AGL CCR Cabinet

  21. CONSTANT CURRENT REGULATORS (CCR) • During any period of Cat I operations shall have its • And that in any event at objective that all: least:  Approach Lighting System  Runway Edge  Runway Threshold  Runway End are SERVICEABLE (Annex 14 – 10.4.10)

  22. CONSTANT CURRENT REGULATORS (CCR) • During any period of Cat II • And that in any event at operations shall have its least: objective that all: 95% 90% 85% 75% Approach inner 450m Approach Touchdown Center line beyond Runway End Zone 450m Threshold Edge (Annex 14 – 10.4.7)

  23. 3. GENERATOR SET

  24. GENERATOR SET

  25. GENERATOR SET SUB A • Kohler (750 KVA) – 1 unit • Scania (300 KVA) – 1 unit SUB B • Kohler (750 KVA) – 1 unit • Scania (300 KVA) – 1 unit SUB C • Kohler (750 KVA) – 1 unit • Kohler (750 KVA) – 1 unit SUB D • Kohler (800 KVA) – 1 unit 7 • Scania (300 KVA) – 1 unit SUB E • Kohler (750 KVA) – 1 unit • Scania (300 KVA) – 1 unit SUB F • Kohler (800 KVA) – 1 unit 12 12 SUB G • Kohler (800 KVA) – 1 unit

  26. 750KVA Standby Generator

  27. GENERATOR SET REQUIREMENTS • Secondary Power Supply • Maximum Switch-over time Requirements for Precision Approach Category II/III:  Runway Edge  Approach – Other parts  Approach – Inner 300m  Runway Threshold  Runway End  Runway Centreline  Runway Touchdown zone (Annex 14 – Table 8-1)  All Stopbars

  28. 3. AIRFIELD LIGHTING SYSTEM

  29. Airfield Lighting System • 2 systems, 32L14R and 32R14L Runway Lights • 4 systems, 32L,14R,32R and 14L CAT II Approach Lights • 4 parallel taxiways, 4 cross taxiways Taxiway & Cross Taxiway Lights and 125 taxiways Precision Approach • 4 systems Path Indicator Lights (PAPI)

  30. Airfield Lighting System • 440 sets Guidance Signs (MAGS) Constant Current • 128 circuits Regulators (CCR) Single Lamp Control • 15,000 lamps and Monitoring System (SLCMS) • 4 illuminated wind directional Miscellaneous Lights indicator and 22 traffic lights.

  31. Airfield Lighting System ADB HONEYWELL THORN

  32. Runway Lightings

  33. Runway Lightings Runway Center, Touch Down Zone, Runway Edge Light & Taxiway Center Threshold Light & End Lights

  34. Approach Lightings

  35. Approach Lightings Approach 32R – CAT II System Approach 14R – CAT II System

  36. Taxiway Lightings Taxiway Edge & Taxiway Center

  37. PAPI

  38. Miscellaneous Fittings Traffic / Stop-Bar Guard Lights Illuminated Wind Direction Indicator

  39. Movement Area Guidance Sign Information Sign – Location and Direction Mandatory Sign

  40. 4. CONTROL & MONITORING SYSTEM

  41. Control & Monitoring System Individual Lamp Control via Power Line Control Signal Pre-defined Runway Lighting Selection Selectable uni-directional or bi-directional taxiway lighting as required Fast Reaction Panel (FRP) and Touch Screen Input Devices Single Lamp Failure Monitoring Automatic Monitoring and Reporting System and Element Failures Direct Individual Unique Identification of Failed Equipment or Element

  42. Control & Monitoring System

  43. Lamp Control & Monitor - Tower Control Tower - Controller Working Position

  44. View of the Controller Working Position (CWP) Screen

  45. Zoom-in view of a section on the Controller Working Position (CWP)

  46. View of the Controller Working Position (CWP) Screen

  47. 5. POWER SYSTEM

  48. AGL - Power System 5 lots of Standby Generating System: 5 nos. Substations: 750KVA x 1 4 nos. of 400m2 nos. x 4 (footprint) + 1 no. of substations + 570m2 (footprint) 750KVA x 2 nos. x 1 substations 5 lots of HV/LV Systems: Switch Gear: 11KV x 5 substations 4 lots of Uninterrupted Transformer: 630KVA x 2 nos. x 4 Power Supply substations + System Dynamic 1600KVA x 2 nos. x 1 Generator Set: 350KVA x 1 substations nos. x 4 substations Back Indication Panel - 5 sets Battery Other related Distribution Boards and Bank:257nos Cables x 2 Banks 22,000L Fuel Tank System - 5 sets (Total 490AH) x 4 Substations

  49. Typical Substations

  50. Constant Current Regulator & Transformer Module Transformer Module & Constant Current Regulator Panels Transformer Module – 25KV

  51. LV Panel & ACB

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend