UMATAC Industrial Processes Progress in China Fushun ATP Project - - PowerPoint PPT Presentation

umatac industrial processes progress in china fushun atp
SMART_READER_LITE
LIVE PREVIEW

UMATAC Industrial Processes Progress in China Fushun ATP Project - - PowerPoint PPT Presentation

UMATAC Industrial Processes Progress in China Fushun ATP Project Update Colorado School of Mines 34 th Oil Shale Symposium October 14, 2014 UMATAC Industrial Processes ThyssenKrupp Industrial Solutions A company of ThyssenKrupp Industrial


slide-1
SLIDE 1

ThyssenKrupp Industrial Solutions

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

UMATAC Industrial Processes Progress in China – Fushun ATP Project Update

Colorado School of Mines 34th Oil Shale Symposium October 14, 2014

slide-2
SLIDE 2

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

Agenda

Operation Update

  • Plant is currently producing oil.
  • 40 day run length achieved.
  • Oil quality as per design.

Fushun Project Background

  • Mechanical completion in 2010.
  • First oil in 2013.
  • Continued improvements through 2014.

Technical Challenges

  • Burner fouling.
  • Flue gas cooler fouling.
  • Ash system reliability.
  • New East Open Pit mine.

Page 2

ATP Plant Main Flare Oil Production

slide-3
SLIDE 3

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

FMG ATP Plant Flowsheet

Page 3

MINE & SPENT SHALE DISPOSAL ORE HANDLING FLUE GAS CLEAN‐UP TANK FARM POWER GENERATOR OIL RECOVERY WATER TREATMENT PRODUCT LOAD‐OUT ELECTRICITY SPENT SHALE FEED SHALE SILOS UTILITIES & OFFSITES GAS CYCLONES FLUE GAS COOLER INERT STOCKPILE INERT SILOS COMBUSTION AIR SUPPLY ASH SILOS FRACTIONATION COMB. AIR FAN SCRUBBER STACK ATP PROCESSING FUEL OIL BAGHOUSE NAPHTHA SOUR H2O ATP PROCESSOR FLARE CONTROL SYSTEM STEAM, COOLING WATER RAIL TRANSPORT FUEL OIL

slide-4
SLIDE 4

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

FMG ATP Plant Flowsheet

Page 4

MINE & SPENT SHALE DISPOSAL ORE HANDLING FLUE GAS CLEAN‐UP TANK FARM POWER GENERATOR OIL RECOVERY WATER TREATMENT PRODUCT LOAD‐OUT ELECTRICITY SPENT SHALE FEED SHALE SILOS UTILITIES & OFFSITES GAS CYCLONES FLUE GAS COOLER INERT STOCKPILE INERT SILOS COMBUSTION AIR SUPPLY ASH SILOS FRACTIONATION COMB. AIR FAN SCRUBBER STACK ATP PROCESSING FUEL OIL BAGHOUSE NAPHTHA SOUR H2O ATP PROCESSOR FLARE CONTROL SYSTEM STEAM, COOLING WATER RAIL TRANSPORT FUEL OIL FUEL GAS

slide-5
SLIDE 5

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

ATP Burner Fouling Update

ATP Burners

  • Used vertical retort derived fuel oil from

existing FMG plant.

  • Now using low solids, low water content

ATP produced heavy oil, increasing fuel system reliability. Fouling

  • Determined to be due to exposure of clays

to high temperature in flame (slagging).

  • Proposed solution was to reduce flame

intensity. Solution

  • Automated mechanical cleaning.
  • Installed Big Blasters™ (air cannons).
  • Successful.

Slag build-up

Page 5

slide-6
SLIDE 6

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

ATP Burner Fouling Update

ATP Burners

  • Used vertical retort derived fuel oil from

existing FMG plant.

  • Now using low solids, low water content

ATP produced heavy oil, increasing fuel system reliability. Fouling

  • Determined to be due to exposure of clays

to high temperature in flame (slagging).

  • Proposed solution was to reduce flame

intensity. Solution

  • Automated mechanical cleaning.
  • Installed Big Blasters™ (air cannons).
  • Successful.

Blaster Nozzle

Page 6

slide-7
SLIDE 7

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

Retrofit ATP to Utilize Off Gas

ATP Produced Off Gas

  • Design was to generate 15 MWe of

electricity by burning off gas in internal combustion engines.

  • Generators are not yet commissioned

and gas is being flared. Temporary Use

  • Burn off gas in ATP Processor and

displace coke & heavy oil combustion.

  • Replaced one of three heavy oil

burners with a gas burner.

Page 7

slide-8
SLIDE 8

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

Flue Gas Cooler / Combustion Air Preheater

Flue Gas Cooler

  • Cools flue gas & preheats combustion air.
  • Ammonia and sulphur dioxide in flue gas.
  • Process design exit temperature was 175°C,

reduced to 150°C during detail design. Equipment configuration issues

  • Low tube-wall temperature at cold end.
  • Low tube-side gas velocity.
  • Gas distribution.

Fouling

  • Condensation of water and ammonia salts.
  • Run length initially limited to 7 days, but

now exceeding 40 days. Baghouse Cyclones ATP Processor Flue Gas Cooler

Page 8

slide-9
SLIDE 9

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

COMBUSTION AIR SUPPLY ‐35 to +40°C HOT FLUE GAS 335°C COOLED FLUE GAS 150°C PREHEATED AIR 265°C CYCLONES FLUE GAS COOLER COMB. AIR FAN BAGHOUSE

Tube wall temperatures were below water and ammonia salt condensation temperatures.

