Status of Delta-DOR interoperability Bordeaux Apr 15 th , 2012 - - PowerPoint PPT Presentation

status of delta dor interoperability
SMART_READER_LITE
LIVE PREVIEW

Status of Delta-DOR interoperability Bordeaux Apr 15 th , 2012 - - PowerPoint PPT Presentation

Status of Delta-DOR interoperability Bordeaux Apr 15 th , 2012 Mattia Mercolino E SA/ E SOC Summary Validation of ESA enhanced Wideband DOR Validation of RDEF format Validation of low SNR development Ka-band Quasar


slide-1
SLIDE 1

Status of Delta-DOR interoperability

Bordeaux Apr 15th, 2012 Mattia Mercolino E SA/ E SOC

slide-2
SLIDE 2

Summary

 Validation of ESA enhanced Wideband DOR  Validation of RDEF format  Validation of low SNR development  Ka-band Quasar catalogue  Full interoperability validation

slide-3
SLIDE 3

E SA wideband DOR

 All 3 ESA DS antennas are equipped with wide-band DDOR wiring

(latest being MLG, tested from June 2012 on)

 Functional tests of wideband implementation was carried out during

Spring/Summer 2012

 Final test with flying S/C with DOR tones executed on JUNO (Sept

2013)

 Validation with JPL: Data correlated by ESA/JPL in the frame of the

RDEF validation

  • Results in line with theoretical sigma calculations
  • End-to-end validation (including OD) still pending
  • Needed in the frame of In-Sight preparation

 Validation with JAXA: still pending (needed in the frame of

BepiColombo cross-support)

slide-4
SLIDE 4

RDE F interface (1)

 RDEF format has been implemented at both data translator and

correlator level

 The current implementation of the data translator / correlator

provides all possible translation combinations

RDEF Translator NASA DSN JPL VSR ESA DSN Correlator MK-V VLBI ESA EOLP RDEF

slide-5
SLIDE 5

RDE F interface (2)

 Final RDEF implementation was integrated in the upgraded ESA

translator/correlator S/W

 Concerning the validation of the RDEF format,

  • Validation with JPL: JUNO data have been used to this

purpose. The exercise showed no issues between JPL implementation and ESA S/W.

  • Validation

with JAXA: still pending (needed for the BepiColombo cross-support)

  • Validation with BITTT: initiated (on VEX data translated to

RDEF and provided to BITTT) in the frame of the Chang’E3 Delta-DOR support. No data received so far from BITTT. No end-to-end exercise completed to date.

slide-6
SLIDE 6

Low SNR

 Last enhancement of the ESA DDOR correlator regards the

capability to process data at very low SNR (i.e. 1 dBHz)

 Such capability has first been implemented and tested with

simulated data in February 2012

 Final test was performed on VEX data, which were artificially

manipulated in order to add “thermal-like” noise and lower down the signal-to-noise density ratio on the S/C signal.

 Test demonstrated that current ESA implementation agrees with

theoretical expectations given the signal-to-noise density ratio level and the integration time used

 Test/Use with actual data may be planned with Hayabusa  TBC

with JAXA

slide-7
SLIDE 7

Ka-band Quasar survey [1]

 Following the meeting in Boulder, a roadmap was set together with

  • C. Jacobs to target a Ka-band quasar observation campaign from

Malargüe, in late 2012, early 2013

 An IA and a dedicated TAA were signed between NASA/ESA  First set of test was organised, involving Robledo and Canberra

antennas on JPL side and Cebreros on ESA side, in July 2012.

 After validation of set-up the PRSR (JPL receiver) has been

shipped to ESA DS-3 (Malargüe) and installed there in November.

 First tests executed in December 2012 with detection of fringes in

Ka-band

 More

tests (including 12-h long runs) were performed in January/February

 Latest tests performed on 12/13th of April (data still to be

processed)

slide-8
SLIDE 8

Ka-band Quasar survey [2]

 ESA DS-3 adds 3 baseline to the current JPL configuration, allowing for

full southern sky coverage

 Almost perpendicular baselines between W-E and N-S directions

9810 km 8400 km 8500 km 10,600 km 9900 km

slide-9
SLIDE 9

Ka-band Quasar survey [3]

 Tests with MLG allowed the addition of 95 new sources in Ka-band to date  Accuracy can be improved only by further observations  The continuation of the activity needs a formal request by JPL

slide-10
SLIDE 10

Full interoperability validation [1]

 In order to have a full interoperability validation between ESA and

any other Agency, the following has to be addressed

 I/F validation

  • Validation of RDEF format
  • Validation of TDM (for processed DDOR and meteo data)
  • Validation of OEM (for orbit predication data)

 Functional validation

  • Validation of wideband DDOR (necessary to support S/C with

DOR tone according CCSDS 401-B)

  • Validation of low SNR (in case S/C with weak signal have to be

supported)

 End-to-end validation

  • Validation
  • f

OD solutions

  • btained

with interoperability exercise

slide-11
SLIDE 11

Full interoperability validation [2]

Validation with JPL

 I/F validation

  • Validation of RDEF format  OK (on JUNO)
  • Validation of TDM  OK (several instances, also new TDM)
  • Validation of OEM  OK (several instances)

 Functional validation

  • Validation of wideband DDOR  OK (on JUNO)
  • Validation of low SNR  Not exercised yet

 End-to-end validation

  • Validation of OD solutions  OK (for narrowband DDOR)
  • Validation of OD solutions  Not done yet (for wideband DDOR)

Priority: exercise end-to-end validation of wideband DDOR (for In-Sight)

slide-12
SLIDE 12

Full interoperability validation [3]

Validation with JAXA

 I/F validation

  • Validation of RDEF format  Not exercised yet
  • Validation of TDM  OK (TBC)
  • Validation of OEM  OK

 Functional validation

  • Validation of wideband DDOR  Not exercised yet
  • Validation of low SNR  Not exercised yet

 End-to-end validation

  • Validation of OD solutions  Not done yet (for narrowband DDOR)
  • Validation of OD solutions  Not done yet (for wideband DDOR)

Priority: validate RDEF, end-to-end narrow-band DDOR and end-to-end of wideband DDOR (for BepiColombo)

slide-13
SLIDE 13

Full interoperability validation [4]

Validation with BITTT

 I/F validation

  • Validation of RDEF format  On-going
  • Validation of TDM  On-going
  • Validation of OEM  OK

 Functional validation

  • Validation of wideband DDOR  Not exercised yet
  • Validation of low SNR  Not exercised yet

 End-to-end validation

  • Validation of OD solutions  Not done yet (for narrowband DDOR)
  • Validation of OD solutions  Not done yet (for wideband DDOR)

Priority: validate RDEF, end-to-end narrow-band DDOR and end-to-end of wideband DDOR (for Chang’E3)