SAWMI LL ROAD / BRI GHT ROAD CORRI DOR STUDY PROJECT OVERVIEW NOVEMBER 29, 2016 AGENDA Sawmill Road/Bright Road Corridor Study Project background Next steps Preliminary ideas Additional Bright Road Projects Cul-de-sac


  1. SAWMI LL ROAD / BRI GHT ROAD CORRI DOR STUDY PROJECT OVERVIEW NOVEMBER 29, 2016

  2. AGENDA Sawmill Road/Bright Road Corridor Study • Project background • Next steps • Preliminary ideas Additional Bright Road Projects • Cul-de-sac construction • Waterline and sanitary sewer construction

  3. PROJECT BACKGROUND The study is intended to address congestion and safety issues within the Sawmill Road/Bright Road corridor: • Determine the number of through lanes needed along Sawmill Road • Investigate intersection improvements • Study roadway improvements to Bright Road

  4. PROJECT BACKGROUND Study Area • Sawmill Road • SR 161 to Hard Road • Bright Road • Emerald Parkway to Sawmill Road • Snouffer Road • Sawmill Road to Caine Road

  5. NEXT STEPS • • Develop conceptual alternatives Continue public for intersection improvements information and • Sawmill/SR 161 participation • Sawmill/Banker/Sawmill Place • Develop design year • Sawmill/Federated/Village Pkwy traffic • Sawmill/Snouffer • Determine the • Snouffer/Caine appropriate number of • Sawmill/Dublin Center lanes on Sawmill Road • Sawmill/Billingsley and Bright Road • Sawmill/Bright/Sawbury • Sawmill/Hard

  6. BRI GHT ROAD PRELI MI NARY I DEAS

  7. BRI GHT ROAD PRELI MI NARY I DEAS

  8. BRI GHT ROAD PRELI MI NARY I DEAS

  9. BRI GHT ROAD PRELI MI NARY I DEAS

  10. CONTACT I NFORMATI ON We request that you provide us your input. This will allow us to address issues during the study. You can contact the Project Team the following ways: • The comment forms provided here • Contacting the City of Dublin: Jean-Ellen Willis, Engineering Manager - Transportation 5800 Shier Rings Road Dublin, Ohio 43016 614.410.4633 jwillis@dublin.oh.us

  11. BRI GHT ROAD CUL-DE-SAC F

  12. Gateway - Location View for the Driver Views from the Path

  13. Gateway - Landscape Seasonal Plant Selection Layered Landscapes

  14. Gateway - Feature Elements Pillars Decorative Iron Fence Layered Seasonal Plant Landscapes Selection

  15. Sanitary Sewer and Water Extensions – Bright Road area Area 4B • Engineering Design - 2017 • Construction – 2018 • Bright Road from Riverside Drive to Grande Cliffs Subdivision F

  16. Sanitary Sewer & Water Extensions – Bright Road area Madbeth Dr Area 4C • Engineering Design - 2017 • Construction – 2018 • Grandee Cliffs Drive from Jenmar Court to Bright Road • Bright Road from MacBeth Drive to Grande Cliffs Subdivision F

  17. Sanitary Sewer and Water Extensions – Bright Road area Area 4A • Engineering Design - 2018 • Construction – 2019 • Riverside Drive – Emerald Parkway to Hard Road F

  18. Sanitary Sewer and Water Extensions – Bright Road area Area 4D • Engineering Design - 2029 • Construction – 2030 • Development potential • Bright Road – Emerald Parkway to Sawmill Road F

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.