Moisture Condensation & Salt Fouling

Page 9

335°C 150°C 35°C 265°C

slide-10
SLIDE 10

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

HOT FLUE GAS 335°C COMBUSTION AIR SUPPLY 80°C COOLED FLUE GAS 180 to 200°C PREHEATED AIR 265°C CYCLONES FLUE GAS COOLER COMB. AIR FAN BAGHOUSE

Increase Tube Inlet Wall Temperature

  • Increased combustion air inlet

temperature to 80°C and reverted to 180°C FG exit temp.

  • Reduced fouling.

Duct installation

Page 10

335°C 180°C 80°C 265°C

slide-11
SLIDE 11

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

Inlet Air Distribution

Inlet air distribution resulted in localized

  • ver-cooling of tubes.

Page 11

335°C 180°C 80°C 265°C

slide-12
SLIDE 12

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

Improved Inlet Air Distribution

Fouling was reduced, and run length increased to over 40 days.

Page 12

335°C 180°C 80°C 265°C

slide-13
SLIDE 13

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

Ash System Reliability

Parallel operating/stand-by conveyor belt lines are installed, but both have similar problems.

  • Complex layout with multiple transfer points.
  • Transfer point chutes are long, with

compound angles and insufficient slope.

  • Oversized water control valves lead to poor

control of ash moistening.

  • Moistened ash is sticky.
  • Belt skirting is insufficient.
  • Ash bins bridge and rat-hole.

Major modification program has started.

Chute modifications

Page 13

Plugged Transfer Chute

slide-14
SLIDE 14

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

West Pit Mine is Closing

  • Pilot testing and design were done on West Pit ore: 7% oil yield, 5% free water.
  • Excellent particulate physical strength.

East Pit Opened – ore grade during early years of mine operation will be low.

  • Operations in 2014 mostly used East Pit ore. 4-5% oil, 5-8% water.
  • Much lower particulate physical strength, resulting in higher fines generation.

Oil Shale Feed Variation

Ash from West Pit Ore Ash from East Pit Ore

Page 14

slide-15
SLIDE 15

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

West Pit Mine is Closing

  • Pilot testing and design were done on West Pit ore: 7% oil yield, 5% free water.
  • Excellent particulate physical strength.

East Pit Opened – ore grade during early years of mine operation will be low.

  • Operations in 2014 mostly used East Pit ore. 4-5% oil, 5-8% water.
  • Much lower particulate physical strength, resulting in higher fines generation.

Oil Shale Feed Variation

Overburden Green Shale Oil Shale Coal

Ash from West Pit Ore Ash from East Pit Ore

Page 15

slide-16
SLIDE 16

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

2014 Operations

FMG is taking a cautious but firm approach to operation in 2014. This year’s targets were to achieve a 30 day run (done) and then a 90 day run. FMG has added a second 30 day run to test reliability improvements. Oil shale throughput is 70 to 80% of design.

Oil Shale and Ash Trains May 2014

Page 16

slide-17
SLIDE 17

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

2014 Operations

July 2014 Start Date Run Length (days) Feed Rate Notes

  • Jan. 2014

7 Inert feed Baghouse bag replacement. April 2014 15 Inert feed Check-out run, refractory dry-out. May 2014 15 Oil Shale 140-170 t/h FG cooler modifications, ash system improvements, Big Blaster installation. July 2014 40 Oil Shale 160-180 t/h (70-80% of design) Successful improvement of plant

  • perability.
  • Oct. 2014

Currently in Operation Oil Shale 160-180 t/h Targeting 30 day run, to be followed by 90 day operation.

Page 17

slide-18
SLIDE 18

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

~ 200,000 tonnes oil shale processed, 70,000 bbls oil produced to date in 2014.

FMG ATP Processor Operating Hours

Page 18

Mechanical completion First

  • il
slide-19
SLIDE 19

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

Oil Shale Operation July 2014

Page 19

slide-20
SLIDE 20

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

Oil Shale Operation July 2014

Temperature Control Feed & Ash System Upsets

Page 20

slide-21
SLIDE 21

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

ATP Operations Video

2014 Video – ATP Commercial Oil Shale Operations (China) View online at UMATAC Industrial Processes Videos

http://youtu.be/XxNLuK6DLuE

Page 21

slide-22
SLIDE 22

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

In 2014, FMG has focused on operating the plant and improving plant reliability. UMATAC and TKIS continue to support FMG’s operating and engineering teams. Reliability improvements are working. Production run length > 40 days achieved. Oil recovery system is working very well. Oil & gas quality meet design expectations. ATP Processor is working well & handling ore much different than design.

Summary

Product oil load-out and future upgrader

Page 22

slide-23
SLIDE 23

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

Questions?

谢谢 Thank You اركش

Page 23

slide-24
SLIDE 24

UMATAC Industrial Processes

A company of ThyssenKrupp Industrial Solutions

Contact Information

UMATAC Industrial Processes Inc. Suite #110, 6835 Railway Street S.E. Calgary, Alberta, Canada T2H 2V6 Telephone: +1-403-910-1000 Facsimile: +1-403-910-1040 email: umatac@thyssenkrupp.com web: www.umatac.ca

Page 24