Union Culvert Spray Lining Hydraulic Engineering Conference - - PowerPoint PPT Presentation

union culvert spray lining
SMART_READER_LITE
LIVE PREVIEW

Union Culvert Spray Lining Hydraulic Engineering Conference - - PowerPoint PPT Presentation

Union Culvert Spray Lining Hydraulic Engineering Conference September 8, 2011 Anthony C. Turowski, E.I. Overview Purpose & Need of Project Scoping & Funding Plan Development Construction Comparison w/ Field


slide-1
SLIDE 1

Union Culvert Spray Lining

Hydraulic Engineering Conference September 8, 2011 Anthony C. Turowski, E.I.

slide-2
SLIDE 2

Overview

  • Purpose & Need of Project
  • Scoping & Funding
  • Plan Development
  • Construction
  • Comparison w/ Field Paving
slide-3
SLIDE 3

Purpose & Need

  • US 33 corrugated metal pipes

corroding

  • Repair needed to maintain

lifespan

  • This section built in 1986
  • All sites are less than 10’ span.
slide-4
SLIDE 4

Scoping

  • D6 Bridge Inspectors tasked with

finding locations

  • Location Criteria :
  • Surficial Rust Present, but

Structurally Sound

  • Little dewatering and MOT

required

  • No additional r/w or complex

waterway permits required

  • Project Scoped: 2/5/10
  • File Date: 3/1/10
slide-5
SLIDE 5

Funding

  • Originally planned as part of the

“Stimulus 2” group of projects

  • Lack of funding delayed the

project for over a year.

  • The project was later programmed

with district funding.

slide-6
SLIDE 6

Plan Development

  • The plan has minimal notes and detail, similar to a resurfacing project.
  • Permitting was the most critical part of the process. Jurisdictional

determinations were required for each site, and an RGP was obtained for two of nine sites on the project.

  • Although the liner itself is not considered to be fill below the OHWM (the pipe is

an existing improvement), the temporary work outside the limits of the pipe IS fill below the OHWM. This is an important distinction for jurisdictional waterways.

  • The Cost estimate was largely provided by material manufacturers.
slide-7
SLIDE 7

Construction

  • Began in August 2011, is currently in progress.
  • Plan was bid at $817,370 vs. the Engineer’s Estimate of $1,175,000.00 (70%).
  • E.B. Miller of Cincinnati was awarded contract.
  • D.A. Van Dam & Associates is the Resin Supplier
  • Don Violet & Jill Kirby are the ODOT project supervisors.
slide-8
SLIDE 8

Equipment

slide-9
SLIDE 9

Cleaning the Pipe

  • Powerwashing and wire brushing are the primary cleaning methods used.
  • Ditch checks are placed downstream of the pipe to contain solids washed out
  • f the pipe.
  • The contractor had issues with keeping material out of the pipe after cleaning

but before the spray application.

  • These sites were selected specifically so they could be constructed in a dry

condition, with minimal dewatering, but there were still issues.

  • Future plans should probably include cofferdams as a pay item, and should be

permitted to allow the use of more intrusive dewatering activities.

slide-10
SLIDE 10

Mixing the Material

slide-11
SLIDE 11

Ventilation

slide-12
SLIDE 12

Ventilation

slide-13
SLIDE 13

Spray Application

slide-14
SLIDE 14

Testing the Thickness

  • Coating Thickness Gage

Retails for $500 - $1000.

  • Calculating yields from the spray

application is contractor’s preferred method of measurement.

slide-15
SLIDE 15

Field Paving with Concrete

Field Paving VS Spray Lining

Spray Lining

  • Avg. Awd of $130/LF
  • Structural Repair
  • Changes hydraulic
  • pening (3” fill in bottom
  • f pipe).
  • Avg. Awd of ~$350/LF
  • Current Spec is for non-

structural repairs.

  • Does not change

hydraulic opening.

slide-16
SLIDE 16

∗ Both the spray lining and field paving unit prices were taken from single projects. I encourage you to contact the manufacturer to verify unit prices for a given site. ∗ District Six has 3 field paving projects scoped for FY 12 through FY 14, additional data will be available after the sale of those projects.

Cost Data Disqualifiers

slide-17
SLIDE 17

Questions/Discussion?