US 20 at Harmony Road Study Public Hearing August 5, 2015 Project - - PowerPoint PPT Presentation

us 20 at harmony road study
SMART_READER_LITE
LIVE PREVIEW

US 20 at Harmony Road Study Public Hearing August 5, 2015 Project - - PowerPoint PPT Presentation

US 20 at Harmony Road Study Public Hearing August 5, 2015 Project Location 2013 Preferred Alternative Fo Former Harmon Harmony School y School (His (Historic Proper ric Property) ty) Project Development Process Plan Analysis of


slide-1
SLIDE 1

US 20 at Harmony Road Study

Public Hearing August 5, 2015

slide-2
SLIDE 2

Project Location

slide-3
SLIDE 3

2013 Preferred Alternative

Fo Former Harmon Harmony School y School (His (Historic Proper ric Property) ty)

slide-4
SLIDE 4

Project Development Process

PHASE III

Construction

PHASE II

Design & Land Acquisition

PHASE I

Preliminary Engineering & Environmental Studies

  • Analysis of conditions
  • Purpose and Need
  • Development of Alternatives
  • Preferred Alternative
  • Plan

Preparation

  • Acquire Right

Of Way

Current Phase

This improvement is included in the Department’s FY 2016-2021 Proposed Highway Improvement Program. The current engineering efforts are targeted to enable a contract letting in the middle years of our current multi-year program contingent upon plan readiness, land acquisition, and funding availability through future annual legislative appropriations.

slide-5
SLIDE 5

Process and Schedule

PM #1 PH #1 Roundabout Alternative Approved

(May 2013)

Public Meeting Project Milestone Stakeholder Meeting

Initiate Phase I Study

PHASE PHASE I I

Stakeholder Meeting

  • Eng. & Env. Studies

Environmental Measures

  • Cultural Resources
  • Threatened and Endangered

Species

  • Wetlands
  • Woodlands
slide-6
SLIDE 6

2013 Roundabout

Fo Former Harmon Harmony School y School (His (Historic Proper ric Property) ty)

slide-7
SLIDE 7

Section 106/4(f) Studies

  • National Register Eligible
  • National Historic

Preservation Act of 1966

  • National Transportation Act
  • f 1966
  • Re-opened Phase I
  • Avoidance alternatives
slide-8
SLIDE 8

Process and Schedule

Public Meeting Project Milestone Stakeholder Meeting We Are Here PH #2 Stakeholder Meeting Stakeholder Meeting Stakeholder Meeting Stakeholder Meeting

Initiate Phase I Study

PHASE PHASE I I

Begin Phase II

PM #1 PH #1 Roundabout Alternative Approved

(May 2013)

Stakeholder Meeting FHWA/SHPO Concurrence on Avoidance SHPO Designates Harmony School Property eligible for Historic Register

slide-9
SLIDE 9

Purpose and Need

Pr Project Pur

  • ject Purpose
  • se
  • Improve Safety and Operations

Transpor ansportation Needs tation Needs

  • Safety

– 5% Location – Fatal and Severe Crashes – Rear End, Angle Crashes

  • Design

– Poor sightlines, curved alignment – Lack of turn lanes

slide-10
SLIDE 10

Existing Conditions - Traffic

I

HARMONY R HARMONY ROAD AD US 20 US 20 8200 v 8200 vehicles hicles per da per day 2500 v 2500 vehicles hicles per da per day

slide-11
SLIDE 11

Existing Conditions - Plan

I

HARMONY R HARMONY ROAD AD 55° 55° US 20 US 20

slide-12
SLIDE 12

Existing Condition - Profile

Harmony Road W US 20

L C

E Northbound Harmony centerline US 20 N S

slide-13
SLIDE 13

Existing Condition - Profile

Harmony Road W US 20 centerline E

slide-14
SLIDE 14

Existing Conditions - Safety

I

17 14 11 17

slide-15
SLIDE 15

Alternatives Considered

  • Do nothing
  • 4-way stop
  • Reduce Speed Limit
  • Cut down hill on US

20

  • Traffic signal with no

reconstruction  Safety issues not addressed  Back Ups  Not effective as stand alone strategy  Does not address curve and skew  Does not address sightlines

slide-16
SLIDE 16

I

Additional Left Turn Lane on US 20 Extension of Left Turn Lane on Harmony Road US 20 Right Turn Lane Eastbound Right Turn Lane North Leg Realigned South Leg Realigned Profile Flattened

2015 Signal Alternative

slide-17
SLIDE 17

I

2015 Roundabout Alternative

Raised traffic Islands North Leg Realigned Profile Flattened Future Right Turn Lane (as needed)

slide-18
SLIDE 18

Alternative Comparison

Roundabout undabout Traf affic Signal ignal

Land Acquisition 3.3 Acres 7.9 Acres Impacted Parcels 6 Parcels 21 Parcels Level of Service C (AM) / B (PM) D (AM) / C (PM) Construction Cost ± $5.0 M ± $6.4 M Land Cost ± $0.38 M ± $1.3 M Building Removals 1 2 Relocations 1 Wetland Impacts 0.72 Acres 0.8 Acres Woodland Impacts 1.5 Acres 2.9 Acres Expected Severe Crash Reduction 57% Decrease 9% Decrease

slide-19
SLIDE 19

Detour Map

Closu Closure: e: East Leg of Intersection De Detour: ur: Westbound Marengo Road to Southbound US 20

slide-20
SLIDE 20

Roundabouts

slide-21
SLIDE 21

Roundabouts

Entr Entry Exit Exit Cir Circulat ulator

  • ry R

y Roadw adway Tr Truck A Apron Splitt Splitter Island er Island Cent Center Island er Island

slide-22
SLIDE 22

Roundabouts - Safety

  • Reduce conflict points

– 44% reduction in overall crashes – 82% reduction in injury/fatal crashes

  • Motorists travel at lower

speeds

– Safer for pedestrians – Increase driver reaction time

slide-23
SLIDE 23

Roundabouts – Truck Apron

Tr Truck A Apron

slide-24
SLIDE 24

Land Acquisition Procedure

  • Fee Simple
  • Acquisition of all rights and interest
  • Permanent Easement
  • Ownership retained by property owner
  • IDOT allowed permanent use of property

to construct and maintain facilities

  • Temporary Easement
  • Ownership retained by property owner
  • Temporary use to construct minor

improvements

Relocation Assistance Condemnation if Necessary Negotiations with Property Owners Prepare Independent Appraisal Determine Ownership

slide-25
SLIDE 25

Next Steps

  • Browse exhibits
  • Direct questions to the study

team

  • Please fill out a comment form

– Comment period ends August 26,

2015

  • Provide verbal testimony to the

court reporter

slide-26
SLIDE 26

Thank You

www www.us20atHarmon .us20atHarmony.com .com