Status of Delta-DOR interoperability E SOC, Darmstadt October 19 - - PowerPoint PPT Presentation

status of delta dor interoperability
SMART_READER_LITE
LIVE PREVIEW

Status of Delta-DOR interoperability E SOC, Darmstadt October 19 - - PowerPoint PPT Presentation

Status of Delta-DOR interoperability E SOC, Darmstadt October 19 th , 2009 Mattia Mercolino E SA/ E SOC, Summary ESA-JAXA DOR tracking on Hayabusa / VEX Status and plans of ESA enhanced Wideband DOR for future supports to JPL


slide-1
SLIDE 1

Status of Delta-DOR interoperability

E SOC, Darmstadt October 19th, 2009 Mattia Mercolino E SA/ E SOC,

slide-2
SLIDE 2

Summary

ESA-JAXA ΔDOR tracking on Hayabusa / VEX Status and plans of ESA enhanced Wideband ΔDOR for

future supports to JPL

ESA-JPL wideband ΔDOR interoperability testing and

MSL support

slide-3
SLIDE 3

ESA-JAXA ΔDOR tracking

  • n Hayabusa / VEX
slide-4
SLIDE 4

Hayabusa observations

Acquisitions: 2 acquisitions of Hayabusa were made during 2008 During the first tracking there were problems in DSN

antenna pointing for the uplink of ranging tones to the S/C, therefore only quasar and carrier signal were acquired

The second tracking was successful Data translation: After a first round of data translation / correlation, problems

with biases of JAXA data when correlated against either NNO data or DSN data, were detected

Any need for further investigation? How can ESA help on this?

slide-5
SLIDE 5

VE X observations

  • VEX is currently being observed monthly (once per month) by ESA in
  • rder to provide JPL with plane-of-the-sky measurement of the S/C
  • ESA provided JAXA with the dates for a VEX tracking in the 2009/2010

timeframe

  • This will most probably be the last opportunity to perform such mixed-

baseline validation on VEX

  • Passes 2009
  • Passes 2010 (confirmed at the moment)
  • JAXA to identify suitable dates for the support
  • ESA / JAXA to plan and execute the observation(s)

DDOR Date in 2009 UTC 2010 DoY CEB 10 DEG BOA BOT EOT EOA 06-Nov 05:43-07:43 310 06:28 05:43 06:28 07:28 07:43 14-Dec 07:25-09:25 348 08:10 07:25 08:10 09:10 09:25 DDOR Date in 2010 UTC 2010 DoY CEB 10 DEG NNO BOA NNO BOT NNO EOT NNO EOA Status with NNO Comments 16-Feb 08:25-10:25 47 08:38 08:25 09:10 10:10 10:25 OK 20-Mar 08:05-10:05 79 08:00 08:05 08:50 09:50 10:05 OK 11-Apr 07:40-09:40 101 07:41 07:40 08:25 09:25 09:40 NOK Move to DSN 10-May 07:50-09:50 130 07:43 07:50 08:35 09:35 09:50 NOK Move to DSN 23-Jun 08:50-10:50 174 08:52 08:50 09:35 10:35 10:50 NOK Move to DSN

slide-6
SLIDE 6

Status and plans of ESA enhanced Wideband ΔDOR

slide-7
SLIDE 7

E SA enhanced wideband ΔDOR (1)

From Phoenix support experience, the limiting factor of ESA ΔDOR

accuracy is the total spanned bandwidth at the receiver (maximum 28 MHz) that allows the reception of only one of the ΔDOR tones at X-band (19 MHz wrt the carrier)

ESA is undergoing an activity to upgrade its ΔDOR receiving

capabilities for wideband ΔDOR (i.e. use of both 19 MHz tones and/or 2nd harmonics of such tones)

Some rewiring of the back-end at both Cebreros and New Norcia

DSA was performed during summer 2009.

slide-8
SLIDE 8

E SA enhanced wideband ΔDOR (2)

In order to be able to acquire the spectrum The wiring will be upgraded as follows

slide-9
SLIDE 9

E SA enhanced wideband ΔDOR (3)

The new wiring was installed in Cebreros and New Norcia later

than expected due to the slip pf Herschel-Plank launch.

At both stations the wiring concept was successfully validated

during Summer 2009

Dry-run tests were run in late September showing that some

modification is needed in the IFMS receiver. Such modification has already been requested and work is currently on-going.

Modifications on the S/W correlator are also needed. These will be

undertaken during 2010.

The objective is to acquire data in Wide-band during the first

months of 2010 for later processing.

slide-10
SLIDE 10

ESA-JPL wideband ΔDOR interoperability testing and support to MSL

slide-11
SLIDE 11

MRO observations

  • In order to fully validate the ESA wideband Delta-DOR functionality the

following options are foreseen:

First functional validation of the acquisition with one station only First end-to-end validation on ESA S/C (VEX in the frame of th eactivity

already foreseen)

Real-scenario validation using a S/C with DOR tones at X-band

candidate MRO. Is this feasible in the frame of the mutual agreement between JPL and ESA for Delta-DOR operations? Any other S/C that could be used?

Two are the configuration to be tested: Delta-DOR from ESA stations only Delta-DOR in mixed-baseline mode

  • Since data translation from/to VSR has already been proven, the
  • bservations on MRO would:

Validate ESA wideband raw data capture Validate ESA capability of correctly correlate data acquired in wideband

at its stations

Validate ESA capability of correctly correlate data acquired in wideband

in mixed-baseline mode

slide-12
SLIDE 12

Tentative schedule

ESA-JPL MRO Delta-DOR tentative schedule: JPL to provide ESA with possible tracking dates ESA to arrange such trackings within its station schedule

  • Dec. 09
  • Sept. 10

TBD 10 HW upgrades readiness SW upgrades readiness

  • Apr. 2009

Tracking and data processing and validation

slide-13
SLIDE 13

ΔDOR support to MSL?

ESA is undertaking an upgrade to wideband Delta-DOR in order to

be able to support recordings up to 100 MHz wide (the limitation in this case is the diplexer) in the band 8.4 – 8.5 GHz

This should enhance the Delta-DOR accuracy of the ESA system to

the same level of the JPL system

Once the capability is installed, verified and tested in a real-case

scenario (i.e. with VEX and then with MRO), JPL and ESA could jointly produce and distribute to the MSL project a Memo outlining the obtained results

Status of MSL project? Request for ESA DDOR support?